Rekap (RAB )REKAPITULASI RENCANA ANGGARAN BIAYA

Kegiatan: Pembangunan Embung Dan Bangunan Penampung Air LainnyaPekerjaan: Pembangunan Embung Lurah Sarai Sungai JamburLokasi: Kecamatan IX Koto Sungai Lasi Kabupaten SolokTahun Anggaran: 2013

NOU R A I A NJUMLAHHARGA

APEKERJAAN PERSIAPANRp3,000,000.00BPEKERJAAN JALANRp146,489,357.00CPEKERJAAN EMBUNGRp681,256,558.00

SUB-TOTAL Rp830,745,915.00HPSRp1,000,000,000.00PPN 10% Rp83,074,591.50SELISIHRp86,180,000.00TOTAL Rp913,820,506.50PERSENTASE91.38%DIBULATKAN .Rp913,820,000.00PENURUNAN8.62%TerbilangRp804,161,600.00Rp20,104,040.00(.)109658400Baso, 21 Mei 2013Baso, 21 Mei 2013Penawar BoronganPenawar BoronganCV. MINANK'S 89CV. MINANK'S 890ttdttd0BAHRUL ULUMBAHRUL ULUMDirekturDirektur

RABDAFTAR RENCANA ANGGARAN BIAYA (RAB)Kegiatan: Pembangunan Embung Dan Bangunan Penampung Air LainnyaPekerjaan: Pembangunan Embung Lurah Sarai Sungai JamburLokasi: Kecamatan IX Koto Sungai Lasi Kabupaten SolokTahun Anggaran: 2013

NOU R A I A NSATUANVOLUMEH. SATUANJ. HARGATOTAL HARGA( Rp )( Rp )( Rp )

APEKERJAAN PERSIAPAN830,745,915.001001Pengukuran kembali / uitzettenLs1.00Rp2,000,000.00Rp2,000,000.00830,745,915.001002Pengujian Material Pasir dan KerikilLs1.00Rp500,000.00Rp500,000.00830,745,915.001003Plank Proyekbh1.00Rp500,000.00Rp500,000.00830,745,915.00100Rp3,000,000.00830,745,915.00100BPEKERJAAN JALAN830,745,915.001001Galian Untuk Pembentukan Badan Jalanm32,576.11Rp42,200.00Rp108,711,842.00830,745,915.001002Timbunan Sirtu di Datangkan dan dipadatkan untukm3356.65Rp89,100.00Rp31,777,515.00830,745,915.00100Untuk Badan Jalan830,745,915.001003Gorong - Gorong DN 80 cmUnit2.00Rp3,000,000.00Rp6,000,000.00830,745,915.00100Rp146,489,357.00830,745,915.00100CPEKERJAAN EMBUNG830,745,915.001001Galian tanah biasam32,100.40Rp42,200.00Rp88,636,880.00830,745,915.001002Pasangan batu kali 1 : 4m3303.30Rp594,500.00Rp180,311,850.0034,727,850.00830,745,915.001003Plesteran camp. 1 : 3 m2600.00Rp48,700.00Rp29,220,000.00830,745,915.001004Pembesiankg9,525.20Rp22,900.00Rp218,127,080.0095,252,000.00830,745,915.001005Bekistingm2312.24Rp94,500.00Rp29,506,680.00830,745,915.001006Beton cor camp. 1 : 2 : 3m375.26Rp886,800.00Rp66,740,568.00830,745,915.001007Pipa GI DN 100 (panjang 27,00 m')LsLsRp54,000,000.00Rp54,000,000.00830,745,915.001008Dop Pipa GI DN 100 (2 buah)LsLsRp2,000,000.00Rp2,000,000.00830,745,915.001009Timbunan kembali bekas galianm3905.80Rp10,500.00Rp9,510,900.00830,745,915.0010010Pekerjaan Gebalan Rumputm2239.00Rp13,400.00Rp3,202,600.00830,745,915.00100Rp681,256,558.00830,745,915.00100

