Upgrade Phase 2 Mechanics meeting, 21 March 2013 Introduction

Post on 17-Feb-2016

34 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

DESCRIPTION

Upgrade Phase 2 Mechanics meeting, 21 March 2013 Introduction. Agenda of this meeting Tracker Layout and Module concepts Overall planning Collaboration between design teams, meetings. Agenda. Tracker layout and module concepts. Barrel + Endcap. Long Barrel. 2S modules. PS modules. - PowerPoint PPT Presentation

Transcript

1

Upgrade Phase 2 Mechanics meeting, 21 March 2013Introduction

Upgrade Phase II Mechanics, 21 March 2013, indico: 240514 Antti Onnela, CERN

Agenda of this meeting Tracker Layout and Module concepts Overall planning Collaboration between design teams, meetings

2

Agenda

Upgrade Phase II Mechanics, 21 March 2013, indico: 240514 Antti Onnela, CERN

3

Tracker layout and module concepts

Long Barrel

Upgrade Phase II Mechanics, 21 March 2013, indico: 240514 Antti Onnela, CERN

PS modules

2S modules

Barrel + Endcap

2S, 2-Strip modulesR > 600 mm

PS, Pixel-Strip modules R > 200 mm

VPS, Pixel-Strip modules with Vertical interconnections

R > 200 mm

4

Overall planning

Upgrade Phase II Mechanics, 21 March 2013, indico: 240514 Antti Onnela, CERN

Conceptual design, studies on materials, technologies

, cooling

D. Abbaneo

First major milestone: TP in autumn 2014Describe a mechanics concept (consistent with the proposed detector layout!), with detector modules, support and cooling structures, services arrangements. Also initial plans on how the detector can be constructed, assembled, tested and commissioned.

5

Collaboration between design teams, meetings

Until the upgrade project has chosen between the proposed, different Tracker layout concepts, the mechanics design work needs to continue on all of them.

Mechanics design teams should collaborate to:1. Identify and share common topics (e.g. choice of adhesives, cooling pipe material and connection

techniques)2. Allow for cross-checks between designs3. Avoid duplication of work4. Avoid leaving topics completely or poorly covered.

Collaboration between the design teams:1. Use Web-accessible data storages

Common ones: https://espace.cern.ch/Tracker-Upgrade/SitePages/Home.aspx and EDMS (both need a brush-up!)+ Storages maintained by each design team

2. Hold Phase 2 Mechanics meetings every ~2 months. See next slide for 2013 CMS calendar.

3. Hold a Review on the Phase 2 Mechanics in summer-autumn 2013.4. And of course email and phone.

Upgrade Phase II Mechanics, 21 March 2013, indico: 240514 Antti Onnela, CERN

6Upgrade Phase II Mechanics, 21 March 2013, indico: 240514 Antti Onnela, CERN

N.B. During CMS Weeks difficult to

find time for Upgrade meetings

?

??

?

?

Mechanics Review?

top related