Nuclear Infrastructure Development in IndonesiaAdiwardojo

National Nuclear Energy Agency of the Republic of Indonesia

Presented at IAEA Technical Meeting on the Introduction of Nuclear Power Programme: Management and Evaluation of a National Nuclear Infrastructure , 8-11 February 2011, IAEA, Vienna

Page 2: Adiwardojo Indonesia

1. Introduction

• Indonesia has for a long period planned for the introduction of nuclear power.

• Act No 10 of 1997 on Nuclear Energy. This is the primary legislation in Indonesia

• Act No. 17 of 2007 on Long-Term National Development Plan of Indonesia for 2005 to 2025.This is the basis act of establishing long term commitment for the use of nuclear energy to meet national energy demand

• Indonesia performed self-assessment on National Nuclear Infrastructure prior to Integrated Nuclear Infrastructure Review and IAEA-INIR mission was held in November 2009

• Action Plan Phase 2 status IFR have been prepared

Page 3: Adiwardojo Indonesia

FOUNDATION PHYLOSOPHY

• APPLICATION AND DEVELOPMENT IN NUCLEAR SCIENCE & TECHNOLOGY IS FOR PEACEFUL USES ONLY

• SAFETY & SECURITY IS THE PRIME CONSIDERATION

• DEMAND DRIVEN AND STAKEHOLDER SATISFACTION

Page 4: Adiwardojo Indonesia

STATUS OF INDONESIA : INTERNATIONAL CONVENTION ON NUCLEAR ENERGY

Signed (1997)Bilateral cooperation and supply agreement(s)11.

Signed (1997)Supplementary Compensation for Nuclear Damage10.

Signed (1997)Protocol to Amend the Vienna Convention9.

Signed (1997)Joint Convention on the Safety of Spent FuelManagement and the Safety of Radioactive WasteManagement

8.

Under process for ratification Comprehensive Nuclear Test-Ban Treaty (CTBT)7.

Ratified by Presdeg No.106 Th. 2001Convention on Nuclear Safety6.

Ratified: Act No. 9 Th. 1997 Treaty on the Southeast Asia Nuclear Weapon FreeZone

5.

Ratified by Presdeg No. 82 Th. 1993Convention on Assistance in the Case of a NuclearAccident or Radiological Emergency

4.

Ratified by Presdeg No. 81 Th. 1993Convention on Early Notification of A Nuclear Accident3.

Ratified by Presdeg No. 49 Th. 1986Convention on Physical Protection of Nuclear Materialand its Amendment

2.

Ratified: Act No. 8 Th. 1978signed Signed

Non-Proliferation Treaty (NPT)- Safeguard Agreement with IAEA- Additional Protocol to Safeguards

1.

STATUSINTERNATIONAL CONVENTIONSNo.

Page 5: Adiwardojo Indonesia

2. Role of IAEA

Standards and Guidance

Reviews and Services

Knowledge Networks

Forum for communicating, increasing transparency, sharing lessons learned

Technical Cooperation

Capacity Building

Page 6: Adiwardojo Indonesia

IAEA document for newcomer • “Potential for Sharing Nuclear Power Infrastructure

between Countries”, TECDOC-1522, October 2006• “Managing the First Nuclear Power Plant Project”,

TECDOC-1555, May 2007• “Considerations to Launch a Nuclear Power Programme”

,GOV/INF/2007/2 , March 2007• “Milestones in the Development of a National

Infrastructure for Nuclear Power, NE Series Guide NG-G- 3.1, September 2007

• INSAG-22 on Safety Infrastructure, 2008• Evaluation of the Status of National Nuclear

Infrastructure Development, NE Series No. NG-T-3.2, 2008

• Integrated Nuclear Infrastructure Review (INIR) Missions, Guidance on Preparing and Conducting INIR Missions, 2009

Page 7: Adiwardojo Indonesia

Managing the first NPPBasic consideration in Managing the First NPP

• National and International Framework

• Nuclear Safety• Nuclear power supply market• Financial market• Economics of nuclear power• Safeguards• Security of nuclear material

and other radioactivity• Management system• Regional and interregional

cooperation• IAEA Assistance

Page 8: Adiwardojo Indonesia

Managing the first NPP

Pre-Project Stage

• National energy supply planning• Nuclear power system planning• Activities related with treaties,

convention and agreement• National infrastructure• National participant plan• Site survey• HRD Programme

