Carissa P. Sedlacek MANAGER, RESOURCE INTEGRATION AND ANALYSIS Reliability Committee Meeting Forward Capacity Auction #6 (FCA #6) Results Summary MAY 15, 2012 | WESTBOROUGH, MA Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING
Feb 24, 2016
Carissa P. SedlacekM A N A G E R , R E S O U R C E I N T E G R A T I O N A N D A N A L Y S I S
Reliability Committee Meeting
Forward Capacity Auction #6 (FCA #6) Results Summary
M A Y 1 5 , 2 0 1 2 | W E S T B O R O U G H , M A
Stephen J. RourkeV I C E P R E S I D E N T , S Y S T E M P L A N N I N G
2
Highlights
• The sixth Forward Capacity Auction (FCA #6) was held April 2-3 and successfully procured resources to satisfy the region’s Installed Capacity Requirement (ICR) for the 2015/2016 Capacity Commitment Period (CCP)
• Approximately 38,601 MW of qualified resources competed to provide the needed 33,456 MW of capacity (Net ICR)
• Of the qualified new resources, about 84% (or 2,041 MW) of new resources (generation, imports, demand resources) cleared the auction and have a Capacity Supply Obligation (CSO)
• Approximately 1,889 MW of de-list bids submitted were approved. Those not approved and retained for reliability were in the NEMA/Boston load zone
• A dynamic de-list bid for Vermont Yankee (604 MW) was accepted
• The ISO filed results of FCA #6 with FERC on April 30
3
FCA #6 Overview
• There were seven rounds in which Participants could submit bids and offers
• Starting price was $11.446/kW-mo
• Ending price was $3.434/kW-mo
• Cleared MW will receive a prorated payment of $3.129/kW-mo unless they elect to prorate their MW obligation
• FCA #6 results FERC Filing made on April 30 is available at:– http://www.iso-ne.com/regulatory/ferc/filings/2012/apr/er12-___-000_04-30-12_6th_fc
a_results_filing.pdf
• The resource proration election window was April 9-11 and results were provided to Participants (via MIS report) in early May– No resources in the NEMA/Boston load zone were allowed to prorate due to
the fact some resources were retained for reliability
4
FCA #6 Auction Details
• ICR for June 1, 2015 through May 31, 2016 is 34,498 MW– After accounting for 1,042 MW of Hydro-Québec Installed Capacity Credits, 33,456
MW remained to be procured (Net ICR)
• Approximately 38,731 MW of resources qualified to participate in FCA #6 at the time of the Informational Filing – However, due to new resource termination and/or withdrawal from Critical Path
Schedule monitoring, only 38,601 MW of qualified resources actually did participate – Qualified Existing Resources (36,174 MW)
• 32,076 MW of Generating Capacity, including Intermittent*• 315 MW of Import Capacity• 3,783 MW of Demand Resources
– Qualified New Resources (2,427 MW)• New Supply Resources (1,953 MW)
– 133 MW Generating Capacity– 1,820 MW Import Capacity
• New Demand Resources (474 MW)
* Includes new RTEG which receives existing treatment in the auction
5
FCA #6 Auction Details, cont.
