August 2017 UPDATED PROJECT DESCRIPTION Pikangikum Distribution Line Project REPORT Project Number: 1657738 Distribution: 1 e-copy - Wataynikaneyap Power L.P. 1 e-copy - Ministry of Natural Resources and Forestry 1 e-copy - Golder Associates Ltd. Submitted to: Wataynikaneyap Power L.P.
67
Embed
1657738-R-Rev0-2017Aug24-PD-Pikangikum Distribution Line ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
August 2017
UPDATED PROJECT DESCRIPTION
Pikangikum Distribution Line Project
RE
PO
RT
Project Number: 1657738
Distribution:
1 e-copy - Wataynikaneyap Power L.P. 1 e-copy - Ministry of Natural Resources and Forestry 1 e-copy - Golder Associates Ltd.
Submitted to:
Wataynikaneyap Power L.P.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
4.1.1 Ministry of Natural Resources and Forestry Class Environmental Assessment for Resource Stewardship
and Facility Development ............................................................................................................................. 5
4.1.2 Ministry of Natural Resources and Forestry Class EA for Provincial Parks and Conservation Reserves .... 5
4.2 Canadian Environmental Assessment Act ......................................................................................................... 5
7.1 Air Quality and Climate .................................................................................................................................... 10
7.5 Land and Resource Use .................................................................................................................................. 14
8.0 EFFECTS ASSESSMENT AND MITIGATION ............................................................................................................. 15
8.2 Parks and Protected Areas .............................................................................................................................. 18
8.2.1 Study Areas ............................................................................................................................................... 18
8.3 Species at Risk ................................................................................................................................................ 31
8.4 Built Heritage Resources and Cultural Heritage Landscapes Assessment...................................................... 32
8.4.1 Study Area ................................................................................................................................................. 34
8.5.1 Study Area ................................................................................................................................................. 43
Table 2: Heritage Resources Criteria and Indicators ............................................................................................... 34
Table 3: Potential Effects, Mitigation and Residual Effects for the Environment on the Project .............................. 40
Table 4: Archaeological Resources Criterion, Rationale and Indicators .................................................................. 42
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 i
Table 5: Potential Effects, Mitigation and Net Effects for the Environment on the Project ....................................... 47
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation ....................... 50
Table 7: Summary of Potential Permits and Approvals from Provincial and Federal Agencies and Other Organizations .................................................................................................................................. 58
Figure 2: Revised Project Design and Previous Alignment ......................................................................................... 4
Figure 3: Existing Environment and Land Use .......................................................................................................... 12
APPENDICES
APPENDIX A CEAA Screening and MNRF Screening Matrix for the Pikangikum Distribution Line (2009) and Ministry of Natural Resources and Forestry Correspondence
APPENDIX B Wildlife Species at Risk Assessment
APPENDIX C Aboriginal Engagement Plan
APPENDIX D Stage 1 Archaeological Assessment
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 1
1.0 INTRODUCTION
Wataynikaneyap Power Limited Partnership (Wataynikaneyap) is proposing to construct, operate and maintain a
44 kV and 25 kV distribution line, the Pikangikum Distribution Project (the Project). The Project will provide
a distribution connection between Pikangikum First Nation and the existing transmission system from Red Lake,
Ontario. The Project is located in northwestern Ontario (Figure 1).
The Pikangikum First Nation successfully completed a federal environmental screening assessment under the
previous Canadian Environmental Assessment Act (CEAA) (1992); and a screening under the Ministry of Natural
Resources and Forestry Class Environmental Assessment Resource Stewardship and Facility Development
(MNRF RSFD) screening under Category B in 2009. The 2009 federal screening environmental assessment (EA)
concluded no significant impacts and received approval under Section 16 of CEAA. The Project has not yet
commenced. Wataynikaneyap, as the new Project proponent, has developed a revised Project design, based on
engagement results, First Nation community preference and design engineering (Figure 2).
More than five years have elapsed since the EA Statement of Completion was issued by the MNRF in
August 20, 2009. Therefore, under the MNRF RSFD Class EA there is a requirement to provide an updated Project
Description (PD). In addition, the Project crosses dedicated protected areas (DPAs) that were not identified or in
force in 2009. Therefore, the MNRF Class EA for Provincial Parks and Conservation Reserves (PPCR) now also
applies.
This updated PD has been prepared for submission to the MNRF in accordance with the content requirements for
an updated PD identified in the MNRF letter dated October 27, 2016 (Appendix A), scope clarification meetings
with the MNRF during engagement and the requirements of the PPCR Class EA. This PD includes the following
main components:
Project purpose and rationale;
Project proponent;
Environmental assessment regulatory requirements;
Project details, including highlighting Project detail revisions since the 2009 Statement of Completion
issuance;
Existing baseline overview, effects assessment and mitigation;
Summary of potential permits and approvals;
Species at Risk Report (Appendix B);
Aboriginal Engagement Plan (Appendix C); and
Stage 1 Archaeology Assessment (Appendix D).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 2
2.0 PROJECT PURPOSE AND RATIONALE
Pikangikum First Nation (Pikangikum) is a remote settlement approximately 100 km north of Red Lake in
Northwestern Ontario (MNRF Red Lake District). The community has a reserve land base of 1,808 ha with no
year-round road access. The purpose of the Project is the construction and operation and maintenance of a power
line and associated distribution station (substation) that will connect Pikangikum with the provincial electrical grid
at Red Lake; thereby meeting one of the priorities identified in Ontario’s Long-Term Energy Plan (LTEP) (Ministry
of Energy 2013).
Pikangikum currently relies upon a diesel generating station to provide electricity to the community. It frequently
operates near, at, or above rated capacity, thereby constraining basic infrastructure such as sewage and running
water, as well as housing growth in accordance with a growing population. This diesel generation has proven over
time to be unreliable; the outcomes of a system failure are inconvenient and costly. Fuel costs have increased in
recent years and the resulting high cost to the community has a net effect of reducing funds available for the
maintenance of other community infrastructure assets. An additional Project benefit is the reduction of greenhouse
gases (GHG) as a result of reduced reliance on diesel generator. The Project will also serve to mitigate risks and
costs associated with the existing generating system by providing access to more affordable and consistent
electricity while providing additional power to meet future increases in electrical load, thereby supporting
Pikangikum’s socio-economic growth.
3.0 PROJECT PROPONENT
Wataynikaneyap is the proponent for this Project. Wataynikaneyap is a transmission company equally owned by
22 First Nations communities in partnership with FortisOntario Inc. The company will develop, own, and operate
new transmission facilities in Northwestern Ontario in order to connect 17 remote First Nation communities
currently powered by diesel generation. On August 4, 2016, Pikangikum First Nation joined Wataynikaneyap and
mandated Wataynikaneyap to develop the Pikangikum Distribution Line Project on an expedited basis.
LEGEND!. City!( Town") First Nation Community") Wataynikaneyap Power Community"/ Recreation Point!. Tourism Establishment Area
Major Roads and HighwaysWinter Road
TrailExisting ElectricalTransmission LineWatercourse2009 Proposed Distribution Line RoutePikangikum Distribution Study Corridor - Current RoutePikangikum Distribution Study Corridor - Option APikangikum Distribution Study Corridor - Option B
Substation AreaFirst Nation Reserve LandWaterbodyConservation ReserveDedicated Protected AreaProvincial Parks
PIKANGIKUM DISTRIBUTION LINE PROJECT
500m
200m
B1
B2
BEEKAHNCHEEKAHMEENGDEEBAHNCHEEKAYWEEHN
EENAHOHNAHNUHN
BerensRiver
PeekwatahmaeweeSahkaheekahn/Berens
Lake
"/
"/
!.
500m
200m
200m
200mK1
K2Stormer
WildernessCamp Ltd.
BEEKAHNCHEEKAHMEENGDEEBAHNCHEEKAYWEEHN
EENAHOHNAHNUHN
Kirkness Creek
Stormer Lake
0 5 10
Kilometers1:270,000
30m
200m
100m
200m
N1
N2
NungesserRiver
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
!( Town") Wataynikaneyap Power Community") First Nation Community#0 Tower!. Water Wells1 Mine#0 Active Aggregate Sites"S Abandoned Mines"/ Recreation Point!. Tourism Establishment Area
e Seaplane BaseMajor Roads and HighwaysWinter RoadTrail2009 Proposed Distribution Line RoutePikangikum Distribution Study Corridor - Current RoutePikangikum Distribution Study Corridor - Option APikangikum Distribution Study Corridor - Option B
Predicting and characterizing net effects of the Project (Project Case);
Predicting and characterizing cumulative effects of the predicted Project Case net effects in combination with
past, present and reasonably foreseeable future activities (Reasonably Foreseeable Development Case);
Determining the significance of the net effects of the Project Case and the Reasonably Foreseeable
Development Case;
Identify key factors influencing confidence in effects predictions and how uncertainty is managed so that
effects are not underestimated;
Identifying monitoring and follow-up to confirm predictions and address uncertainty; and
Presenting overall conclusions with regard to the results of the assessment for each assessed criterion.
Assessment Boundaries
Spatial Boundaries
Defining the geographic extent of study areas is a key step in the environmental assessment process.
Spatial boundaries are selected for the assessment using the following factors:
physical extent of the Project;
physical extent of anticipated Project-related effects; and
physical extent of key environmental systems (e.g., watershed boundary of potentially affected streams).
Study areas generally defined for the Project include:
Project footprint – established to identify areas of direct disturbance (i.e., the physical area required and
cleared for Project construction and operation). The Project footprint includes the up to 40-m-wide ROW and
substation. The specific footprint for this project has not been fully defined and is conservatively assessed in
this report considering the up to 40-m-wide ROW within the limits of work representing the most sensitive
area defined for a specific environmental component.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 17
Local Study Area –The local study area (LSA) is meant to encompass the area where most effects of
the Project are likely to be measurable, including the Project footprint; and therefore the focus of data
collection to characterize the existing environment. The LSA for the disciplines includes the limits of work
(between 200 m and 500 m width; see Figure 2) where most of the Project components are expected to be
located; and therefore most of the Project effects are expected to occur.
Regional Study Area – The regional study area (RSA) includes areas outside of the LSA used to measure
broader-scale existing environment conditions, and provide regional context for the maximum predicted
geographic extent of effects from the Project (e.g., changes to downstream water quality, caribou ranges, or
changes to regional employment and incomes). Cumulative effects from the Project in combination with past,
present, and reasonably foreseeable developments are typically assessed at this larger spatial scale.
Temporal Boundaries
The environmental assessment is designed to evaluate the short- and longer-term changes from the Project and
associated effects on the physical, biological and socio-economic environments. Temporal (time) boundaries
considered for this Project include:
Construction Phase – Construction is expected to commence in the late-summer of 2017, to meet an
in-service date of fall 2018.
Operations and Maintenance Phase – The Project is expected to operate indefinitely.
Assessment Cases
Project Case – This scenario represents predictions of the existing conditions (Base Case) combined with
the effects that may result from the Project. This case is used to identify incremental changes that are
predicted to occur from the Project.
Reasonably Foreseeable Development Case – This scenario characterizes cumulative effects associated
with past and present developments, the Project Case plus additional reasonably foreseeable developments
in the region that have not yet been approved or are approved but not yet constructed. Developments and
activities that are currently under application review, have officially entered a regulatory application process,
are considered reasonably foreseeable.
Determination of Significance
The net effects characterization of primary pathways and the associated predicted changes in indicators provide
the foundation for determining the significance of incremental (i.e., Project Case), and cumulative effects from the
Project and other past, present, and reasonably foreseeable developments on criteria assessment endpoints
(i.e., the Reasonably Foreseeable Development Case). The characterization of net effects and the determination
of significance are completed for assessment of the Project. The key factors considered in the determination of
significance of effects to criteria are:
Results from the net effects characterization.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 18
Context, magnitude, geographic extent, duration and reversibility are the primary factors used to determine
significance. Frequency and timing are modifiers for determining significance, where applicable.
Where uncertainty is high and the effect might be either significant or not significant, the assessment would
use a precautionary approach and identified the effect as significant and provided additional follow-up actions
to reduce uncertainty.
8.2 Parks and Protected Areas
This section presents the parks and protected areas baseline characterization and effects assessment and
mitigation. This section also provides an alternatives analysis, as required under the MNRF Class EA PPCR
and the Provincial Parks and Conservation Reserves Act (2006) (PPCRA).
8.2.1 Study Areas
One study area, the LSA, is the limits of work at the BDE DPA.
8.2.2 Baseline Characterization
On April 18, 2011 the majority of the Whitefeather DPA were regulated as provincial parks without classification
under the PPCRA. The proposed Project crosses the BDE DPA, which is regulated under the PPCRA.
Cultural Landscape Waterways are described as: “a special land use category to enhance the value of waterways
to visitors who wish to enjoy the land through recreation and tourism activities. These areas are in most cases a
combination of Dedicated Protected Areas and Enhanced Management Areas”. This DPA category recognizes
these waterways as having an important place in the culture and history of Pikangikum people; as cultural
landscapes, they are the living result of Pikangikum people’s historical customary stewardship role in the
Whitefeather planning area. This land use category also enhances opportunities for recreation and eco-cultural
tourism activities (Pikangikum First Nation and Ontario Ministry of Natural Resources 2006).
The boundaries of this DPA follow ecosystem features and natural and cultural feature boundaries. There are no
critical landform vegetation within the DPA that could be affected by the Project.