HARSATPEK. Sungai JamburDAFTAR HARGA SATUAN PEKERJAANKegiatan: Pembangunan Embung Dan Bangunan Penampung Air LainnyaPekerjaan: Pembangunan Embung Lurah Sarai Sungai JamburLokasi: Kecamatan IX Koto Sungai Lasi Kabupaten SolokTahun Anggaran: 2013

HARGANOU R A I A NSATUANSATUANKET( Rp )1Pengukuran kembali / uitzettenlsRp2,000,000.002Pengujian Material Pasir dan KerikillsRp500,000.003Plank ProyekbhRp500,000.004Galian tanah biasam3Rp42,200.005Galian tanah kerasm3Rp56,200.006Galian tanah berbatum3Rp84,400.007Memecah batu besar (min dia 0.80 m)m3Rp172,400.008Bongkaran Pas. Lamam3Rp125,400.009Timbunan tanah kembalim3Rp10,500.0010Timbunan tanah didatangkanm3Rp18,500.0011Timbunan Sirtu Didatangkan dan Dipadatkanm3Rp89,100.0012Pasangan batu kali 1 : 3 m3Rp634,100.0013Pasangan batu kali 1 : 4 m3Rp594,500.0014Pasangan batu kali 1 : 4 (Batu bekas Memecah batu)m3Rp507,800.0015Plesteran 1 : 3m2Rp48,700.0016Siaran 1:2m2Rp36,300.0017Bronjong dengan kawat digalvano 4 mmm3Rp461,200.0018Cetakan beton / bekistingm2Rp94,500.0019Pembesian dengan besi polos atau ulirkgRp22,900.0020Beton 1 : 3 : 5 m3Rp732,500.0021Beton 1:2:3m3Rp886,800.0022Pengecatan dengan cat minyak setara "Platon"m2Rp31,600.0023Pipa GI DN 100m1Rp2,000,000.0024Dop Pipa GI DN 100bhRp1,000,000.0025Gorong - GorongUnitRp3,000,000.00

HARSATMAT. Sungai JamburDAFTAR HARGA SATUAN UPAH DAN BAHANKegiatan: Pembangunan Embung Dan Bangunan Penampung Air LainnyaPekerjaan: Pembangunan Embung Lurah Sarai Sungai JamburLokasi: Kecamatan IX Koto Sungai Lasi Kabupaten SolokTahun Anggaran: 2013

IUPAH :HARGANOU R A I A NSATUANSATUANKETERANGAN( Rp )

1Pekerja hariRp54,000.002MandorhariRp69,660.003Tukang BatuhariRp69,660.004Tukang BesihariRp69,660.005Tukang KayuhariRp69,660.006Tukang Anyam bronjonghariRp69,660.007Tukang CathariRp69,660.008Kepala TukanghariRp85,320.00

IIBAHAN :HARGA (Rp)JUMLAHQUARY /BATAS AKHIRTRANSPORTASI DENGANHARGANOJENIS BAHANSATUANINSERTDENGAN KEND.MANUSIAJARAKSATUANKETERANGAN( Rp )RODA 6( Rp )( Km )( Rp )( Rp )