Page 9: Adiwardojo Indonesia

3. Evaluation of the status of nuclear national infrastructure

• In order to assess status of nuclear national infrastructure a self-assessment using milestone approach is used

• The status (Nov 2009) is shown as Figure 1• The nuclear national infrastructure is developed in three phase with

each milestone:• First phase: consideration before decision to launch a nuclear power

program with milestone 1 of ready to make knowledgeable commitment to nuclear power program

• Second phase: preparatory work for the construction of a NPP after a policy decision with milestone 2 ready to invite bid

• Thirds phase: activities to implement a first NPP with milestone 3ready to commission and operate the first NPP

Page 10: Adiwardojo Indonesia

Fig 1: Nuclear Infrastructure Development Program (Nov 2009)

Phase 1

Consideration before a decision to

launch a nuclear power programme

is taken

Phase 2

Preparatory work for the construction

of a NPP after a policy decision has

been taken

Phase 3

Activities to implement a first

NPP

Phase 4

Maintenance and continuous

infrastructure improvement

Pre Project Project Decision Making

Construction Operation/ decommissioning

Nulear power option included

within the national energy

strategy

Milestone 1Ready to make a knowledgeable commitment to a nuclear programme

Milestone 2Ready to invite bids for the first NPP

Milestone 3Ready to commission and operate the first NPP

10-15 years

Pres.Reg. 5/2006

Act. 17/2007

Feasibility study Bidding process Commissioning

Infr

astr

uctu

re

Dev

elop

men

t P

rogr

am1st

NP

P

Pro

ject

Status NPP Dev

Page 11: Adiwardojo Indonesia

Evaluation of the status of nuclear national infrastructure

• Key Infrastructure Issues to be evaluated

• National position• Nuclear safety• Management• Funding and financing• Legislative framework• Safeguards• Regulatory framework• Radiation protection• Electrical grid• Human resources development

• Stakeholder involvement• Site and supporting facilities• Environmental protection• Emergency planning• Security and physical

protection• Nuclear fuel cycle• Radioactive waste• Industrial involvement• Procurement

Page 12: Adiwardojo Indonesia

Integrated Nuclear Infrastruktur Review (INIR)

• INIR mission is conducted in order to provide external peer review by IAEA

• INIR Mission is implemented at different phases of the infrastructure development of Member state

• INIR Mission phase 1 has been done in 23-27 November 2009

Page 13: Adiwardojo Indonesia

Integrated Nuclear Infrastruktur Review (INIR)

The mission utilized the following techniques:

a) Study of documents, performed in two stages (i) prior to the mission, as part of preparation and (ii) during the mission. The documents include:

• Self-Assessment Report, 2009 October;• Indonesian strategy documents for peaceful utilization of atomic energy;• Atomic Energy Law and related decrees and regulations;• Formulation of sustainable energy development strategies under

framework of climate change, IAEA/RCA Project (RAS/0/045), BATAN, 2008

b) Interviews to gather information through discussions with representatives of the counterpart organizations.

Page 14: Adiwardojo Indonesia

Result of Nuclear Infrastructure Review

• Indonesia is planning in earnest for the introduction of nuclear power.

• Two key organizations have been formed: BATAN as promoting organization that in charge of development work and preparations for nuclear energy, and BAPETEN, the regulatory body.

• No decision has, however, yet been made on what organization will be responsible for owning and operating the nuclear power plants.

• Several options are considered.

Page 15: Adiwardojo Indonesia

Result of Nuclear Infrastructure Review

• There is a national consensus in principle that nuclear energy should be a part of the energy portfolio in Indonesia ( Act Number 17 Year 2007 )

• There is good progress in the development of the national infrastructure in many areas, especially nuclear law, safety regulations, grid, human resources development, emergency planning, environmental protection, fuel cycle and waste management.

Page 16: Adiwardojo Indonesia

Result of Nuclear Infrastructure Review

• Less progress has been made in those areas, which will require the involvement of the owner/operator of the nuclear power plants, e.g. management, funding and financing and industry involvement.

• The activities for stakeholder involvement will in particular require significant improvement.

• The infrastructure activities performed by different organisations have so far been informally coordinated;

• it would be advantageous to introduce formal steering and coordination of the future activities.