The PPCRA provides the legislative framework for the formal protection of provincial parks and conservation
reserves, allowing the MNRF (generally through Ontario Parks) to manage these areas. Development is generally
prohibited or limited in Ontario’s parks and protected areas; however, Section 20(2) of the Act does permit utility
corridors, stating that “subject to the policies of the Ministry and the approval of the Minister, with or without
conditions, utility corridors, including but not limited to utility corridors for electrical transmission lines, are permitted
in provincial parks and conservation reserves” (Government of Ontario 2006). Section 21 of the Act states that in
approving a utility corridor under Section 20, the Minister must be satisfied that “there are no reasonable
alternatives; that the lowest cost is not the sole or overriding justification; and that environmental impacts have
been considered and all reasonable measures will be undertaken to minimize harmful environmental impact and
to protect ecological integrity” (Government of Ontario 2006).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 19
The Whitefeather LUS provides direction on access with regards to the BDE DPA and associated enhanced
management areas, which is as follows:
“There will be no road access within this area with the possible exception of access provisions for major
crossings. Waterway crossings required to provide road access for a variety of purposes including
northern communities’ access, mineral exploration and development, and forest management will be
accommodated and determined through appropriate planning processes (Pikangikum First Nation and
Ontario Ministry of Natural Resources 2006).
Land use direction from Keeping the Land: A Land Use Strategy for the Whitefeather Forest and Adjacent Areas
(a community based land use plan under the Far North Act) is reflected in Ontario’s Crown Land Use Policy Atlas
(CLUPA) which lists new energy transmission and communications corridors as possible permitted uses within the
DPA:
“In certain circumstances such as for a major energy transmission and communications corridor,
provisions for access and water crossings will be made through a planning process, considering the
intent and values of the area.” (Queens Printer for Ontario 2014).
8.2.3 Project Alternatives
As required under the PPCR Class EA, an evaluation of alternatives is required including alternatives to the Project
and alternative methods for carrying out the Project. Section 20 (2) of the PPCRA permits utility corridors in
provincial parks (subject to policies of the Ministry and approval of the Minister). Section 21 of the PPCRA lists
conditions for approval that must be met when approving a utility corridor. They are:
There are no reasonable alternatives;
Lowest cost is not the sole or overriding justification; and
Environmental impacts have been considered and all reasonable measures will be undertaken to minimize
harmful environmental impact and to protect ecological integrity.
This section provides the analysis and results of the alternative methods for carrying out the Project.
The alternatives to the Project was completed and included in the 2009 federal screening EA; and therefore will
not be addressed in this document.
Alternatives Analysis
The proposed power line will cross the aforementioned DPA in three locations: Nungesser River, Kirkness Creek,
and the Berens River/Lake. Two alternatives have been identified for each crossing, which are described below.
The two alternative locations for the Kirkness Creek and Berens River / Lake are identified on Figure 2:
Nungesser River – Alternative N1 proposes to cross the Nungesser River as close to the 30 m Nungesser
Road ROW as is technically reasonable (but still intersecting part of the DPA). Alternative N2 is the crossing
location in Nungesser that had been approved in 2009 and is completely within the DPA. This crossing is
approximately 1 km west of Nungesser Road. There is no in-water work planned for either alternative.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 20
Kirkness Creek – Alternative K1 will predominantly be located outside the DPA following the ROW for the
existing Nungesser Road; however, the alternative may require some project activities within the DPA
boundary. The power line would clear span Kirkness Creek. Alternative K2 uses an existing previously
cleared corridor within the DPA, and the power line would clear span Kirkness Creek. There is no in-water
work planned for either alternative. The crossings are of a similar length (approx. 30 m).
Berens River/Lake – Alternative B1 proposes to cross Berens Lake in the DPA at a location adjacent to
where a bridge is proposed to be constructed; and Alternative B2 proposes to cross the Berens River in a
narrower area of the DPA where the crossing distance is minimized.
Table 1 provides a summary of the key factors for the alternatives analysis for the Nungesser River, Kirkness
Creek and Berens River/Lake DPA crossings related to DPA values, environmental considerations, social and
environment considerations, Aboriginal and non-Aboriginal cultural considerations, and cost and constructability.
The key factors considered in the assessment are based on the screening criteria identified in the PPCR Class
EA. Where screening criteria have not been identified as key factors, they are not judged to mark a distinguishing
characteristic between the alternatives (i.e., the project is not expected to affect permafrost within or adjacent to
the DPA; release of contaminants in soils and sediments will be managed through best management practices for
all alternatives; the project will have a high positive effect for the Pikangikum First Nation under all alternatives).
See Table 11 in Section 9.0 for consideration of other screening criteria and identified mitigation. Mitigation
measures summarized for the Project in Section 9.0 are applicable in all work areas, including within and adjacent
to the DPA.
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Nungesser River
N1 (current line) N2 (original project)
Values for which the provincial park or conservation reserve was established (including Aboriginal values, land use and resource management considerations)
The BDE DPA is recognized as having an important place in the culture and history of the Pikangikum people; and the designated land use category also enhances opportunities for remote recreation and eco-cultural tourism activities.
Both alternatives may have a low negative effects on park user experience due to the visual aspect of the power line. There will be potential effects to noise during construction of the Project, but this will be short-term. Neither of these effects are predicted to be significant.
The operation and maintenance of the power line does not result in any limit of access of land or water in or to the DPA for cultural or recreational purposes.
Wildlife and fish resource populations are not predicted to be significantly affected by the Project; thereby not affecting use of these resources in the DPA.
North of Nungesser River there is timing restriction during April and November along a wildlife travel corridor, as per MNRF.
All activities at Nungesser River crossing of the BDE DPA are subject to a timing restriction to minimize sensory disturbance from July 15 to September 15 up to 10 km from a defined area of woodland caribou nursery habitat.
No discernable difference
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 21
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Nungesser River
N1 (current line) N2 (original project)
There are no new permanent access roads associated with the Project in the DPA.
No construction waste associated with the Project will be permitted within the DPA.
Natural environment considerations
The cleared area adjacent to the existing Nungesser Road is not wide enough to accommodate the Project infrastructure and adjacent tree clearing requirements along the crossing of Nungesser River DPA. Based on the position of the road within its defined ROW, vegetation clearing for the Project ROW will extend beyond the road ROW and require clearing within the DPA boundary.
There will be a need for a new separate ROW up to 20 m in width from the centre-line for the construction and operation and maintenance approximately 1 km west of the Nungesser Road.
N1 is preferred to be adjacent to an existing previously cleared corridor (Nungesser Road), to reduce cumulative effects such as visual disturbance, noise, and habitat fragmentation within the DPA.
Vegetation and Habitat Linkages
There will be vegetation clearing required for a new ROW adjacent to the existing road. No rare vegetation communities are identified within the limits of work. The ROW will overlap with the existing road ROW to the degree possible, but some clearing will be required within the DPA. As noted above, timing restrictions for work are in place in this area relative to use by woodland caribou. Vegetation and habitat linkages are not predicted to be significantly affected.
Vegetation and Habitat Linkages
There will be vegetation clearing required for a new ROW. No rare vegetation communities are identified within the limits of work. The ROW would represent a new clearing in an area of undeveloped habitat within the DPA. As noted above, timing restrictions for work are in place in this area relative to use by woodland caribou. A new ROW would introduce potential for effects such as visual disturbance, noise and habitat fragmentation not currently present within this area of the DPA.
Social and economic considerations (including tourism values)
The power line (visually resembling a 115 kV transmission line) will result in visual effects. The power line will be able to be viewed by persons using Nungesser River for recreational and commercial activities at the Nungesser Road; and may be visible from a tourist operator lodge located on the opposite side of the Nungesser Road (east side) from the planned N1 location. The power line will be located adjacent to the road on the west side with primary access to the river on the east side of the road.
There will be a visual effect to cultural and recreational use due to the new power line structure in an undeveloped section of the DPA.
There are no commercial sensitive viewpoints associated with this alternative.
Neither N1 nor N2 is preferred as both result in potential visual effects to cultural and recreational use within the DPA. N1 includes commercial and recreational users who currently access the Nungesser River at a developed location (adjacent to existing Nungesser Road, established boat launch). Development at N2 represents disturbance to a currently undeveloped area.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 22
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Nungesser River
N1 (current line) N2 (original project)
Aboriginal and non-Aboriginal cultural considerations (including archaeology, built heritage, sacred or traditional use sites)
Archaeology
Archaeological potential has been identified at this crossing location. A Stage 2 archaeological assessment is required prior to development. Should archaeological resources be identified, pole location and frozen ground timing restrictions may be implemented, or a Stage 3 and potentially a Stage 4 archaeological assessment may be required.
With the implementation of mitigation measures through the Ministry of Tourism, Culture and Sport (MTCS) staged assessment process, this alternative is not predicted to result in significant effects to known archaeological resources.
Archaeology
Archaeological potential has been identified at this crossing location. A Stage 2 archaeological assessment is required prior to development. Should archaeological resources be identified, pole location and frozen ground timing restrictions may be implemented, or a Stage 3 and potentially a Stage 4 archaeological assessment may be required.
With the implementation of mitigation measures through the MTCS staged assessment process, this alternative is not predicted to result in significant effects to known archaeological resources.
No discernable difference
Built Heritage and Cultural Heritage Landscape
There is no built heritage within the limits of work. There will be ROW clearing required within the DPA that will affect the cultural heritage landscape within the DPA. However, the Project clearing is adjacent to an existing road that has already created a linear corridor intrusion into the cultural heritage landscape. In addition, the building of a power line through the landscape is reversible as the corridor can be removed and the area returned to its original state. No irreversible effects to the cultural heritage landscape is predicted.
Built Heritage and Cultural Heritage Resources
There is no built heritage within the limits of work. There will be ROW clearing required within the DPA that will affect the cultural heritage landscape within the DPA. The building of a power line through the landscape is reversible as the corridor can be removed and the area returned to its original state. No irreversible significant effects to the cultural heritage landscape is predicted.
Sacred or traditional use sites; spiritual, ceremonial or cultural sites
There were no sacred or traditional use sites; spiritual, ceremonial or cultural sites identified within the limits of work in the DPA.
Sacred or traditional use sites; spiritual, ceremonial or cultural sites
There were no sacred or traditional use sites; spiritual, ceremonial or cultural sites identified within the limits of work in the DPA.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 23
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Nungesser River
N1 (current line) N2 (original project)
Preferred Alternative
N1
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Kirkness Creek
K1 K2
Values for which the provincial park or conservation reserve was established (including Aboriginal values, land use and resource management considerations)
The BDE DPA is recognized as having an important place in the culture and history of the Pikangikum people; and the designated land use category also enhances opportunities for remote recreation and eco-cultural tourism activities.
Both alternatives may have a low negative effects on park user experience due to the visual aspect of the power line. There will be potential effects to noise during construction of the Project, but this will be short-term. Neither of these effects are predicted to be significant.
The operation and maintenance of the power line does not result in any limit of access of land or water in or to the DPA for cultural or recreational purposes.
Wildlife and fish resource populations are not predicted to be significantly affected by the Project; thereby not affecting use of these resources in the DPA.
There are no new permanent access roads associated with the Project in the DPA.
No construction waste associated with the Project will be permitted within the DPA.
No discernable difference
Natural environment considerations
The cleared area adjacent to the existing Nungesser Road is not wide enough to accommodate the Project infrastructure along the crossing of Kirkness Creek. Based on the position of the road within its defined ROW, vegetation clearing for the Project ROW may extend beyond the road ROW and require limited clearing within the DPA boundary.
The power line will make use of an existing previously cleared corridor within the DPA. There will be some requirement for clearing of vegetation regrowth within the corridor, and a widening to accommodate the power line.
K2 is preferred to make use of an existing previously cleared corridor, which will mitigate but not remove the effect of ROW clearing.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 24
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Kirkness Creek
K1 K2
Vegetation and Habitat Linkages
There will be vegetation clearing required for a new ROW adjacent to the existing road. No rare vegetation communities are identified within the limits of work. The ROW will overlap with the existing road ROW to the degree possible, but clearing may be required within the DPA. Vegetation and habitat linkages are not predicted to be significantly affected.
Vegetation and Habitat Linkages
There will be clearing of vegetation regrowth within the existing previously cleared ROW in the DPA, and a widening to accommodate the power line. No rare vegetation communities are identified within the limits of work. Vegetation and habitat linkages are not predicted to be significantly affected.
Social and economic considerations (including tourism values)
The power line (visually resembling a 115 kV transmission line) will result in visual effects. The power line will be able to be viewed by persons using Stormer Lake for recreational and commercial activities; be viewed from Stormer Wilderness Camp Ltd. accessed on the west side of the Nungesser Road approximately 250 m south of the crossing of Kirkness Creek; and viewed by cultural and recreational users in the DPA.
There will be a visual effect to cultural and recreational use due to the new power line structure in the DPA.
There are no commercial sensitive viewpoints associated with this alternative.
K2 is preferred as the potential visual effects are less than K1.
K1 includes commercial and recreational users that experience a remote lake and wilderness camp that may be affected by the addition of a power line along the lake shore and directly adjacent to the wilderness camp.
Aboriginal and non-Aboriginal cultural considerations (including archaeology, built heritage, sacred or traditional use sites)
Archaeology
Archaeological potential has been identified at this crossing location. A Stage 2 archaeological assessment is required prior to development. Should archaeological resources be identified, a Stage 3 and potentially a Stage 4 archaeological assessment will be required.