1Batu kalim3Rp55,000.00Rp10,000.00Rp5,000.000,100-0,200Rp70,000.002Pasir pasanganm3Rp50,000.00Rp10,000.00Rp5,000.000,100-0,200Rp65,000.003Pasir betonm3Rp50,000.00Rp10,000.00Rp5,000.000,100-0,200Rp65,000.004Kerikil betonm3Rp60,000.00Rp10,000.00Rp5,000.000,100-0,200Rp75,000.005Sirtum3Rp60,000.00Rp10,000.00Rp5,000.000,100-0,200Rp75,000.006Besi betonkgRp8,000.00Rp100.000,100-0,200Rp8,100.007Kawat betonkgRp20,000.000,100-0,200Rp20,000.008Kawat bronjongkgRp15,000.000,100-0,200Rp15,000.009Paku biasakgRp20,000.000,100-0,200Rp20,000.0010Semen @ 50 kg kgRp53,000.00Rp1,000.000,100-0,200Rp54,000.0011Kayu kls IV (kayu bekisting)m3Rp1,300,000.00Rp150,000.00Rp50,000.000,100-0,200Rp1,500,000.0012Kayu Baniom3Rp2,500,000.00Rp150,000.00Rp50,000.000,100-0,200Rp2,700,000.0013Pipa GI DN 100(panjang 27,00 m')lsRp50,000,000.00Rp3,500,000.00Rp500,000.000,100-0,200Rp54,000,000.0014Dop Pipa GI DN 100 (2 buah)lsRp1,500,000.00Rp350,000.00Rp150,000.000,100-0,200Rp2,000,000.0015Gebalan Rumputm2Rp7,500.000,100-0,200Rp7,500.0016Bambum1Rp2,000.000,100-0,200Rp2,000.001718

ANALISA.Sungai JamburDAFTAR ANALISA HARGA SATUAN PEKERJAANKegiatan: Pembangunan Embung Dan Bangunan Penampung Air LainnyaPekerjaan: Pembangunan Embung Lurah Sarai Sungai JamburLokasi: Kecamatan IX Koto Sungai Lasi Kabupaten SolokTahun Anggaran: 2013

JENIS PEKERJAAN:PEMBERSIHAN LAPANGANSATUAN :M2 ANALISA :HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari0.7500Rp54,000.00Rp40,500.002Mandorhari0.0250Rp69,660.00Rp1,741.50

JUMLAHRp42,241.50Keuntungan ( * )0.0Harga satuanRp42,241.50Untuk 1 m2 (dibulatkan)Rp42,200.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN:GALIAN TANAH BIASASATUAN :M3SATUAN :A.1HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari0.7500Rp54,000.00Rp40,500.002Mandorhari0.0250Rp69,660.00Rp1,741.50

JUMLAHRp42,241.50Keuntungan ( * )0.0Harga satuan (dibulatkan)Rp42,200.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN:GALIAN TANAH KERASSATUAN :M3ANALISA :A.3HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari1.0000Rp54,000.00Rp54,000.002Mandorhari0.0330Rp69,660.00Rp2,298.78

JUMLAHRp56,298.78Keuntungan ( * )0.0Harga satuan (dibulatkan)Rp56,200.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN:GALIAN TANAH BERBATUSATUAN :M3ANALISA :A.3HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari1.5000Rp54,000.00Rp81,000.002Mandorhari0.0500Rp69,660.00Rp3,483.00

JUMLAHRp84,483.00Keuntungan ( * )0.0Harga satuan (dibulatkan)Rp84,400.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN: MEMECAH BATU BESAR (MIN DIAMETER ( 0,80 m) SATUAN :M3ANALISA :C.1HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari3.0000Rp54,000.00Rp162,000.002Mandorhari0.1500Rp69,660.00Rp10,449.00

JUMLAHRp172,449.00Keuntungan ( * )0.0Harga satuan (dibulatkan)Rp172,400.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN:BONGKARAN PAS LAMASATUAN :M3ANALISA :L 4HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari2.0000Rp54,000.00Rp108,000.002Mandorhari0.2500Rp69,660.00Rp17,415.00

JUMLAHRp125,415.00Keuntungan ( * )0.0Harga satuan (dibulatkan)Rp125,400.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN:URUGAN TANAH KEMBALISATUAN :M3ANALISA :A.1HARGAJUMLAHNOURAIANSATUANVOLUMESATUANHARGA( Rp )( Rp )

ATENAGA KERJA1Pekerjahari0.1880Rp54,000.00Rp10,152.002Mandorhari0.0060Rp69,660.00Rp417.96

JUMLAHRp10,569.96Keuntungan ( * )0.0Harga satuanRp10,500.00( * ) Keuntungan Maximum 10 %

JENIS PEKERJAAN:TANAH DIANGKUT SEJAUH