TTRRAANNSSPPOORRTT
World Bank transport program in Vietnam
Transport Sector
World Bank, Hanoi, Vietnam
TTRRAANNSSPPOORRTT
Transport program in Vietnam
• Overview• Changing Program
Objectives• Present status of
program• Future directions
TTRRAANNSSPPOORRTT
Overview
• Why transport? – Key issue for foreign investors: Poor Quality and Lack of Capacity of
Transport Infrastructure– Poverty Reduction: Improvements to rural infrastructure have directly
reduced poverty– Economic Growth: High levels of public investments required to
support rapid growth • The Program.
– Program is about $1 billion of projects under implementation and $ 1 billion of projects under preparation
– The program is growing and Vietnam is the only country in EAP where Bank budgets are increasing
– Vietnam is moving from IDA to IBRD status as a result the WB is increasing its support to large scale infrastructure projects
TTRRAANNSSPPOORRTT
Changing Program Objectives
• Reconnection– In the ’90s projects supported the need to reinstate the
main transport links, particularly national roads. This work is largely completed.
• Integration– The focus of projects started to move beyond
‘emergency works’ towards building sustainable transport networks. This work is still ongoing.
• Expansion– With over 10 years of high growth, the capacity of the
transport network is inadequate.
TTRRAANNSSPPOORRTT
5
Projects under Implementation
Project Approved Closing AgeIDA
approved (US$m)
Current Amount (US$m)
Disbursed to date [1]
(US$m)
Percentage disbursed
(%)
Mekong Transport & Flood Protection
FY01 12/10 8.5 110 132 117 86.22
MTFP Addit’l Financing
FY07 12/10 2 25 25 18.3 29.02
Road Network Improvement
FY04 09/10 5.5 225 241 105.8 42.91
Road Safety FY05 06/11 4.3 32 32 5.1 15.44
Rural Transport III FY06 12/11 3.5 106 114 27.8 23.85
Mekong Delta Transport Infrastructure Development
FY07 12/13 2.3 207 211 9.1 4.19
Hanoi Urban Transport
FY08 12/13 2.0 155 156 7.2 4.48
Northern Delta Transport Development Project
FY08 6/14 1.0 170 164 -- --
[1] AS of January15, 2010
TTRRAANNSSPPOORRTT
Projects under implementation
• Issues:– WB program suffers from slow disbursement progress.– Disbursements are low for up to 2 years on approval.
There is a need for the identification of funding, and the timely preparation of projects.
– Provincial projects are increasingly decentralized which increases the complexity and capacity building is key
– According to WB guidelines we cannot use dependent SOE consultants and contractors. Therefore we need to work closely with the emerging private sector and capacity building is key.
– Most projects require substantial resettlement activity which is expensive and time consuming
TTRRAANNSSPPOORRTT
Projects under preparation
• Road Network Improvement Project (Additional Financing) (FY11) – US$ 230m
• Da Nang-Quang Ngai Expressway (FY11) – IBRD US$500m/IDA US$70m: First transport IDA/IBRD blended operation.
• Haiphong Urban Transport (FY11) - US$150-175 m
• Third Rural Transport AF (FY11) – US$50m
• Project Preparation Facility (FY10) – US$75m
TTRRAANNSSPPOORRTT
Projects under preparation
• Issues:– WB used to prepare projects using PHRD grant but
this is no longer available– All preparation work is government executed typically
using government and/or grant finance– Limitations of existing institutional and capacity terms
of identifying, planning, and implementing projects.– Institutional arrangements to bring together planning,
implementation, and operation of assets needs to be improved
– Need to widen sources of funding, possibilities for PPP type arrangements in transport projects
TTRRAANNSSPPOORRTT
Policy and Strategy work
Bank Budget • Vietnam Expressway Investment Strategy – implementation to commence
in FY10• Infrastructure finance – Looks at different financing options, in particular
PPP, for infrastructure development
Infrastructure for Growth Trust Fund (AusAID) • State-Owned Enterprise and Construction Industry Review (US$125,000) • Preparation work for Danang to Quang Ngai Expressway (US$350,000)• Monitoring and evaluation study for two multi-modal transport projects
(US$100,000)• International Road Assessment Program (iRAP Vietnam) (US$ 400,000)• Urban Transport in Medium Cities (US$150,000)
TTRRAANNSSPPOORRTT
Policy and strategy work
Infrastructure Policy & Sector Support Trust Fund (DFID)
• Rural Transport Support – US$250,000
• Transport Sector Support – US$300,000
• Infrastructure policy and research activities – US$275,000
TTRRAANNSSPPOORRTT
Thank you!