With the implementation of mitigation measures through the Ministry of Tourism, Culture and Sport (MTCS) staged assessment process, this alternative is not predicted to result in significant effects to known archaeological resources.
Archaeology
Archaeological potential has been identified at this crossing location. A Stage 2 archaeological assessment is required prior to development. Should archaeological resources be identified, a Stage 3 and potentially a Stage 4 archaeological assessment will be required.
With the implementation of mitigation measures through the MTCS staged assessment process, this alternative is not predicted to result in significant effects to known archaeological resources.
No discernable difference
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 25
Table 1: Project Alternatives Analysis
Key Factors
Project Alternatives Preferred Alternative and
Rationale Kirkness Creek
K1 K2
Built Heritage and Cultural Heritage Landscape
There is no built heritage within the limits of work. There will be ROW clearing required within the DPA that will affect the cultural heritage landscape within the DPA. However, the Project clearing is adjacent to an existing road that has already created a linear corridor intrusion into the cultural heritage landscape. In addition, the building of a power line through the landscape is reversible as the corridor can be removed and the area returned to its original state. No irreversible effects to the cultural heritage landscape is predicted.
Built Heritage and Cultural Heritage Resources
There is no built heritage within the limits of work. The Project will use an existing ROW, which has already created a linear corridor intrusion into the cultural heritage landscape. In addition, the building of a power line through the landscape is reversible as the corridor can be removed and the area returned to its original state. No irreversible significant effects to the cultural heritage landscape is predicted.
Sacred or traditional use sites; spiritual, ceremonial or cultural sites
There were no sacred or traditional use sites; spiritual, ceremonial or cultural sites identified within the limits of work in the DPA.
Sacred or traditional use sites; spiritual, ceremonial or cultural sites
There were no sacred or traditional use sites; spiritual, ceremonial or cultural sites identified within the limits of work in the DPA.
Preferred Alternative
K2
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 26
Table 1: Project Alternatives Analysis
Berens River / Lake
Key Factors B1 B2 Preferred
Alternative and Rationale
Values for which the provincial park or conservation reserve was established (including Aboriginal values, land use and resource management considerations)
The DPA is recognized as having an important place in the culture and history of the Pikangikum people; and the designated land use category also enhances opportunities for remote recreation and eco-cultural tourism activities.
Both alternatives may effects on park user experience due to the visual aspect of the power line. There will be potential effects to noise during construction of the Project, but this will be short-term. Neither of these effects are predicted to be significant.
The operation and maintenance of the power line does not result in any limit of access of land or water in or to the DPA for cultural or recreational purposes.
Wildlife and fish resource populations are not predicted to be significantly affected by the Project; thereby not affecting use of these resources in the DPA.
There are no access roads associated with the Project in the DPA; the B1 alternative would be located adjacent to the planned Berens River bridge, which would connect two sides of a planned road approved in the Whitefeather Forest Management Plan. Construction and maintenance access to the B2 alternative would be through the corridor itself.
No waste associated with the Project will be permitted within the DPA.
No discernable difference
Natural environment considerations
The power line will be located adjacent to a planned road ROW. A smaller area of vegetation clearing is required for the power line ROW where the Project can be located adjacent to the planned Whitefeather Forest Road ROW.
There will be a need for a new separate ROW up to 20 m in width from the centre-line for the construction and operation and maintenance of the power line, approximately 1 km downstream of the planned Berens River bridge location.
B1 is preferred as a smaller area of vegetation clearing may be required for the power line ROW where the Project can be located adjacent to the planned Whitefeather Forest Road ROW. Additionally, given plans for a future bridge with a large truss structure in the vicinity of B1, the aerial collision hazard of power line is expected to be partially reduced.
Vegetation and Habitat Linkages
A smaller area of vegetation clearing may be required for the power line ROW where the Project can be located adjacent to the planned Whitefeather Forest Road ROW. No rare vegetation communities are identified within the limits of work. The ROW will overlap with the planned road ROW to the degree possible, but clearing will be required within the DPA. Vegetation and habitat linkages are not predicted to be significantly affected.
Vegetation and Habitat Linkages
There will be vegetation clearing required for a new ROW. No rare vegetation communities are identified within the limits of work. Vegetation and habitat linkages are not predicted to be significantly affected.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 27
Table 1: Project Alternatives Analysis
Berens River / Lake
Key Factors B1 B2 Preferred
Alternative and Rationale
Social and economic considerations (including tourism values)
The power line will clear span Berens Lake adjacent to the planned Berens River bridge location. There will be a visual effect to cultural and recreational use due to the new power line structure in the DPA; however, the contribution of the power line compared with the cumulative visual effect of the power line and the bridge is not predicted to be significant.
There are no commercial sensitive viewpoints associated with this alternative.
The power line through the DPA will be a new structure approximately 1 km downstream from the planned Berens River bridge location. There will be a visual effect to cultural and recreational use due to the new power line structure in the DPA.
There are no commercial sensitive viewpoints associated with this alternative.
B1 is preferred as the power line will be near to the planned bridge structure.
Aboriginal and non-Aboriginal cultural considerations (including archaeology, built heritage and cultural heritage landscapes, sacred or traditional use sites; spiritual, ceremonial or cultural sites
Archaeology
One identified archaeological site and archaeology potential have been identified within the limits of work. A Stage 2 archaeological assessment is required prior to development. Should archaeological resources be identified a Stage 3 and potentially a Stage 4 archaeological assessment will be required.
With the implementation of mitigation measures through the Ministry of MTCS’s staged assessment process, this alternative is not predicted to result in effects to archaeological resources.
Archaeology
There is archaeology potential within the limits of work. A Stage 2 archaeological assessment is required prior to development. Should archaeological resources be identified a Stage 3 and potentially a Stage 4 archaeological assessment will be required.
With the implementation of mitigation measures through the MTCS’s staged assessment process, this alternative is not predicted to result in effects to archaeological resources.
B2 is preferred as there is an identified archaeological site within the limits of work for B1.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 28
Table 1: Project Alternatives Analysis
Berens River / Lake
Key Factors B1 B2 Preferred
Alternative and Rationale
Built and Cultural Heritage Landscapes
There is no built heritage within the limits of work. There will be ROW clearing required within the DPA that will affect the cultural heritage landscape within the DPA. However, the Project clearing is adjacent to the proposed Whitefeather Road ROW to minimize the linear corridor intrusion into the cultural heritage landscape. In addition, the building of a power line through the landscape is reversible as the corridor can be removed and the area returned to its original state. No irreversible significant effects to the cultural heritage landscape is predicted.
Built and Cultural Heritage Landscapes
There is no built heritage within the limits of work. There will be ROW clearing required within the DPA that will affect the cultural heritage landscape within the DPA. However, the Project clearing is adjacent to the proposed Whitefeather Road ROW to minimize the linear corridor intrusion into the cultural heritage landscape. In addition, the building of a power line through the landscape is reversible as the corridor can be removed and the area returned to its original state. No irreversible significant effects to the cultural heritage landscape is predicted.
Sacred or traditional use sites; spiritual, ceremonial or cultural sites
There are no known sacred or traditional use sites; spiritual, ceremonial or cultural sites identified within the limits of work in the DPA.
Sacred or traditional use sites; spiritual, ceremonial or cultural sites
There are no known sacred or traditional use sites; spiritual, ceremonial or cultural sites identified within the limits of work in the DPA.
Preferred Alternative B1
Cost was not included in the alternatives evaluation above as there is no discernable difference between each pair
of alternatives, given the coarse nature of estimations at this stage of the Project. Therefore, cost was not a factor
in identifying the preferred alternative.
Based on the analyses completed above, N1, K2, and B1 have been identified as the preferred alternatives to
cross the DPAs. These preferred alternatives were carried into the effects assessment described in the next
section, which includes recommended impact mitigation measures.
8.2.4 Effects Assessment and Mitigation
Project Case
The Project has been designed to avoid effects to any known archaeological sites, built heritage, sacred sites or
traditional use sites in the DPA where possible. One archaeological site is identified within the limits of work for
the B1 crossing alternative in the area of the planned Berens River Bridge. Compliance with the findings of further
archaeological investigations (e.g., MTCS Stage 2) will guide specific design in this area. No significant effects to
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 29
known archaeological sites, sacred sites or traditional use sites in the DPA are predicted for any of the alternatives
considered. Significant effects to fish and wildlife populations, which may be used for cultural and recreational
resources, are not predicted.
During construction, site preparation activities, such as vegetation clearing for the power line ROW,
tower foundation preparation and erection of towers may temporarily limit access in the DPA during the
construction period; and result in an increase in noise disturbance that could affect use of the DPA by wildlife and
for cultural, recreational or commercial use by people in the area of construction. There will be emissions
associated with construction equipment and machinery that may have localized effects to air quality. However,
these potential effects will be short-term, limited to the timeframe of construction through the DPA. Temporary
access restrictions at the location of construction through the DPA may be required during the construction period.
The construction period is anticipated to be up to three months in the DPA.
The Project has been designed to follow or use existing and planned ROWs where possible with the intent to
limit the requirement for vegetation clearing, including areas within the DPA. For the Nungesser River crossing,
the power line ROW will require vegetation clearing to the water’s edge within the DPA adjacent to the exis ting
Nungesser Road. Primary access for construction, operation and maintenance will be via the Nungesser Road.
There will be no in-water work in the DPA. A riparian buffer regrowth to 30 m from the high water mark will be
implemented post-construction with consideration for the safe operation of the power line. The up to 40 m wide
ROW overlaps approximately 2 ha of the BDE DPA and up to 6 poles are expected to be required within this area.
For the Kirkness Creek crossing, Wataynikaneyap will use a previously cleared ROW in the DPA for access and
construction of the power line. There will be a requirement for clearing of vegetation that has overgrown this ROW.
A riparian buffer regrowth to 30 m from the high water mark will be implemented post-construction with
consideration for the safe operation of the power line. The up to 40 m wide ROW will overlap approximately 1.2 ha
of the BDE DPA and up to 4 poles are expected to be required within this area.
For the Berens River crossing, the power line ROW will require vegetation clearing in the DPA; but will align with
the planned Whitefeather Forest Road ROW. Access during construction will use the existing road or clearing,
depending on its construction status, and may include temporary access along the ROW where road construction
is not complete along the Whitefeather Forest road. An ice crossing across the Berens River may also be utilized
should ice conditions permit. Vegetation clearing for the power line ROW will be to water’s edge; however there
will not be a requirement for any in-water work in the DPA. A riparian buffer regrowth to 30 m from the high water
mark will be implemented post-construction; with consideration of the safe operation of the power line. There are
no new access roads associated with the Project in the DPA. No construction waste associated with the Project
will be permitted within the DPA. After construction, all construction materials will be removed and the area
rehabilitated, as required. The up to 40 m wide ROW overlaps approximately 5 ha of the BDE DPA ground surface
and up to 15 poles are expected to be required within this area.
No construction waste associated with the Project will be permitted at any of the proposed DPA crossings. After
construction, all construction materials will be removed and the area will be rehabilitated in manner consistent with
best utility practice.
Maintenance and operation of the power line ROW will require routine mechanical clearing. Riparian vegetation
regrowth will be permitted along the Berens River, Kirkness Creek and Nungesser River crossings, such that the
vegetation does not interfere with the safe operation of the power line. The power line structure will result in a
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 30
change of view in the DPA. At the Kirkness Creek crossing K2; there is no current structure through the DPA. At
the Berens Lake crossing B1, there is no current structure; however, the power line location will align with the
proposed bridge location, which will minimize potential visual effects of the Project. At the Nungesser River
crossing N1, there is no current structure; however the power line location will align with the current Nungesser
Road and bridge plans within the DPA; which will minimize potential visual effects of the Project. The power lines
will not reduce access in or to the DPA, and are predicted to have a negligible effect to park users and sense of
remoteness.
Mitigation measures that will be implemented by Wataynikaneyap include the following:
no new permanent access roads associated with the Project in the DPA;
no construction waste associated with the Project will be permitted within the DPA;
install signs on the ROW during construction indicating the DPA boundary;
no burning of merchantable timber in the DPA;
minimize number of towers in the DPA;
clean equipment before moving it between the DPA and other non-protected area land;
no laydown areas permitted in the DPA; and
at all waterbodies maintain a minimum 30 m vegetated buffer post-construction.
With the Project design and mitigation described above, it is not predicted that the Project will result in a significant
effects to parks and protected areas. In addition, the Project is not anticipated to result in a significant effect to the
cultural and recreational values and resources associated with the DPA. The Project will not result in permanent
loss of access in or to the DPA for cultural or recreational purposes, and will result in negligible effects to park
users and sense of remoteness due to the presence of the power line structure in the DPA.
Reasonably Foreseeable Development Case
For the Berens River crossing, a bridge and planned Whitefeather Forest Road will be constructed. The power
line would be located adjacent to the bridge and the Whitefeather Forest Road to minimize cumulative effects with
projects that have already been planned and located.
