Pikangikum First Nation School Capital Planning Study Community Information Presentation
Mar 29, 2015
Pikangikum First NationSchool Capital Planning
Study
Community Information Presentation
Community’s New School …… Moving Fast Forward
Pikangikum First Nation’s NEW SCHOOL
Funding Commitment From Aboriginal Affairs and Northern Development
Project Overview
What Grades Levels Will Be Taught At The New School?• Kindergarten K4 & K5• Elementary Grades 1 to 8• High School Grades 9 to 12
How Many Students Will the New School Accommodate?• The New School will Accommodate Over 900 Students and will have provisions for future expansion.
Project Overview
What Will Be the Size of The New School?• The New School Will Be Over 90,000 square feet. That is equivalent to 5 NHL Hockey Rinks
+ + + + = NEW SCHOOL
How Much Will It Cost to Build?• The New School will cost over $50 Million
Project Overview
What will be Included in the New School?
8 – Kindergarten Rooms 14 – Grades 1-3 Classrooms
10 – Grades 4-6 Classrooms 4 – Grades 7-8 Classrooms
6 – Grades 9-12 Classrooms Aboriginal Studies Room
Religious Studies Room 2 – Science Laboratories
Library / Resource Computer Lab
Music & Drama Room Art Room
Two Cafeterias (Elementary + Senior) Two Gymnasiums (Elementary + Senior)
Family Studies / Food & Fashion Room Manufacturing Shop
Construction Shop Special Needs Room
Health Room Staff Room
Native Language Coordinator Office Guidance Counsellor Office
Administration Offices Education Storage
Project Overview – Site Location
New School Site
Project Overview
School Site Fly-By…
School Development Schedule
• Performance Specifications for New School
• Nov 4 to Jan 20, 2014
• Design-Builder Selection Competition
• Jan 21 to Apr 30, 2014
• New School Design and Construction
• May 1, 2014 to Aug, 2016
• New School Open• September 2016
K-12 School Site Plan
NOTESECOND GYM
and CAFETERIA NOT SHOWN
Next Steps
• The School Study Which is Now Being Finalized Has Triggered the Design and Construction Stages
Finalize Study
• Owner’s Consultant Coordinates Retaining a Design-Build Firm
• Manages Quality Control For Design and Construction
Owner’s Consultant
• Detailed Design• Construction
Hire Design Builder
Chief & Council welcome your input
on theNEW SCHOOL
PROJECT