• Approximately 617 MW (uncapped by Maximum Capacity Limit (MCL) and Real-Time Emergency Generation (RTEG)) remained at the floor price– Existing Resources (34,285 MW)*
• 30,954 MW of Existing Supply Resources– 30,678 MW of Generation Capacity– 276 MW of Import Capacity
• 3,331 MW of Existing Demand Resources– New Resources (2,041 MW)
• New Supply Resources (1,727 MW)– 79 MW of Generation Capacity– 1,648 MW of Import Capacity**
• New Demand Resources (314 MW)
• Approximately 36,309 MW (capped by RTEG) total capacity was used to calculate the effective payment rate
* Accounts for Non-Price Retirements and includes new RTEG ** Capped by Interface Limits
6
New Capacity Resources by State
CT16%
MA46%
ME7%
NH5%
RI17%
VT9%
Demand Resources*314 MW
Generation79 MW
* Includes 8% T&D Gross-up and new RTEG
MA28%
ME 60%
NH12%
7
On Peak 65%
Real Time21%
Real Time EG1%
Seasonal Peak 13%
New Demand Resources by Type314 MW Total
Includes approximately 247 MW of New Energy Efficiency Projects
8
New Generation by Type79 MW Total
Combined Cycle13%
Hydraulic Turbine
14%
Photovoltaic1%
Wind Turbine72%
9
Trends in New Capacity Resources
FCA #1 FCA #2 FCA #3 FCA #4 FCA #5 FCA #6FCA New Cleared Capacity
0
500
1000
1500
2000
2500
3000
3500
Generation Imports Demand Response
MW
10
FCA #6 De-list Details
• A total of 191 de-list bids (approximately 1,968 MW) were received from resources in all six New England states. Approximately 96% were accepted– Permanent, static, exports and administrative export bids were submitted
prior to the auction at prices greater than 0.8 X Cost of New Entry (CONE)• 10 resources submitted (approximately 351 MW)
– All 351 MW were accepted– Additional static de-list bids were submitted by the ISO on behalf of the
Participant due to the inability to qualify winter MW (“low winter flag”)• Submitted for 31 resources representing 122 MW (22 MW in NEMA)
– All 122 MW were accepted– Dynamic de-list bids are submitted during the auction at prices less than 0.8 X
CONE (or below $4.758/kW-mo) • 150 dynamic de-list bids (approximately 1,495 MW)
– 1,416 MW accepted– 79 MW denied (6 dynamic de-list bids in the NEMA/Boston load zone)
11
Approved Submitted De-list Bids by State
1,889 MW Total
CT29%
Imports2%
MA24%
ME6%
NH2%
RI3%
VT34%
12
FCA #6 De-list Details, cont.• A dynamic de-list bid for Vermont Yankee (604 MW) was accepted for FCA #6
based on completion of various system upgrades in MA and VT that resolve identified reliability concerns
– A dynamic de-list bid was also submitted in FCA #4 & 5 but the resource was retained for reliability in those auctions
• De-list bid submittal trends are starting to emerge– AES Thames
• Cleared a Dynamic De-list bid for the unit in FCA #5 & 6 – West Springfield 3
• Cleared a Dynamic De-list bid for the unit FCA #5• Cleared a Static De-list bid for the unit FCA #6
– Bridgeport Harbor 2• Cleared a Dynamic De-list bid for the unit in FCA #4, 5, & 6
– Somerset Jet 2• Cleared a Static De-list bid for the unit in FCA #3, 4, & 5• Cleared a Permanent De-list bid for the unit in FCA #6• Retired effective 4/20/2012
– Somerset 6• Cleared a Static De-list bid for the unit in FCA #1, 2, 3, 4, & 5• Cleared a Permanent De-list bid for the unit in FCA #6• Retired effective 4/18/2012
• Resources are also exiting the market via Annual Reconfiguration Auctions and Bilaterals
13
Example – Real Time Emergency GenerationChange in Capacity Supply Obligations (CSOs)
0
100
200
300
400
500
600
700
800
900
1000
FCA 1 FCA 2 FCA 3 FCA 4 FCA 5 FCA 6
FCA Cleared CSO Latest CSO
14
Resources Retained for Reliability
• Few resources retained for reliability previous auctions– Norwalk Harbor Unit 1 in FCA #1
• Unit #2 was later allowed to de-list– Salem Harbor Units 3 & 4 for FCA #3, 4 and 5