The Wataynikaneyap Phase 2 Project ROW is likely to overlap the Project limits of work at the Berens River
crossing. North of the planned substation for the Project, including the Berens River crossing, Phase 2 Project will
require construction of a separate transmission line ROW operating at 115 kV. This line is currently planned to
twin the Project and Whitefeather Forest Road alignments from the substation location to the point where the
Project follows an existing clearing west toward the Pikangikum First Nation community. Through Project design
and locating the Phase 2 ROW next to and paralleling existing cleared corridors, the area required to be cleared
to provide an up to 40-m-wide ROW for Phase 2 transmission line can be minimized, additional clearing for access
roads reduced, and visual effects limited to one location.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 31
With the Project and Phase 2 being co-located with existing and planned disturbances in the Berens River crossing
in the DPA; the reasonably foreseeable development case and incremental changes in the DPA is predicted to
not results in significant effects to the DPA.
8.2.5 Prediction Confidence in the Assessment
Confidence that there will be no predicted significant effects on parks and protected areas is high based on the
location of the Project crossings in the DPA, use of existing ROWs for construction and access, limit clearing for
the ROW and mitigation measures to minimize potential effects to park users, resources and the values identified
for the DPA.
8.2.6 Follow-up, Inspection, and Monitoring
No follow-up, inspection or monitoring is required.
8.2.7 Conclusions
With the implementation of identified mitigation measures, no significant effects to parks and protected areas are
predicted from the Project.
8.3 Species at Risk
Correspondence from the MNRF (Appendix A) identified the following Species at Risk be addressed:
Woodland caribou
Eastern whip-poor-will
Wolverine
Bank swallow
Little brown myotis and northern long-eared myotis
Lake sturgeon.
Appendix B provides a detailed baseline characterization, effects assessment, and proposed mitigation for all the
terrestrial species above. Findings are summarized in this section and in Table 6 of Section 9.0 Summary and
Conclusions, along with proposed mitigation.
For terrestrial SAR species, except for bats and woodland caribou, the Project Case and the RFD Case are not
predicted to result in significant effects with the implementation of identified mitigation.
The little brown myotis population at Base Case is predicted to be significantly affected. However with effective
implementation of mitigation, the Project is predicted to have a small but negative effect on the bats, and have no
to little contribution to the combined effects from the Base Case. No significant effects are predicted from the
Project Case. The RFD Case is conservatively predicted to be significant due to uncertainty associated with future
forestry activities, climate change, and population demographic rates. However, the Project is expected to
contribute little to the significance of RFD Case.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 32
No significant effects to woodland caribou are predicted from the Project Case. The RFD Case is conservatively
predicted to be significant due to uncertainty associated with future forestry activities, climate change, and
population demographic rates. However, the Project is expected to contribute little to the significance of RFD Case.
Lake Sturgeon (northwestern population) is listed as Threatened under the provincial ESA, Endangered under the
Committee on the Status of Endangered Wildlife in Canada (COSEWIC) evaluation and are present in the Berens
River and Pikangikum Lake. The removal of the submarine crossing from the previous Project proposal has
reduced the potential to affect this species. Potential to cause adverse effects to Lake Sturgeon as a result of the
current Project are consistent with those identified for aquatic SAR at aerial water crossings identified in the
previous 2009 EA approval (Appendix A), and associated use of temporary crossing structures during
construction, namely through damage to shoreline or riparian vegetation, disturbance to or erosion of banks from
construction activities, sediment entrainment, and deposition within the water body, and potential for fuel spillage.
Where the Project crosses the Berens River, the approved Whitefeather Forest Management Plan all-season road
paths will be utilized to access the north side of the Berens River and also the proposed substation area to the
south. An ice crossing across the Berens River may also be utilized should ice conditions permit. For the
construction of the ice crossing, no new temporary or permanent soil fill will be placed below the high water mark).
As Lake Sturgeon occur in the bottom areas of lakes and large rivers (Nelson and Paetz 1992), the riparian area
is not part of the critical habitat of Lake Sturgeon, and removal of riparian vegetation can occur following Fisheries
and Oceans Canada (DFO) Measures to Avoid Causing Harm to Fish and Fish Habitat including Aquatic Species
at Risk (DFO 2016).
The Project will implement mitigations identified in the 2009 EA approval (Appendix A) to control sediment and
erosion to the Berens River and Pikangikum Lake, as well as potential releases from spills to water bodies spanned
by the Project. In addition, the Project will follow DFO’s Measures to Avoid Causing Harm to Fish and Fish Habitat
Including Aquatic Species at Risk (e.g., no clearing of vegetation during the timing window1 if there is open water;
allowing riparian vegetation below the ordinary high water mark to regrow, if any is required to be removed during
construction; when practicable, pruning or topping the vegetation instead of grubbing/uprooting) and MNRF’s
Environmental Guidelines for Access Roads and Water Crossings. Specific mitigations are summarized in Table 6
(Section 9.0).
Considering the design of the Project (aerial water crossings and use of temporary crossing structures with no
work below the high water mark) and implementation of proposed mitigations, there are no predicted significant
effects of the Project to Lake Sturgeon.
8.4 Built Heritage Resources and Cultural Heritage Landscapes Assessment
This section describes and summarizes a preliminary screening and assessment of the effects of the Project on
built heritage resources and cultural heritage landscapes (termed heritage resources for remaining text).
As defined in the Provincial Policy Statement, 2014 (PPS 2014), built heritage resources are “a building, structures,
1 At Peekwatahmaewee Sahkaheekahn/Berens Lake, based on the thermal regime designation (cool), the restricted activity timing window
for work would be April 1 to July 15. Based on MNRF information, species specific timing would be: September 15 to June 30 (Cisco [October 1 to May 31], Lake Whitefish [September 15 to May 31], Lake Sturgeon [May 1 to June 30] plus spring spawning species [e.g., Walleye, Northern Pike]). Confirmation with MNRF and/or DFO on required timing would be obtained if clearing of vegetation under open water conditions was determined to be required below the ordinary high water mark.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 33
monuments, installations, or any manufactured remnant that contributes to a property’s cultural heritage value or
interest as identified by a community, including an Aboriginal [Indigenous] community”. A cultural heritage
landscape is “a defined geographical area that may have been modified by human activity and is identified as
having cultural heritage value or interest as identified by a community, including an Aboriginal [Indigenous]
community” (PPS 2014). The area “may involve features such as structures, spaces, archaeological sites,
or natural elements that are valued together for their interrelationship, meaning or association” (PPS 2014).
Examples of cultural heritage landscapes include: heritage conservation districts designated under Part V of the
Ontario Heritage Act; cemeteries, trailways, viewsheds, natural areas, and industrial complexes of heritage
significance; villages, parks, gardens, battlefields, mainstreets, and neighbourhoods; and areas recognized by
federal or international designation authorities, such as a National Historic Site or a UNESCO World Heritage Site
(PPS 2014). Keeping the Land: A Land Use Strategy for the Whitefeather Forest and Adjacent Areas (Pikangikum
First Nation and Ontario Ministry of Natural Resources 2006) defines specific cultural landscapes within the
Whitefeather Forest portion of the Project area.
The Province of Ontario, through the MTCS, has developed a series of products to advise municipalities,
organizations, and individuals on heritage protection and conservation. Identifying the presence of heritage
resources within a project area is aided by the MTCS Criteria for Evaluating Potential for Built Heritage Resources
and Cultural Heritage Landscapes: A Checklist for the Non-Specialist (2015), while more detailed guidance on
other aspects of heritage evaluation and conservation provided in the Ontario Heritage Tool Kit series.
The screening for this project is being conducted under the Class Environmental Assessment for MNR Resource
Stewardship and Facility Development Projects and the Class Environmental Assessment for Provincial Parks and
Conservation Reserves. This process is managed by the MNRF which provides guidance for the assessment of
Built Heritage and Cultural Heritage Landscapes through their Technical Guideline for Cultural Heritage Resources
for Projects Planned Under the Class Environmental Assessment for MNR Resource Stewardship and Facility
Development Projects and the Class Environmental Assessment for Provincial Parks and Conservation Reserves
(2006). Further guidance from the MNRF in Forestry Management areas comes from their Forest Management
Guide for Cultural Heritage Values (2007).
If the potential for heritage resources in a LSA is identified when completing the MTCS or MNR Checklist, further
investigation as part of a Cultural Heritage Evaluation Report (CHER) or Heritage Impact Assessment (HIA) is
required. In both a CHER and HIA the heritage value or interest of listed properties or newly identified resources
is evaluated using the Ontario Regulation 9/06 Criteria for Determining Cultural Heritage Value or Interest
(O. Reg. 9/06 and O. Reg. 10/06). The effects of a development or site alteration on known or newly identified built
heritage resources or cultural heritage landscapes are assessed as part of a HIA. In this EA report, heritage
resources are represented by two key indicators: known heritage resources (resources already protected under
formal or informal government policy or legislation), and potential heritage resource (resources which could be
considered for protection under formal or informal government policy or legislation). These key indicators have
been identified to assess the effects of the Project on the heritage resources in the study area. The criterion,
rationale and indicators are summarized in Table 2.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 34
Table 2: Heritage Resources Criteria and Indicators
Criteria Rationale Indicators
Built Heritage and
Cultural Heritage
Landscapes
Built heritage remains are a non-renewable resource that could be affected by Project activities
Cultural heritage landscapes are a non-renewable resource that could be affected by Project activities
Heritage resources and cultural heritage landscapes have spiritual and symbolic meaning for First Peoples and to Canadians
Heritage resources and cultural heritage landscapes are protected under the Ontario Heritage Act
Number, type and location of identified and potential built heritage resources and cultural heritage landscapes
8.4.1 Study Area
One study area, a LSA, has been identified for Built Heritage Resources and Cultural Heritage Landscapes. The
LSA is the limits of work shown on Figure 2, plus a 50 m buffer.
8.4.2 Baseline Characterization (Base Case)
8.4.2.1 Methods
Historic research was conducted using archival and secondary materials including historic atlases and topographic
maps, local histories, and government reports. A review of government registers was conducted to determine the
presence of municipally, provincially, and federally recognized heritage resources in the study area. Analysis of
historic mapping material also provided a context from which to determine the location of known heritage resources
in the study area.
8.4.2.2 Results
8.4.2.2.1 Known Heritage Resources
The following provides a preliminary understanding of known built heritage and cultural heritage landscapes in the
LSA that are already protected under formal or informal government policy or legislation.
Federally Recognized Heritage Resources
Federally-recognized built heritage resources are those properties, buildings, and places that have been
designated under a form of federal legislation such as the Canada National Parks Act or the Heritage Railway
Stations Protection Act. Federal heritage designations can include national historic sites, persons and events of
national historic significance, heritage railway stations, federal heritage buildings, and heritage lighthouses.
Only a proportion of these are directly administered by Parks Canada but the agency provides heritage
conservation advice and support whether the asset is privately owned or the responsibility of a provincial or federal
department.
Parks Canada manages the Canadian Register of Historic Places (CRHP), which is a database of recognized
heritage properties. A search of the CRHP database on March 14, 2017 found no recognized federal sites in the
LSA. Of note, the Pikangikum First Nation have stated in their Land Use Strategy for the Whitefeather forest that
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 35
they intend to pursue a National Historic Site proposal for Kirkness Lake in close proximity to the LSA
(Pikangikum 2006).
The study area also crosses a small portion of the area formerly included in a UNESCO World Heritage
Nomination, called Pimachiowin Aki. Pimachiowin Aki included an area of 33,499 square kilometres of land and
water spanning both Manitoba and Ontario. The nomination was a collaboration between five Anishinaahe
First Nations groups, including Pikangikum. In 2016, Pikangikum First Nation withdrew from the Project.
A bid for nomination was submitted in 2017 including a smaller geographic area, which is outside of the study area
of this project. The federal agency, Parks Canada, is the Government of Canada’s representative for the UNESCO
World Heritage Convention. While the nominated area is not federal, Parks Canada does retain interest in any
area under a UNESCO World Heritage Nomination and would be responsible for ensuring the planning
mechanisms in place to protect and conserve the site are upheld should its Nomination be successful
(Parks Canada 2016).
Provincially Recognized Properties of Heritage Value or Interest
Protection and conservation of properties of heritage value or interest in Ontario is primarily achieved under the
Ontario Heritage Act, which empowers municipalities to recognize and protect built heritage resources and cultural
heritage landscapes. Although the MTCS also has the authority to designate properties of heritage value or interest
under the Ontario Heritage Act. Other provincial acts such as the Funeral, Burial and Cremation Services Act,
2002 and the Provincial Parks and Conservation Reserves Act, 2006 also serve to protect heritage resources.
Provincial parks are administrative areas set aside as reserves for the purpose of protecting the natural
environment within their boundaries. There are seven different classes of parks including wilderness, nature
reserve, cultural heritage, natural environment, waterway, recreational, and aquatic. All seven classes of parks
can include heritage resources within their boundaries, which are to be protected by implementing administrative
controls carried out by each park’s staff and the MNRF.
Provincially-recognized heritage resources include properties, plaques, and monuments that have been
recognized by the provincial government and provincial agencies through the use of registers, plaque programs,
monuments and conservation easements, agreements, and covenants. The MTCS and the Ontario Heritage Trust
(OHT), a provincial government agency, maintain a list of these resources, and the OHT also manages the Ontario
Heritage Act Register, which includes information on properties designated under the Ontario Heritage Act.
Management of these provincially-recognized heritage resources is guided by the Standards and Guidelines for
the Conservation of Provincial Heritage Properties (MTCS 2010).
The desktop review of provincial heritage inventories indicated that three designated or listed heritage properties
are located in the LSA. These designated properties are in a regulated provincial park; (BDE DPA), of which the
project crosses at three points: Berens River, Kirkness Creek; and the Nungesser River.