Page 17: Adiwardojo Indonesia

Result of Nuclear Infrastructure Review

Based on these findings, the team recommends that in order to implement the provisions of Act No. 17 of 2007 and Presidential Regulation decree No. 5 of 2006 Indonesia will need to:

• Clarify the planning and decisions needed for a nuclear power program and identify owner/operator

• Create an inter-agency team to oversee and steer infrastructure development work

• Develop a detailed action plan for infrastructure development for phase 2 (until invitation to bid is issued) as part of longer term planning

Page 18: Adiwardojo Indonesia

Result of Nuclear Infrastructure Review

• Develop a detailed action plan for infrastructure development for phase 2 (until invitation to bid is issued) as part of longer term planning

• Develop a comprehensive program for stakeholder (incl. public) involvement

• Expand the existing national policy and strategy for national industry involvement to also include the involvement for constructing and operating nuclear power plants

• Enhance international/regional/bilateral cooperation

Page 19: Adiwardojo Indonesia

No. INFRASTRUCTURE STATUS OF PHASE 11. National Position NEPIO not yet establish

2. Nuclear Safety No actions needed

3. Management NEPIO not yet establish

4. Funding and Financing Minor actions needed

5. Legislative Framework Minor actions needed

6. Safeguards No actions needed

7. Regulatory Framework No actions needed

8. Radiation Protection No actions needed

9. Electric Grid No actions needed

10. Human Resource No action needed

11. Stakeholder Involvement Well-structured programme needs to establihed

12. Site and Supporting facility Minor actions needed

13. Environmental Protection No actions needed

14. Emergency Planning No actions needed

15. Security and Physical Protection No actionsw needed

16. Nuclear Fuel Cycle No actions needed

17. Radioactive Waste No actions needed

18. Industrial Involment Minor actions needed

19. Procurement No actions needed

Recommendations and Suggestions

Page 20: Adiwardojo Indonesia

4. Action Plan Phase 1 and 2• Action Plan Phase 1

-National Position : Indonesian NEPIO in Phase 2- Management : NEPIO Programme in Phase 2- Stakeholder Involvement : Public Information and Education will be carried out continuously

• Action Plan Phase 2- Programme A :Responsibility Institution : National Nuclear

Energy Agency (BATAN)- Programme B : Responsibility Institution : Nuclear Energy

Regulatory Agency (BAPETEN) - Programme C : Responsibility Institution : Ministry of Energy and

Mineral Resources, Ministry of Industry, Ministry of Environment, Electric State Own Company (PT PLN), etc

Page 21: Adiwardojo Indonesia

Programme ANo, INFRASTRUCTURE 2010 *) 2011 2012 2013 2014

1 Nuclear Safety

2 Socialization on Utilization of NPP Note:

A. Public acceptance measures Acceleration Program 

A. Stakeholder Involvement Participation Funded by PLN

A. Involvement of people surrounding site candidate  RKA‐KL  ***)

3 Feasibility Study

A. Site and supporting facilities 

‐ Bangka Belitung

‐ Banten

‐ Muria

A. Non Site 

‐ Pre Feasibility Study

‐ Feasibility Study **) **)

4 Nuclear Fuel Cycle 

A. Uranium deposit exploration

A. Thorium deposit exploration

A. Nuclear Fuel element Fabrication Technology

5 Radioactive Waste Management

6 Environment (including Marine Radioecology)

Page 22: Adiwardojo Indonesia

Programme B

No. Activities 2010 2011 2012 2013 2014

1 Nuclear Safety

2.  Legislative Framework

3. Regulation Framework

4. Safeguard

5. Radiation Protection

6. Emergency Planning

7. Security & Physical Protection

Page 23: Adiwardojo Indonesia

Programme CNo. Activities 2010 2011 2012 2013 2014

1 National Position *

2.  Management *

3. Funding & Financing*

4. Electrical Grid**

5. Human Resources Development***

6. Stakeholder Involvement*

7. Environment Protection****

8. Industrial Involvement*****

9. Procurement*

Page 24: Adiwardojo Indonesia

5. ConclussionIndonesia has done extensive preparatory work on most infrastructure issues that would allow the country to make decision to further consider introduction of nuclear power, i.e. to go from phase 1 to phase 2 in Milestone methodology.

It can be suggested that some issues mainly connected to the responsibilities of the owner/operator of the nuclear power plant, still will require further work, most of which can be performed in parallel during phase 2.