Technology June 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Briefing

1. Monthly StatusBriefingJune 2012 2. Project Background The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safelydestroy 2,611 tons of mustard agent in mortar…

Documents September 2012 PCAPP Monthly Status Briefing

1. Monthly StatusBriefingSeptember 2012 2. Project Background The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safelydestroy 2,611 tons of mustard agent…

Business PCAPP Monthly Status Briefing - September 2011

1. Monthly StatusBriefingSeptember 2011 2. Project Background The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safelydestroy 2,611 tons of mustard agent…

Business PCAPP Monthly Status Briefing November 2011

1. Monthly StatusBriefingNovember 2011 2. Project Background The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safelydestroy 2,611 tons of mustard…

Documents August 2012 PCAPP Monthly Status Briefing

1. Monthly StatusBriefingAugust 2012 2. Project Background The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safelydestroy 2,611 tons of mustard…

Documents December 2012 PCAPP Monthly Status Briefing

Monthly Status Briefing December 2012 Project Background  The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611 tons of mustard agent in…

Technology April 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Briefing

Monthly Status Briefing April 2012 OPSEC Completed 12 April 2012 Project Background  The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611…

Technology May 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Briefing

Slide 1 Monthly Status Briefing May 2012 OPSEC Completed 14 May 2012 Project Background The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611…

Business PCAPP Monthly Status Briefing December 2011

Monthly Status Briefing December 2011 OPSEC Completed 08 December 2011 Project Background  The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy…

Government & Nonprofit PCAPP Update 30 April 2014

Slide 1 PCAPP Update 30 April 2014 Safety As of March 31, 2014 PCAPP staff has accomplished: 704 Safe Work Days 3,870,185 Safe Work Hours VPP Application Submitted 2 2 Staffing…