The DPA was created in 2011. This park was created from part of the cultural landscape area identified within the
Land Use Strategy for the Whitefeather Forest and Adjacent areas a planning document created through
collaboration between the Pikangikum First Nations and the Ontario Ministry of Natural Resources in 2006.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 36
The following is a brief summary of the Pikangikum First Nations understanding of their cultural heritage
landscapes with common elements shared by all three waterways. This is followed by some distinctions for the
three waterways which are crossed by the project. All three waterways were part of the former UNESCO World
Heritage Nomination completed for the area (Pimachiowin Aki Corporation 2016). The following description of the
three cultural landscapes is taken primarily from the Whitefeather Land Use Strategy (Pikangikum 2006) and
the UNESCO World Heritage Nomination (Pimachiowin Aki Corporation 2016).
Cultural Landscapes as Defined by Pikangikum First Nation
The Pikangikum First Nations have defined their cultural heritage landscapes as “the living result of Pikangikum
people’s historical customary stewardship role” (Pikangikum 2006). This stewardship role is expressed through
the spiritual beliefs of the Anishinaabeg people:
“Anishinaabeg understand the Creator put them on the land, providing them with all the physical and
spiritual resources they need to survive and prosper. In acknowledgement of the gift of life,
Anishinaabeg uphold a sacred trust with the Creator to care for aki, the land and all its life. This sacred
trust entails a duty to work with other beings in a respectful way, a way that honours creation, with the
understanding that all beings are united under the Creator, Gaa-debenjiged or Gizhe-Manidoo
(Great Spirit). (Pimachiowin Aki Corporation 2016).
The Anishinaabeg people uphold their sacred trust through Ji-ganawendamang Gidakiiminaan:
“Ji-ganawendamang Gidakiiminaan is a set of beliefs, values, knowledge, and practices that guide
relations with the land and all life placed on the land by the Creator; these are the aadizookewin
(“teachings”) passed down through the generations through oral traditions in Anishinaabemowin
(the Ojibwe language). (Pimachiowin Aki Corporation 2016).
The Anishinaabe tradition of Ji-ganawendamang Gidakiiminaan is not about transforming the
landscape, it is about living within the opportunities and limits presented by the boreal forest
environment of Pimachiowin Aki. Anishinaabe akiing ondaaji’idizowin (customary livelihood practices)
entail the harvest of plants, animals, and other forms of life in a manner that ensures the continuity of
the Creator’s gifts. Every being, everything on the land, has a purpose for being and its own relationship
with the Creator that must be respected, even if that relationship is not well understood by human
beings. (Pimachiowin Aki Corporation 2016).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 37
The cultural landscapes within the LSA are:
“an exceptional expression of the cultural tradition of Ji-ganawendamang Gidakiiminaan. A complex
network of interlinked sites, routes, and areas make up the attributes that span the nominated area,
providing testimony to the beliefs, values, knowledge, and practices that constitute Keeping the Land.
While the material remains of Anishinaabe use and occupation are generally impermanent and often
difficult to observe for an untrained eye, the evidence of Ji-ganawendamang Gidakiiminaan is pervasive
within the nominated area and can be understood through Anishinaabe knowledge and oral traditions.
(Pimachiowin Aki Corporation 2016).
Key attributes with the cultural landscapes which reflect the cultural tradition of Ji-ganawendamang Gidakiiminaan
include harvesting sites, habitation and processing sites, travel routes, named places, sacred and ceremonial
sites, and trapline areas:
At harvesting sites, Anishinaabeg of Pimachiowin Aki honour the Creator’s gifts through the harvest of
plants, animals, and other forms of life in a manner that ensures continuity of all life on the land.
Habitation and processing sites in Pimachiowin Aki enable Anishinaabeg to focus harvesting efforts in
areas where resources are most abundant. Travel routes, especially waterways, and the named places
that serve as landmarks along those travel routes, support the shifting use of this vast landscape as
people respond to the uneven and changing distribution of resources. Sacred and ceremonial sites are
important nodes on the Pimachiowin Aki cultural landscape where Anishinaabeg acknowledge
dependence on the Creator and observe respectful behaviour toward other beings. Trapline areas within
Pimachiowin Aki enable shared use of the land while also acknowledging that extended family groups
are responsible for stewardship of specific areas, based on their established histories of trapping,
hunting, and fishing. (Pimachiowin Aki Corporation 2016).
Nungesser River (Ohshkahtohkahweeseebee) – Cultural Heritage Landscape
The Nungesser River connects Nungesser Lake with Little Vermillion Lake. The former UNESCO World Heritage
Nomination notes a number of important features in association with this cultural heritage landscape:
habitation sites at the mouth of the Nungesser River on Nungesser Lake approximately 3 km from the Project
crossing of the Nungesser River. Archaeological sites data states that a site is located there under Borden
number EiKk-1 (Pimachiowin Aki Corporation 2016).
Extensive hunting and trapping sites along its route (Pimachiowin Aki Corporation 2016).
A significant waterway travel route (Pimachiowin Aki Corporation 2016).
Kirkness Creek/Stormer Lake – Cultural Heritage Landscape
Kirkness Creek connects Kirkness Lake/Stormer Lake with Shining in the Distance Lake/Nungesser Lake.
This cultural heritage landscape is located in the LSA. The location of the proposed Project is at the mouth of
Kirkness Creek on Stormer Lake. Stormer Lake is directly connected with Kirkness Lake to the west. Kirkness
Lake (Wahshaygahmesshiing) is an important lake as a historical location of a summer village for the Pikangikum
people and a historical crossroads for the Pikangikum people and the fur trade (Pikangikum 2006).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 38
Important aspects noted near the LSA within the cultural heritage landscape include:
An important significant waterway travel route (Pimachiowin Aki Corporation 2016).
Extensive hunting and trapping sites within the area (Pimachiowin Aki Corporation 2016).
Manoomin (Northern Wild Rice) harvest area identified within 500 m to the east of the LSA (Pimachiowin Aki
Corporation 2016).
Berens Lake/Berens River (Kitchee Zeebee) – Cultural Heritage Landscape
Berens Lake/Berens River is the major watercourse through the region which eventually drains into Lake Winnipeg
to the west. The LSA is located at a crossing of the Berens River at the outlet of Berens Lake. Pikangikum Lake
is located to the west along the waterway and numerous significant areas are located up river including
Silcox Lake, Throat River, Owl River, and Mamakwash Lake.
The Land Use Strategy for the Whitefeather Forest describes the Berens River as the “heart of the Pikangikum
cultural landscape” (Pikangikum 2006). Important aspects noted near or in the LSA within the cultural heritage
landscape include:
A significant waterway travel route (Pimachiowin Aki Corporation 2016).
Extensive hunting and trapping sites within the area (Pimachiowin Aki Corporation 2016).
A number of cabins and campsites are located along the shores of Berens Lake (Pimachiowin Aki Corporation
2016). All noted locations are not in close proximity to the LSA.
A set of rapids (Pimachiowin Aki Corporation 2016) are located within the LSA.
An archaeological site is registered within the LSA and the cultural heritage landscape; EkKk-4, Berens Lake
Portage (Hamilton and Taylor-Hollings 2010).
Where the project crosses these cultural heritage landscapes, the power line design seeks to parallel existing and
planned road crossings to the degree possible.
Municipally Recognized Built Heritage and Cultural Heritage Landscapes
Municipally recognized built heritage and cultural heritage landscapes are primarily designated or listed properties
and protected under by-laws enabled by Part IV and V of the Ontario Heritage Act; and other forms including
informally recognized plaques, monuments and parks.
The only municipality within the LSA is the Municipality of Red Lake. The Official Plan of the Municipality of Red
Lake indicates that there are currently no identified built heritage or cultural heritage landscapes within the
Municipality (Red Lake 2015).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 39
8.4.2.2.2 Potential Heritage Resources
According to MTCS guidelines (MTCS 2005), any resources (i.e., buildings or structures) older than 40 years can
be considered potential heritage resources. These properties are not listed or designated properties and currently
have no associated controls or heritage by-laws, but could be protected for their heritage value should any level
of government deem them significant heritage resources.
Based on the preliminary desktop research, one potential resource was identified within the LSA close proximity
to the LSA with potential heritage value: the Leemac Occurrence (Gold Mine) location, identified through review
of the Abandoned Mines Information System (AMIS). The Ministry of Northern Development and Mines (MNDM)
AMIS database record MDI52N04SE00006 indicates this location represents a gold deposit tested in the 1940s
and 1950s. The recorded point within the AMIS database is located approximately 60 m east of the limits of work
boundary; as the extent of the site is not documented, features associated with the testing could be located within
the LSA. Where the project crosses this potential heritage resource, the power line design seeks to parallel the
existing Nungesser Road which will further increase the setback distance to the recorded point in the AMIS
database.
8.4.3 Effects Assessment and Mitigation
Project Case
As noted in Section 8.4.2, known and potential heritage resources within the LSA were identified based on historic
research using archival and secondary materials, a review of government registers, analysis of historic mapping
material, historic survey, aerial photography, LIDAR, and topographical maps.
The potential interactions with Project activities, the potential effects from the Project, the need for mitigation, and
the predicted residual environmental effects are presented in Table 3 for the two key indicators, known heritage
resources and potential heritage resources identified to assess the effects of the Project on Built Heritage
Resources and Cultural Landscapes.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 40
Table 3: Potential Effects, Mitigation and Residual Effects for the Environment on the Project
Indicators
Project
Component or
Activity
Effect Pathway Mitigation Measures Description of
Net Effect
Known heritage resources and potential heritage resources
Project activities during the construction stage, including clearing and grubbing of vegetation along the power line alignment right-of-way, and other construction areas
Alteration of a heritage resource from vibration of construction equipment during construction, clearing and grubbing of vegetation along the power line alignment right-of-way and other construction areas
Consultation with the MNRF to determine best practice for the protection of identified heritage resources.
Existing roads and trails will be used where possible.
Implement mitigation measures identified in the 2009 INAC screening report to minimize for potential indirect effects from water quality, for example, to heritage resources.
Identified heritage resources near the Project footprint and their associated setbacks will be staked or flagged.
Project personnel will avoid areas that are flagged or fenced and abide by restrictions on in/out privileges that are implemented in areas requiring special protection due to environmentally sensitive features.
In the event that heritage resources not previously identified are suspected or encountered unexpectedly during construction, implement a Chance Find Procedure.
In the event that a previously unidentified heritage resource is suspected or encountered, Wataynikaneyap will contact the applicable First Nation, heritage or archaeology resource specialist, municipality and MTCS, as applicable.
Suspend activity at that location if it has the potential to damage or affect a heritage feature. Work at that location will not resume until permission is granted by Wataynikaneyap in engagement with appropriate regulators, as required.
The resource specialist may deem it necessary to visit the site and will, regardless of whether a site visit is required, develop an appropriate mitigation plan in engagement with Wataynikaneyap, applicable First Nation and the MTCS.
Not significant
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 41
Potential effects on heritage resources are most likely to occur during the construction of the Project. Specifically,
negative effects related to heritage resources can occur as a result of any alteration, relocation, or demolition of
heritage resources. Avoidance of heritage resources during the design and routing phases of the Project will
minimize any potential effects on the heritage resources.
When undertaking projects that may result in the demolition, alteration, or relocation of a heritage
resource, mitigation measures are recommended to avoid or minimize adverse effects on the resources. Typically,
strategies are implemented to avoid and retain a resource in situ, relocate the resource to a suitable location or,
if those options are not feasible, document the resource prior to or during its demolition. By successfully carrying
out these mitigation strategies effects of the Project on heritage resources will be mitigated.
To the extent feasible, temporary workspace will be established in a manner that accommodates the identified
heritage resources (including the features of the cultural heritage landscapes identified at the water crossings for
the Nungesser River, Kirkness Creek and Berens River) to avoid demolition or alteration of their features.
Consultation with the MNRF will be undertaken to ensure best practice for the conservation of heritage features
and determine next steps to be completed.
No residual effects on heritage resources are predicted as a result of the Project construction (Table 3).
Likewise, no interaction between the Project and heritage resources is anticipated during operation. Consequently,
Built Heritage Resources and Cultural Heritage Landscapes was not carried forward in the assessment for
evaluation of significance or considered under the reasonably foreseeable development case assessment.
Reasonably Foreseeable Development Case
No significant effects are predicted for the Project case; therefore a reasonably foreseeable development case
assessment was not completed.
8.4.4 Prediction Confidence in the Assessment
Confidence in the prediction of no significant effects on heritage resources is moderate. The investigation of
heritage resources to be completed for the Project complies with the best practices identified in the Technical
Guideline for Cultural Heritage Resources for Projects Planned Under the Class Environmental Assessment for
MNR Resource Stewardship and Facility Development Projects and the Class Environmental Assessment for
Provincial Parks and Conservation Reserves (MNR 2006).
8.4.5 Follow-up, Inspection, and Monitoring
Consultation with the MNRF will be undertaken to ensure best practice for the conservation of heritage features
and determine next steps to be completed including possible follow-up, inspection or monitoring to address
Built Heritage and Cultural Heritage Landscapes for this project.