• Area transmission upgrades ongoing• Restudy results for the fourth Capacity Commitment Period being
discussed later today– Vermont Yankee for FCA # 4 and 5
• Area transmission upgrades ongoing• Restudy results for the fourth Capacity Commitment Period being
discussed later today
• These resources were retained for local reliability reasons
15
0
500
1,000
1,500
2,000
2,500
3,000
FCA #1 FCA #2 FCA #3 FCA #4 FCA #5 FCA #6
DR Generator Import
Meg
awatt
sTrends in De-list Bids Submitted
79 MW Rejected604 MW
Rejected
1,191 MW Rejected581 MW
Rejected
0 MW Rejected
330 MW Rejected
16
Resources Retained for Reliability in FCA #6
• There were six dynamic de-list bids (79 MW) rejected– All in the NEMA/Boston load zone– Five demand resources– One partial de-list from the Kendall Steam generating facility
• Restudy of these rejected de-list bids will begin this summer with the hope of allowing these resources to de-list based on changes in load forecast and other assumptions
Price ID Resource Name De-list BidAmount (MW) Round Resource
Type
$4.577 37871 RTDR_50017_Boston (7507) -38.866 5 DR$4.577 37040 KENDALL STEAM -27.379 5 GEN$4.292 37997 RTEG_50017_North Shore (7508) -4.830 5 DR$4.291 37986 RTDR_RTEG_50689_North Shore (7508) - Grp A -2.526 6 DR$4.291 17301 RTEG_50689_North Shore (7508) -3.500 6 DR$3.863 37991 RTEG_50017_Boston (7507) -1.512 6 DR
17
Next Steps for the Rejected De-list Bid
• A presentation to the RC is expected to be made in June to discuss in detail the resources that were retained for reliability (de-list bid rejection)
• In accordance with Planning Procedure No. 10, Section 7.5.1., an advisory RC vote regarding concurrence with how the analyses for the rejected De-list Bids was conducted is required and expected in June – “…The Reliability Committee shall provide formal input and advice to the ISO
with regard to rejected de-list bids after the relevant FCA through an advisory vote….”
• Pursuant to Market Rule 1, Section III.13.2.5.2.5.1(a)(ii), these resources will continue to be re-evaluated prior to June 1, 2014 to determine if it may be allowed to de-list
Reliability Committee Meeting
Forward Capacity Auction #6 (FCA #6) Results Summary – Appendix
M A Y 1 5 , 2 0 1 2 | W E S T B O R O U G H , M A
19
Summary of Auction Rounds withExcess Supply and Price Changes
Round Start Price End Price Delta $ Excess Start1 Excess End1 Delta MW
1 11.446 6.868 4.578 4656.835 4372.869 283.966
2 6.868 5.723 1.145 4372.869 4280.766 92.103
3 5.723 5.151 0.572 4280.766 4197.273 83.493
4 5.151 4.578 0.573 4197.273 4151.505 45.768
5 4.578 4.292 0.286 4151.505 2956.207 1195.298
6 4.292 3.863 0.429 2956.207 2840.203 116.004
7 3.863 3.434 0.429 2840.203 2821.658 18.545
1capped by Import Interface Limits and MCL
20
Results of New England’s FCA #6
Price at end of auction:$3.434/kW-Mo
(Floor price: 0.6 X CONE)
Resources Capped by RTEG 36,309 MW
Need in 2015 (NICR):
33,456 MW
Effective Payment Rate ($/kW-Mo):
$3.129
RTEG:$3.044
Price at beginning of auction:
$11.446/kW-Mo(2 X CONE)
On Peak 1,288 MW
Seasonal Peak 355 MW
Real Time 1,385 MW
Real Time EG 617 MW
New Resources: 2,427 MW
Existing Resources:36,174 MW
Demand: 474 MW
Generating:32,076 MW
Imports:315 MW
Imports:1,820 MW
Demand:3,783 MW
Generating:133 MW
Excess Capacity:2,853 MW
(Total cleared minus net ICR capped by
RTEG)
Capacity Zones: One
No Price Separation
Qualified Resources Entering the Auction:
38,601 MW
Existing:30,678 MW
New:79 MW
Generating Resources:30,757 MW
Existing:3,331 MW
New:314 MW
Demand Resources:3,645 MW
Existing:276 MW
New:1,648 MW
Cleared Imports:1,924 MW
Import: 39 MW
Demand: 452 MW
Generating: 1,398 MW
MW from existing resources requesting
to de-list 1,968 MW
Rejected:79 MW
Approved: 1,889 MW
Resources cleared (uncapped) in the
auction at the floor price:
36,326 MW