8.5 Archaeological Resources Assessment
This section describes and summarizes the archaeological study undertaken for the Project, and presents an
assessment of the effects of the Project on archaeological resources. Archaeological resources include known
and undiscovered archaeological objects, material or physical features that may have cultural heritage value or
interest, and are protected under the Ontario Heritage Act.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 42
The screening for this project is being conducted under the Class Environmental Assessment for MNR Resource
Stewardship and Facility Development Projects and the Class Environmental Assessment for Provincial Parks and
Conservation Reserves. This process is managed by the MNRF which provides guidance for the assessment of
archaeological resources through their Technical Guideline for Cultural Heritage Resources for Projects Planned
Under the Class Environmental Assessment for MNR Resource Stewardship and Facility Development Projects
and the Class Environmental Assessment for Provincial Parks and Conservation Reserves (2006) (MNRF
Technical Guide for Cultural Heritage Resources). Further guidance from the MNRF in Forestry Management
areas comes from their Forest Management Guide for Cultural Heritage Values (2007).
In addition, the archaeological studies undertaken for the Project are in accordance with the Ontario Heritage Act,
and the Standards and Guidelines for Consultant Archaeologists (MTCS 2011).
One criterion (archaeological resources) has been identified to assess the effects of the Project on the
archaeological resources. The rationale and key indicators are summarized in Table 4.
Table 4: Archaeological Resources Criterion, Rationale and Indicators
Criterion Rationale Indicators
Archaeological resources
Archaeological resources are a non-renewable resource that could be affected by Project activities
Archaeological resources have spiritual and cultural importance to First Peoples and to Canadians
Archaeological sites are protected under the Ontario Heritage Act
Number, type and location of known archaeological resources
Area of archaeological potential
The archaeology resources assessment focuses on the following types of archaeological resources
Known archaeological resources: Known archaeological sites are those that have been previously
registered with the MTCS. The known archaeological resources are protected under the Ontario Heritage
Act.
Potential archaeological and cultural resources: Potential archaeological and cultural resources include
any type of site that contains evidence of past human occupation which may be considered by some level of
authority as worthy of protection under a relevant archaeological protection method but has not yet been
evaluated or given formal recognition or protection by a governmental approval agency.
The Ontario Heritage Act provides the provincial government and municipalities the power to preserve and protect
heritage properties and archaeological sites on non-federally owned land within Ontario including both privately
and publically owned lands. Under the Ontario Heritage Act, the MTCS is responsible for the “administration of the
Act and may determine policies, priorities and programs for the conservation, protection and preservation of the
heritage of Ontario”. Prior to any construction activities, a letter of compliance from the MTCS is required which
states that no further archaeological work is required for the Project.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 43
The Ontario Heritage Act defines archaeological resources and the term may also refer to artifacts and
archaeological sites. These are defined as follows:
archaeological resource: an object, material or physical feature that may have cultural heritage value or
interest;
archaeological site: any property that contains an artifact or any other physical evidence of past human use
or activity that is of cultural heritage value or interest; and
artifact: any object, material or substance that is made, modified, used, deposited or affected by human action
and is of cultural heritage value or interest.
Archaeological sites take the form of objects, constructs and landscape changes which have the potential to yield
information on the cultural history of human activities. Sites can take a variety of forms, but generally consist of
artifacts (e.g., pottery and projectile points), soil impressions or alterations identified as features (e.g., postholes
and building footprints) and landscape changes (e.g., construction of mounds and removal of natural forest for
farming). Cultural deposits are typically layered and can be relatively dated (the deeper the deposit, the older its
date) assuming that they have not been previously disturbed. These layers can range in depth from less than a
centimetre to several metres. The excavation of these deposits by an experienced archaeologist will result in an
understanding of the site’s cultural history through the analysis of the spatial distribution of artifacts, including their
relationship to identified cultural features, the nature of a site’s assemblage and the comparison of the site to
similarly dated sites in the region.
Terrestrial archaeology assessment in Ontario involves a multi-stage process to identify and protect archaeological
resources as directed by the Ontario Heritage Act and outlined in the Standards and Guidelines for Consultant
Archaeologists (MTCS 2011). The process followed to meet provincial requirements involves the completion of a
Stage 1 Archaeology Assessment. Based on the results of the Stage 1, the need to complete a Stage 2
Archaeology Assessment, which includes field surveys, will be completed. The Stage 2 assessment will be
required in areas identified as having archaeological potential in the Stage 1 assessment. Stage 3 assessments
are required when an archaeological site is identified but the Cultural Heritage Value or Interest (CHVI) is not
known. Stage 4 mitigation is required when an archaeological site with CHVI has been identified, Stage 4 mitigation
can take the form of block excavation and documentation of the entire site limits that will be impacted; or, it can
mitigated through avoidance and protection.
Underwater archaeology assessment in Ontario involves a permitting process designed to fit the Project
parameters and protect archaeological resources as directed by the Ontario Heritage Act and the MTCS or Parks
Canada, where federal lands such as historic canals are involved. If deemed appropriate, based on discussions
with the MTCS, a marine archaeologist will design a program of background research and field survey, and submit
the program to the MTCS for approval.
8.5.1 Study Area
The LSA which is the limits of work (defined in Section 8.1 and shown on Figure 2) is identified as the study area
for assessing archaeological resource. The LSA is sufficient to address potential direct effects (e.g., destruction
or alteration) and indirect effects (e.g., water quality) from the Project to these resources. Archaeological resources
outside of this study area were also reviewed to provide more of a regional context.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 44
8.5.2 Baseline Characterization (Base Case)
This section provides a summary of the existing environment for archaeological resources based on the desktop
Stage 1 Archaeology Assessment (Stage 1) completed for the Project.
Methods
Information for the archaeological resources Base Case was collected from review of the following sources:
Reports from previously completed archaeological assessments and surveys;
MTCS’s Archaeological Sites Database, which provides information on known archaeological sites in the
Province provided to Golder on 3 May 2017;
MTCS Standards and Guidelines for Consultant Archaeologists (MTCS 2011);
Ministry of Natural Resources and Forestry Technical Guideline for Cultural Heritage Resources for Projects
Planned Under the Class Environmental Assessment for MNR Resource Stewardship and Facility
Development Projects and the Class Environmental Assessment for Provincial Parks and Conservation
Reserves (MNR 2006);
MNRF Forest Management Guide for Cultural Heritage Values (MNR 2007);
Published environmental and topographic literature and maps;
Published document and books related to previous land uses;
Archival documents and secondary sources; and
Aerial imagery.
This baseline characterization follows the process of a preliminary screening using the checklist provided in the
MNRF Technical Guide for Cultural Heritage Resources (MNR 2006), as well as any additional checklist metrics
identified in the MTCS Criteria for Evaluating Potential for Archaeological Potential: A Checklist for the
Non-Specialist (2015). The purpose of the checklist is to determine, through desktop study, whether known or
potential archaeological resources are present in the Project area, and determine if the Project area has potential
for as of yet undiscovered archaeological resources. In addition to the checklists, the MTCS Standards and
Guidelines for Consultant Archaeologist (2011) provides detailed standards and guidelines for determining
archaeological potential. The general criteria for archaeological resources potential is proximity to known
archaeological sites, elevated and well drained topography such as drumlins, eskers, and ancient beach ridges,
navigable water ways (rivers, lakes streams), burial sites or cemeteries, and Aboriginal or local knowledge of
historically documented evidence of past human land use within a given area (resource procurement locations,
areas of spiritual significance, areas along migration corridors, etc.).
A Stage 2 Archaeological Assessment (Stage 2) to determine whether archaeological sites are located within the
Project footprint will be required within all identified areas of archaeological potential outline in the Stage 1
Following the requirements of the MTCS Standards and Guidelines for Consultant Archaeologists, the Stage 2 will
consist of test pit survey within the environment of the project. Test pit survey involves systematically walking the
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 45
property along regularly spaced transects, excavating small pits by hand at regular intervals and examining their
contents.
8.5.3 Results
Known Archaeology Resources
The primary source of information regarding known archaeological sites in the LSA is the MTCS’s archaeological
sites database; available land use planning documentation, and engagement with Pikangikum First Nation,
Wabauskang First Nation and Lac Seul First Nation.
The results indicate that there are four registered archaeological sites within or in close proximity to the study area.
Two sites are located over 2 km from the LSA (EjKl-4 and EgKk-6), one site is located over 1 km from the LSA
(EhKj-1), and one site, EkKk-4, is located within the LSA at the proposed Berens River crossing (Alternative B1).
These sites are further described below.
Outside the LSA:
EgKk-3 – Pre-contact Laurel tradition campsite containing 4 Hudson Bay Lowland chert artifacts and
broken scraper situated on the east side of and island between McKenzie and Bruce Channels on
Red Lake.
EhKj-1: Coli Lake Cabin – Site of unknown period located on the east side of a long northwest facing
peninsula on Coli Lake across from two small islands.
EjKl-4: Kirkness Area 6 – A large multi-component pre-contact and historic site located on a raised
terrace near the outlet to Stormer Lake into Kirkness Lake. The site contained 103 artifacts associated
with the Blackduck, Laurel and Selkirk traditions, as well as Euro-Canadian material.
Within the LSA:
EkKk-4: Berens Lake Portage – Site of unknown age or cultural affiliation located at the western end of
Berens Lake. The site was first identified by Pollock in 1980 during an assessment of the Berens River
watershed. A small lithic scatter was observed on the surface of a heavily utilized portage trail.
No subsurface testing was conducted but it has been intimated that the additional Pre-Contact Aboriginal
cultural material remains intact below the surface.
Potential Archaeological Resources
Numerous criteria are used to determine the potential for Pre-Contact Aboriginal and historical Euro-Canadian
archaeological sites. Key indicators of archaeological potential include proximity to navigable water-courses,
where well-drained soils are present, along glacial features such as drumlins, eskers, moraines, and glacial beach
ridges, railway infrastructure, glacial shorelines, early transportation routes and known archaeological sites as
outlined in the MNRF Technical Guide for Cultural Heritage Resources (MNR 2006) Section 2.2 and Appendix 2;
MNRF Forest Management Guide for Cultural Heritage Values (MNR 2007) Section 3.3 and MTCS Standards and
Guidelines Section 1.3.1 (2011). Section 1.3.3 of the Standards and Guidelines identifies areas in the Canadian
Shield that are distinct from the surrounding environment such as sand and clay plains possess a higher degree
of archaeological potential (MTCS 2011).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 46
Potential archaeological resources that could be found within the study area include:
Aboriginal sites such as campsites, portage areas, canoe spills (i.e., where cargo from canoe was spilt and
not recovered) caches, sacred sites, resource extraction areas and burial sites.
Potential archaeological resources related to historical Euro-Canadian sites, such as logging associated
infrastructure, mining associated infrastructure, early domestic settlement, early industrial infrastructure,
religious centres (e.g., missionary related), cemeteries, single isolated burials, canoe spills, caches, fur trade
associated infrastructure and early recreational infrastructure (e.g., related to tourism).
Petroglyphs, pictographs, petroforms, and guideposts used by both Aboriginal peoples and Euro-Canadian
settlers.
Areas exhibiting low archaeological potential include areas at a distance removed from a feature of archaeological
potential, or those areas where the likelihood of someone actively using the area for subsistence,
resource activities, habitation or spiritual means has been determined to be low; in the Canadian Shield, areas in
excess of 150 m from a feature of archaeological potential are generally considered to exhibit low archaeological
potential (MTCS 2011).
There is a cultural heritage value identified in a communication by the MNRF (Appendix A) that is outside the LSA
where the project ROW has been designed to avoid the value. The cultural heritage value has been identified as
a Thunderbird nest and was photo documented as part of a site visit completed by Wataynikaneyap representative
on August 24, 2016.
The Whitefeather Forest and Adjacent Areas Land Use Strategy identify that Kirkness Lake “is a very special lake
that is the historical location of a summer village for the Pikangikum people” (June 2006). The land use strategy
further identifies that on Kirkness Lake there is evidence for old cabins and tent frames and that archaeological
work guided by Elders have uncovered artifacts dating back thousands of years. In addition, there are accounts of
Thunderbird nests located near the shores of Kirkness Lake. No exact information was provided on the location of
these cultural resources, however the importance of this lake as the summer location for the Pikangikum people
indicates that archaeological resources are probable to be found in close association to the Project area along
Kirkness Creek. Mapping within the land use strategy does not identify Stormer Lake separately from
Kirkness Lake.
Using the sources noted above, in conjunction with a review of LiDAR imagery, MNRF Stream Order and
archaeological potential data and applying MTCS Standards 1.3.3, 1.3.4, and 2.1.5, the Stage 1 Archaeological
Assessment identified a number of areas of archaeological potential that were recommended for Stage 2
Archaeological Assessment. The primary areas requiring Stage 2 Archaeological Assessment are Pindar Creek,
the Nungesser and Kirkness Rivers, and the Berens River crossing at Dog Rib Rapids. In addition to larger creeks
and rivers, there are small sections of Coli and Prideaux Lakes as well as some unnamed ponds where the outside
limits of the LSA overlap with areas of archaeological potential.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 47
8.5.4 Effects Assessment and Mitigation
Project Case
A summary of the potential interactions with Project activities, the potential effects from the Project, recommended
mitigation and the predicted significance of the potential effect to archaeology resources and cultural values is
presented in Table 5.
Table 5: Potential Effects, Mitigation and Net Effects for the Environment on the Project
Indicator Project
Component or Activity
Effect Pathway
Mitigation Measures Description of Net Effect
Archaeological Resources Sites
Site clearing, soil stripping, grading, distribution line installation and post installation site remediation works and maintenance
Loss of or damage to archaeological resource sites
Completion of Stage 2 (and Stage 3 and 4 if required) archaeology assessment on areas identified in the Stage 1 assessment within the Project footprint to determine whether archaeological sites are present and to recommend appropriate mitigation measures should archaeological resources be identified.
Existing roads and trails will be used where possible.
Implement mitigation measures identified in the 2009 INAC screening report to minimize for potential indirect effects from water quality, for example, to archaeology resources.
Identified archaeological resources near the Project footprint and their associated setbacks will be staked or flagged.
Project personnel will avoid areas that are flagged or fenced and abide by restrictions on in/out privileges that are implemented in areas requiring special protection due to environmentally sensitive features.
No clearing or construction activity within flagged or fenced areas that contain archaeological resources.
In the event that archaeological resources not previously identified are suspected or encountered unexpectedly during construction, implement a Chance Find Procedure.
In the event that a previously unidentified archaeological resource is suspected or encountered, Wataynikaneyap will bring in a resource specialist and contact the potentially affected First Nation community and the MTCS.
Suspend activity at that location. Work at that location will not resume until permission is granted by Wataynikaneyap in engagement with appropriate regulators as required.
The resource specialist may deem it necessary to visit the site and will, regardless of whether a site visit is required, develop an appropriate mitigation measures plan in engagement with Wataynikaneyap and, if necessary, the appropriate regulatory agencies.
Collection of archaeological resources by Project personnel is prohibited. Project personnel will be provided guidance prior to construction.
Not significant
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 48
The potential effect on archaeological resources is expressed as the loss or damage to archaeological resources
potentially affected by the Project. As archaeological resources could affect knowledge of regional history and in
compliance with the Ontario Heritage Act, appropriate mitigation measures were identified where potential effects
were anticipated.
Alteration of the landscape can result in damage or destruction of archaeological resources. These alterations
often involve displacement of artifacts resulting in the loss of valuable contextual information. Or alternation of the
landscape may result in the complete destruction of artifacts and features leading to complete loss of ability for
additions to cultural analysis and to First Nations history. Any activity with the potential to cause ground disturbance
may affect archaeological resources unless appropriate steps are taken in advance to identify and either protect
or have the resource properly excavated by a licensed consultant archaeologist, following the recommended
measures in the Standards and Guidelines for Consultant Archaeologists (MTCS 2011).
As described above in Section 8.5.3, areas of archaeological potential, and previously recorded archaeological
sites identified as being culturally important to the people of the Pikangikum First Nation are located within the
LSA. Avoidance and protection of archaeological resource sites is the preferred approach as per the 2011
Standards and Guidelines for Consultant Archaeologists (MTCS 2011). Direct effects can be avoided by identifying
and avoiding archaeological resources prior to ground disturbance, and by increasing the awareness of Project
personnel about archaeological resources in proximity to the Project footprint. Thus, prior to any ground
disturbance, a Stage 2 will be completed on the archaeology sites and areas of archaeology potential to be
disturbed by the Project prior to the start of construction, with the exception of lands that do not retain
archaeological potential or lands previously subject to Stage 1 or 2 archaeological assessments that have been
entered into the public registry. The results of the Stage 2 assessment will be used to identify archaeological
resources and to develop a strategy to mitigate potential direct effects of the Project on these archaeological
resources.
A Stage 3 archaeological assessment will be undertaken if a site of cultural heritage value or interest is identified
as outlined in the MTCS Standards and Guidelines Section 2.2. Stage 3 is a site-specific assessment undertaken
to determine whether the resource warrants protection under the Ontario Heritage Act. A Stage 4 archaeological
assessment will be undertaken if a resource is determined to have cultural heritage value or interest that warrants
protection and cannot be avoided by relocating the Project infrastructure. Stage 4 involves mitigation of
development impacts to conserve the resource. All required archaeological assessments will be undertaken and
clearance for the Project under the Ontario Heritage Act will be obtained prior to any ground disturbance.
The archaeological resource site-specific mitigation summarized in Table 5 and the completion of Stage 2 (or
Stage 3 and 4) and additional mitigation measures identified from these additional stages will be implemented to
avoid and minimize the potential for both direct effects (i.e., loss or damage) and indirect effects on archaeological
resource sites in the archaeological resources in the limits of work. Given the Project planning and recommended
mitigation strategies to minimize direct and indirect effects, significant net effects on archaeological resources are
not predicted as a result of the Project.
At this stage of Project design, there are no Project components currently planned below the high water mark.
However, should design requirements change, the MTCS Criteria for Evaluating Marine Archaeological Potential:
A checklist for Non-Marine Archaeologists will be completed. If the results of the checklist identify that marine
archaeological potential exists within the limits of work; compliance with the Ontario Heritage Act and with the
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 49
MTCS Standards and Guidelines for Consultant Archaeologists will need to be met through the completion of a
Marine Archaeological Assessment.
Reasonably Foreseeable Development Case
No significant effects are predicted for the Project case; therefore a reasonably foreseeable development case
assessment was not completed.
8.5.5 Prediction Confidence in the Assessment
The confidence in the prediction of residual environmental effects on archaeological resources is high, based on
the available information from existing data sources. Confidence in the mitigation for archaeological resources is
also high given that the mitigation and monitoring identified in Table 13, is based on accepted and proven best
management practices identified in the Standards and Guidelines for Consultant Archaeologists (MTCS 2011) and
will be approved by the MTCS.
8.5.6 Follow-up, Inspection, and Monitoring
A Stage 2 (or Stage 3 and 4) archaeology assessment will be required as discussed above. There may be a
requirement for monitoring to follow the mitigation recommendation that would be identified in the Stage 4 report,
if required.
8.5.7 Conclusions
There are no predicted significant effects to archaeology resources from the Project assuming any additional
mitigation identified in the Stage 2 (or Stage 3 and 4) archaeology assessments are implemented by
Wataynikaneyap.
9.0 SUMMARY AND CONCLUSIONS
As discussed earlier in this report, an INAC Screening EA Report and MNRF RSFD screening criteria table were
completed in 2009. This updated PD has focussed on revisions to Project design and resulting potential effects to
the environment, where it differs from the 2009 assessment results; and the scope of the updated PD based on
input from the MNRF. As such, Table 6 provides an updated MNRF criteria table. The table notes where the
assessment results remain the same, assuming implementation of mitigation identified in the 2009 report and
additional mitigation identified in this report.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 50
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Natural Environment Considerations
Air quality New substation location is not located near sensitive receptors, such as a
community.
No change in effects from previous Project proposal.
Positive benefit from decreased reliance on diesel electricity generation
at First Nation communities; thereby decreasing air emissions and greenhouse gases.
As per previous Project proposal.
Water quantity or quality
No change in effects from previous Project proposal.
Decrease in potential negative effect to water quality due to elimination of
submarine crossing of the Berens River. All watercourse crossings will be overhead.
Positive benefit of decreased risk of accidental spills of diesel that could
affect water quality.
As per previous Project proposal.
If required, access roads or water crossings would be
constructed in accordance with MNR’s Environmental Guidelines for Access Roads and Water Crossings (1990).
Follow DFO Measures to Avoid Causing Harm to Fish and
Fish Habitat Including Aquatic Species at Risk (DFO 2016).
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 51
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Species at risk (SAR) or their habitat
Positive benefit with the removal of the submarine crossing of the Berens
River reduces potential direct habitat impact to Lake Sturgeon. Potential temporary crossing at different location on the Berens River. Implementation of the mitigation measures identified under Water Quality and Fish and Aquatic Species reduce potential impacts to Lake Sturgeon.
Wataynikaneyap will implement the identified mitigation measures that
resulted in a low negative effect rating in the MNRF screening and determination of no significance in the federal EA.
See Appendix B for Species At Risk report for baseline, effects
assessment and mitigation for terrestrial species.
For SAR species, except for bats and woodland caribou, the Project
Case and the RFD Case are not predicted to result in significant effects with the implementation of identified mitigation.
Bats - The population at Base Case is predicted to be significantly
affected. However with effective implementation of mitigation, the Project is predicted to have a small but negative effect on the bats, and have no to little contribution to the combined effects from the Base Case. No significant effects are predicted from the Project Case. The RFD Case is conservatively predicted to be significant due to uncertainty associated with future forestry activities, climate change and population demographic rates. However, the Project is expected to contribute little to the significance of RFD Case.
Woodland Caribou - No significant effects are predicted from the Project
Case. The RFD Case is conservatively predicted to be significant due to uncertainty associated with future forestry activities, climate change and population demographic rates. However, the Project is expected to contribute little to the significance of the RFD Case.
Mitigation measures that will be implemented by Wataynikaneyap include the following:
Minimize footprint.
Where possible, avoid areas of sensitive wildlife habitat
(e.g., calving, rearing, denning).
Where possible, implement construction timing windows to
avoid sensitive lifecycle periods (e.g., rearing). (See last bullet).
Where possible, use or follow existing disturbances. The
preliminary proposed corridor follows existing and planned all season roads to the extent practical and will utilize the existing empty utility corridor on the north side of Berens River.
Revegetation of any temporary construction areas to wildlife
end use objectives.
Limits effects of noxious and invasive plants on natural
vegetation.
Limit traffic speed for vehicles during construction.
Use of wildlife-proof waste receptacles.
If required, complete appropriately timed nest and den
surveys in advance of construction clearing.
Additional details on mitigation relevant to terrestrial species are provided in Appendix B Species At Risk report. Additional details on mitigation relevant to Lake Sturgeon are provided under fish or other aquatic species, communities, populations or their habitat heading.
Significant earth or life science features
None identified within the limits of work.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 52
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Fish or other aquatic species, communities, populations or their habitat
Potential temporary crossing at Berens River.
Decrease to negative effects due to elimination of submarine crossing of
the Berens River that could affect fish and other aquatic organisms.
Decreased risk of accidental spills of diesel that could affect water quality
thereby affecting fish and other aquatic organisms.
As per previous Project proposal for aerial water crossings;
including measures for sediment and erosion control, as well as spills prevention and response (this Project will not include fording of waterbodies or watercourses).
If required, access roads or water crossings would be
constructed in accordance with MNR’s Environmental Guidelines for Access Roads and Water Crossings (1990).
If required, implement Department of Fisheries and Oceans
(DFO) Measures to Avoid Causing Harm to Fish and Fish Habitat Including Aquatic Species at Risk (DFO 2016).
For temporary access during construction, use existing
crossing structures or open an ice crossing at the Berens River to avoid work below the high water mark. The restricted activity timing windows are not applicable if all work is completed above the high water mark, or if the waterbody is frozen and an ice crossing is constructed. Restricted activity timing windows are assigned to avoid work during sensitive life history periods or life stages for all fish that may be present in each waterbody, including movements to spawning areas, spawning and egg incubation, or eggs and newly hatched fry.
Minimize clearing of vegetation along the ROW where
possible, especially below the high water mark of the water body. The high water mark will be determined and marked. Clearing of vegetation below the high water mark may need to follow the restricted activity timing window for the water body.
Install and remove the ice crossing in a manner that protects
the banks from erosion.
Other than crossing with the ROW, maintain a buffer (30 m)
around water bodies, watercourses and wetlands to the degree possible.
Land subject to natural or human-made hazards
Not applicable to the Project
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 53
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Recovery of a species under a special management program (e.g., elk restoration)
Woodland caribou, boreal population is under a federal recovery strategy,
Recovery Strategy for the Woodland Caribou, Boreal population (Rangifer tarandus caribou) in Canada (Environment Canada 2012).
Potential effects to woodland caribou and mitigation are provided in
Section B Species at Risk report. No significant effects are predicted from the Project Case. The RFD Case is conservatively predicted to be significant due to uncertainty associated with future forestry activities, climate change and population demographic rates. However, the Project is expected to contribute little to the significance of RFD Case.
Mitigation measures for this Project specific to woodland
caribou identified above under Species At Risk and provided in Appendix B Species At Risk report.
Ecological integrity No predicted change in effects from previous Project proposal. As per previous Project proposal
Additional mitigation measures referenced above under
Species At Risk and provided in Appendix B Species At Risk report related to limiting effects of noxious and invasive plant species (e.g., cleaning and inspection of vehicles and equipment prior to Project site entry/movement to weed free areas; locating and managing cleaning locations on the Project site).
Terrestrial wildlife (including numbers, diversity and movement of resident or migratory species)
No predicted change in effects from previous Project proposal.
Terrestrial species at risk discussed above and in Appendix B Species At
Risk report.
As per previous Project proposal.
Mitigation measures specific to species at risk identified
above under Species At Risk and provided in Appendix B Species At Risk report.
Natural vegetation and terrestrial habitat linkages or corridors through fragmentation, alteration and/or critical loss
No predicted change in effects from previous Project proposal.
No vegetation species at risk located in the limits of work. Terrestrial
species at risk habitat addressed under Appendix B Species At Risk Report.
As per previous Project proposal.
Mitigation measures identified above under Species At Risk
and provided in Appendix B Species At Risk report.
Permafrost No predicted change in effects from previous Project proposal.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 54
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Soil and sediment quality
No predicted change in effects from previous Project proposal. As per previous Project proposal.
If required, access roads or water crossings would be
constructed in accordance with MNR’s Environmental Guidelines for Access Roads and Water Crossings (1990).
Follow DFO Measures to Avoid Causing Harm to Fish and
Fish Habitat Including Aquatic Species at Risk (DFO 2016).
Drainage and flooding
Does not apply to Project.
Sediment or erosion No predicted change in effects from previous Project proposal. As per previous Project proposal.
If required, access roads or water crossings would be
constructed in accordance with MNR’s Environmental Guidelines for Access Roads and Water Crossings (1990).
Follow DFO Measures to Avoid Causing Harm to Fish and
Fish Habitat Including Aquatic Species at Risk (DFO 2016)
Release of contaminants in soils or sediments
No predicted change in effects from previous Project proposal.
Natural heritage features (e.g., areas of natural and scientific interest, provincially significant wetlands)
None located within the limits of work.
Land Use, Resource Management Considerations
Access to trails or inaccessible areas (land or water)
No predicted change in effects from previous Project proposal. As per previous Project proposal.
Discussions with Whitefeather Forest Land Use Strategy
Implementation Team (WFLUSIT) and WFISG will provide consistency between proposed Project and existing strategic direction.
Or obstruct navigation
Does not apply to Project.
Traffic patterns or traffic infrastructure
No predicted change in effects from previous Project proposal.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 55
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Recreational importance – public or private
No predicted change in effects from previous Project proposal.
Or create excessive waste materials
No predicted change in effects from previous Project proposal.
Or commit a significant amount of a non-renewable resource (e.g., aggregates, agricultural land)
Does not apply to the Project.
Noise levels New substation location is not located near a sensitive receptor, such as
a community.
No predicted change in effects from previous Project proposal.
As per previous Project proposal.
Views or aesthetics The Project crosses the DPA, which results in alteration of view that is not predicted to result in significant effects.
Parallel existing or planned structures to minimize visual
effects.
Or be a precondition or justification for implementing another project
The Pikangikum Project is a precondition for implementing the Wataynikaneyap Phase 2: Connecting 17 Remote First Nation communities.
Adjacent or nearby uses, persons or property
No predicted change in effects from previous Project proposal.
Land Use Potential effects to the BDE DPA not addressed in previous assessment.
Potential effects of crossing the DPA are discussed in Section 8.2. No
significant effects on the DPA are predicted from the Project Case and RFD Case.
No predicted change in effects to other land use from previous Project
proposal.
As per previous Project proposal.
Project right-of way aligned to follow existing or proposed
right-of-way and structure through the DPA to minimize potential effects.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 56
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
Social, Cultural and Economic Considerations
Cultural heritage resources – including archaeological sites, built heritage, and cultural heritage landscapes
A Stage 1 Archaeology Assessment has been completed and is included
in Appendix D and summarized in Section 8.5. With the implementation of mitigation measures through the staged assessment process, no significant effects are predicted from the Project Case.
Potential effects to built heritage and cultural heritage landscapes are
addressed in Section 8.4. There is no built heritage within the limits of work. There will be Project clearing required within the DPA that will affect the cultural heritage landscapes within the DPA. However, the Project clearing will be adjacent to existing or proposed right-of-way minimize the linear corridor intrusion into the cultural heritage landscape. No significant effects to the cultural heritage landscapes are predicted from the Project Case.
Mitigation measures that will be implemented by Wataynikaneyap include the following:
Complete Stage 2 (or Stage 3 and 4) archaeology
assessments.
Project clearing will be adjacent to existing or proposed
right-of-way minimize the linear corridor intrusion into the cultural heritage landscape.
Implement a Chance Find Procedure during construction.
Continue to engage with First Nation communities during
construction.
Or displace people, businesses, institutions, or public facilities
Not applicable to the Project.
Community character, enjoyment of property, or local amenities
No predicted change in effects from previous Project proposal.
Or increase demands on government services or infrastructure
Not applicable to the Project.
Public health or safety
No predicted change in effects from previous Project proposal.
Local, regional or provincial economics or businesses
No predicted change in effects from previous Project proposal.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 57
Table 6: Update to Potential Effects as Compared to Previous Proposal, and Proposed Mitigation
Environment Potential Effects as Compared with Previous Proposal Proposed Mitigation
No predicted change in effects from previous Project proposal.
Aboriginal Considerations
First Nation Reserves or Aboriginal communities
No predicted change in effects from previous Project proposal. As per previous Project proposal.
Sacred, spiritual or ceremonial sites
Wataynikaneyap engaged with First Nation communities to identify
traditional land and resource use activities, site or values within the limits of work that could be affected by the Project (see Section 8.5 Archaeology and Record of Engagement).
Through design changes and proposed mitigation, potential effects of the
Project on identified activities and sites have been avoided or minimized.
No significant effects are predicted from the Project case.
Wataynikaneyap incorporated traditional land and resource
use activities, sites and values into Project design to avoid or minimize potential effects.
A sensitive site was identified by a member of Wabauskang
First Nation within the limits of work. Wataynikaneyap has worked with this community member to identify and implement appropriate mitigation to avoid potential effects to this site.
A member of Lac Seul First Nation expressed their desire to
have the power line shift to the opposite side of the road in a particular area. Wataynikaneyap evaluated the request and was unable to make the requested change. Wataynikaneyap remains open to discussion with the community member.
Wataynikaneyap will continue to engage with First Nations to
incorporate Project design changes, to the extent practical, should additional traditional land and resource use activities, sites or values be identified within the limits of work that could be affected.
Traditional land or resources used for harvesting, activities
Aboriginal values
Lands subject to land claims
Not applicable to the Project.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 58
10.0 POTENTIAL PERMITS AND APPROVALS
Table 7 provides a summary of potential permits and approvals.
Table 7: Summary of Potential Permits and Approvals from Provincial and Federal Agencies and Other Organizations
Agency Applicability to the Project
Provincial
Ministry of the Environment and Climate Change (MOECC)
Ontario Water Resources Act: Water Taking Regulation O. Reg. 387/04 Permit to Take Water
if Project construction requires taking more than 50,000 litres (L) in a day from a lake, stream, river or groundwater source.
Ontario Water Resources Act: Section 53 Environmental Compliance Approval (ECA) for
Industrial Sewage Works. An ECA may be required for the wastewater treatment systems (leaching beds) at the temporary camps.
Environmental Protection Act: Section 9 ECA for Waste Disposal. An ECA may be required for
the storage, transportation and disposal of domestic and industrial wastes, including sewage, from the temporary construction camps.
Environmental Protection Act: Section 9 or Section 27 Environmental Compliance Approval (ECA) for Noise and Vibration may be required for operation of the substation.
A Generator Registration Number is required under O. Reg. 347 of the Environmental Protection Act in the event Hazardous and Liquid Industrial Wastes are generated during Project construction.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 59
Table 7: Summary of Potential Permits and Approvals from Provincial and Federal Agencies and Other Organizations
Agency Applicability to the Project
Provincial
Ministry of Natural Resources and Forestry (MNRF)
Permit under Section 17 of the Endangered Species Act, 2007 if the project affects a listed species or its habitat.
Authorization under the Fish and Wildlife Conservation Act, 1997 in the event Project
construction/operation is anticipated to destroy the nests or eggs of birds, a beaver dam, or the den of a black bear or some furbearing mammals, or interfere with a black bear in its den. Fish and Wildlife Scientific Collector permits for pre-construction surveys to relocate if needed.
Forest Resource Licence (Cutting Permit) is required to harvest and/or cut timber on Crown land under the Crown Forest Sustainability Act, 1994. A discussion with the Whitefeather Forest Community Resource Management Authority will determine if Crown timber cleared under the FRL can be sent to a processing facility.
Burn Permit under the Forest Fires Prevention Act (1990) to enable burning of materials from
forest clearing, if required.
Work Permits under the Public Lands Act (1990) to authorize works on public lands and/or
shore lands including geotechnical investigations, construction/upgrade of access roads and trails, culverts/bridges, and distribution lines.
Land Use Permits required for distribution line, access roads (to and within the Project site) and for temporary laydown and/or spoil areas. The holder of Land Use Permits will be Wataynikaneyap Power L.P.
Approval under Section 20 of the Provincial Parks and Conservation Reserves Act (2006).
Work permits and land use permits under the Provincial Parks and Conservation Reserves Act
(2006) for any activities noted in the Act, regardless of whether lands are occupied under the authority of a lease, land use permit or licence of occupation.
Aggregate Permit under the Aggregate Resources Act (1990) to extract aggregate on all
Crown Land.
Licence of Occupation under the Public Lands Act (1990) as construction works are to occur
on Crown lands.
Crown Lease may be required under the Public Lands Act (1990) for proposed transformer
station. This will require Ontario Crown Land Surveyor engagement and survey instructions from Red Lake office.
Ontario Ministry of Transportation (MTO)
Under the Public Transportation and Highway Improvement Act, the following permits may be required:
An Entrance Permit is required for any entrance onto a provincial highway, including a temporary entrance to construct or service such a proposed development;
A Building and Land Use Permit is required for any development/construction occurring within 45 metres (m) of the right-of-way (ROW) limit of any provincial highway, within 180 m of the intersection of a side road and a “King’s” highway; within 395 m of a controlled access highway; and for any power or distribution line within 400 m of a controlled access highway;
An Encroachment Permit is required for any work within, under, or over a provincial highway ROW;
A Sign Permit is required for all signage erected within 400 m of the limit of a provincial highway; and
Permit/Agreement to occupy the ROW.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 60
Table 7: Summary of Potential Permits and Approvals from Provincial and Federal Agencies and Other Organizations
Agency Applicability to the Project
Provincial
Ontario Ministry of Labour
Notice of Project under Section 23(2) of the Occupational Health and Safety Act (1990).
Ontario Ministry of Tourism, Culture and Sport (MTCS)
Archaeological assessment, to be conducted by a licensed archaeologist as part of the EA under the Ontario Heritage Act (1990) and submitted to the Ontario Public Register of Archaeological Reports. Built heritage and cultural heritage landscape screening and, where required, heritage impact assessments (HIAs) submitted to the MTCS for review under Ontario’s Environmental Assessment Act.
Ontario Energy Board (OEB)
Approval of Leave to Construct application may be required.
Federal
Environment Canada Permit under Section 73 of the Species at Risk Act (2002) should any Project activities occur on federal lands (including First Nations Reserve lands) and affect a species listed under the Species at Risk Act, or its habitat.
Fisheries and Oceans Canada (DFO)
Authorization under the Section 35 of the Fisheries Act (1985) for harmful alteration, disruption and/or destruction of fish and fish habitat, related to in-water works such as blasting, cofferdam construction and/or diversion of water flows.
Self-Assessment completed by Wataynikaneyap Power to determine if the project is likely to affect a Commercial, Recreation or Aboriginal Fisheries and therefore subject to a Project Review or Authorization.
Transport Canada Lighting and marking requirements under the Canadian Aviation Regulations Standard 621 – Obstruction Marking and Lighting in the event the distribution line is located in the vicinity of an airport and could interfere with air navigation.
Indigenous and Northern Affairs Canada (INAC)
Section 67 of the Canadian Environmental Assessment Act, 2012.
Indigenous and Northern Affairs Canada (INAC) must authorize activities on First Nations Reserve lands by means of Section 28(2) of the Indian Act whereby: “The Minister may by permit in writing authorize any person for a period not exceeding one year, or with the consent of the council of the band for any longer period, to occupy or use a reserve or to reside or otherwise exercise rights on a reserve.”
Other
Local Municipality Building Permits in accordance with Building Code Act (1992) and by-laws of relevant municipality.
Municipality of Red Lake - By-Law No. 1083-08 - Noise Exemption if construction work for the Project is expected to make noise between 9 pm and 7 am, a noise by-law exemption will be required.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738 61
11.0 REFERENCES
B. J. Tworzyanski Limited and Keewatin-Aski Ltd. 2009. Pikangikum 115 kV Transmission Line (Operated at
44 kV): Technical Specifications and Drawings.
Fisheries and Oceans Canada (DFO). 2016. Measures to avoid causing harm to fish and fish habitat including
aquatic species at risk. http://www.dfo-mpo.gc.ca/pnw-ppe/measures-mesures/measures-mesures-
eng.html
Environment Canada. 2012. Recovery Strategy for the Woodland Caribou (Rangifer tarandus),
Boreal population, in Canada. Species at Risk Act Recovery Strategy Series. Environment Canada,
Ottawa. xi + 138pp.
Hamilton, Scott and Taylor-Hollings, Jill 2010. Stage 1 Archaeological Assessment of the Proposed Berens River
Bridge Crossing at Dog Rib Falls and Associated Road Extensions in the Whitefeather Forest,
Northwestern Ontario. Consultant’s Report Submitted to the Ministry of Tourism and Culture. PIF #
P276-010-2010.
INAC. 2009. Environmental Screening Report – Canadian Environmental Assessment Act. Indian and Northern
Affairs Canada.
McKenzie Forest Products Inc. 2011. Forest Management Plan for the Lac Seul Forest, Sioux Lookout District –
Northwest Region, For the 10-Year Period from April 1, 2011 to March 31, 2021.
MNR. 1990. Environmental Guidelines for Access Roads and Water Crossings.
PIKANGIKUM DISTRIBUTION LINE PROJECT UPDATED PROJECT DESCRIPTION
August 2017 Project No. 1657738
Report Signature Page
GOLDER ASSOCIATES LTD.
Karen Saunders, MES, R. P. F.
Environment and Aboriginal Engagement Specialist
Allen Eade
Senior ESIA Specialist, Associate
ASE/KB/AB/wlm
Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation.
https://golderassociates.sharepoint.com/sites/10323g/shared documents/project description/1657738-r-reva-2017may31-pd-pikangikum distribution line project.docx