5
Today’s Agenda
§ CALGreen – What is it?
§ A review of key sections§ Residential§ Q & A§ Commissioning§ Non-Residential § Q & A§ Tiers Process§ Q & A
6
California Code of RegulationsTITLE 1. GENERAL PROVISIONSTITLE 2. ADMINISTRATIONTITLE 3. FOOD AND AGRICULTURETITLE 4. BUSINESS REGULATIONSTITLE 5. EDUCATION-------
TITLE 24. BUILDING STANDARDS CODE
7
Title 24: 2010 California Building Standards Code (effective January 1, 2011)
Part 1 – California Administrative CodePart 2 – California Building CodePart 2.5 – California Residential CodePart 3 – California Electrical CodePart 4 – California Mechanical CodePart 5 – California Plumbing CodePart 6 – California Energy CodePart 7 – VacantPart 8 – California Historical Building CodePart 9 – California Fire CodePart 10 – California Existing Building Code
Part 11 – California Green Building Standards CodePart 12 – California Referenced Standards Code
9
§ Chapter 1 - Administration
§ Chapter 2 - Definitions
§ Chapter 3 - Green Building
California Green Building Standards Code
10
§ Chapter 4 - Residential Mandatory Measures
§ Chapter 5 - Nonresidential Mandatory Measures
§ Chapter 6 - Reference Organizations and Standards
§ Chapter 7 - Installer and Special Inspector Qualifications
§ Chapter 8 - Compliance Forms and Worksheets
California Green Building Standards Code
11
§ Appendix A4 – Residential § Tiers and Electives & Checklists
§ Appendix A5 – Non-Residential§ Tiers and Electives & Checklists
California Green Building Standards Code
13
Chapter 1 - Administration§ (101.1) Title§ (101.2) Purpose§ (101.3) Scope
§ Mandatory only for new construction§ Buildings covered – state-owned, low-rise residential (up
to 3 stories), nonresidential/commercial, public elementary & secondary schools, community colleges, hospitals,
§ Not intended to be identified as meeting the requirements of a point rated system
§ (101.4) Provisions in the Appendices (Tiers) are voluntary unless made mandatory by local jurisdiction
§ (101.5) Referenced codes and standards
14
Chapter 1, continued
§ (101.6) Order of precedence and use.§ (101.7) Local amendments based on findings
§ Climate – Topography – Geology – Environmental§ (101.8) Alternate Materials and Methods§ (101.9) Effective date – January 1, 2011§ (102) Construction Documents & Installation Verification§ (103 - 106) State Agency Authorities
15
Chapter 2 – Definitions
§ If used in more than one location in the code a defined term will be located in Chapter 2.
§ If only used in one chapter the defined term will be located in the definition section at the beginning of that chapter.
16
Chapter 3 - Green Building§ Newly constructed buildings
§ Mixed Occupancy Buildings - comply with appropriate requirements for each separate occupancy type.
§ Phased Projects
§ Voluntary Tiers§ Tier 1 and Tier 2
17
Why a CalGreen Code?
n 2004: California Green Building Initiative (EO S-20-04): n 20% electricity reduction in state-owned buildings by 2015.
n 2006 - Global Warming Solutions Act (AB 32): n Reduce GHG emissions to 1990 levels by 2020.
n Buildings: 2nd largest contributor to GHG emissions.
n 2007 – Bills on green building standards in state legislature.
18
By the year 2035, three-quarters of the built environment will be new or renovated.
Source: Architecture 2030
A Historic Opportunity
20
3%
12%
15%
19%
23%
28%
Dishwashing Leaks Faucets Bathing Laundry Flushing
CA Residential Water Use
21
California Building Standards Commission (CBSC)
§ Independent Commission
§ State & Consumer Services Agency
Development and Adoption
22
California Building Standards CommissionChair
§ Secretary of the State and Consumer Services Agency
Commissioners (10)§ One architect§ One mechanical, electrical or fire protection engineer§ One structural engineer§ One licensed contractor§ Three public members, at least one a person with disabilities§ One member from organized labor in the building trades§ One local building official§ One local fire official
23
CBSC Responsibilities
§ Review building standards proposed by state agencies
§ Develop building standards for occupancies where no other state agency has the authority - non-residential
§ Adopt and approve building standards for publication
§ Codify approved building standards
§ Contract to publish the California Building Standards Code
§ Act as the state depository for local government modifications
27
Timeline
§ 2008 Voluntary measures, Aug. 1, 2009
§ 2010 Mandatory standards, adopted Jan. 12, 2010
§ City & County Adoption, Mandatory standards effective Jan. 1, 2011
§ Next adoption cycle: address additions, remodels, high-rise residential
29
Timeline, Mid-term code amendments2010 CALGreen effective 1/1/2011
Submit initial amendments 12/1/2010
Publication date 1/1/2012
Amendments effective 7/1/2012
32
• State Housing LawThe SHL was enacted to protect the health, safety and general welfare of the public and occupants of dwelling units in the State of California. Under this authority, HCD promulgates building standards and regulations to ensure that hotels, motel, apartments, single-family dwellings, and other residential buildings are constructed and maintained in compliance with the model building codes and other provisions of State law.
California Department of Housing and Community Development
33
California Department of Housing and Community Development
HCD AuthorityHotels, MotelsApartment HousesDwellingsLodging HousesHomeless SheltersMonasteries, ConventsEmployee HousingFactory-Built Housing
34
Five Divisions
§ Division 4.1 - Planning and Design
§ Division 4.2 - Energy Efficiency
§ Division 4.3 - Water Efficiency and Conservation
§ Division 4.4 - Material Conservation and Resource Efficiency
§ Division 4.5 - Environmental Quality
Chapter 4 - Residential Mandatory Measures
36
Adopting State Agencies
§ California Building Standards Commission (CBSC)
§ The Department of Housing and Community Development (HCD)
§ Division of the State Architect (DSA)
§ Office of Statewide Health Planning and Development (OSHPD)
38
§ Less than one acre outside the scope of the California State Water Resources Control Board (SWRCB).
§ Will help prevent flooding of adjacent property and prevent pollution from storm water runoff by retaining soil on-site or by providing filtering to restrict sedimentation from reaching storm water drainage systems and receiving streams or rivers.
§ Establishes criteria for a plan to manage storm water drainage during construction.
4.106.2 - Storm water drainage and retention
Chapter 4
39
How to comply§ Retention basin sized and
shown on the site plan.
§ Filtering storm water and routing to a public drainage system.
§ Compliance with local storm water ordinance.
4.106.2 - Storm water drainage and retention
Chapter 4
40
§ Requires planning of the surface drainage system that will serve the site.
§ Requires the construction plans to indicate how surface drainage will be managed.
4.106.3 Surface Drainage
Chapter 4
41
How to comply§ Drainage system is shown on site plan.
§ Swales
§ Drain piping
§ Retention areas
§ Ground water recharge
4.106.3 Surface Drainage
Chapter 4
45
4.201.1 - Minimum Energy Performance for Low-Rise Residential Buildings.
§ The California Energy Commission (CEC) adopts regulations to establish the minimum level of energy efficiency that a heated or cooled structure must meet or exceed.
Chapter 4
46
4.201.1 - Energy Efficiency
How to comply§ Prescriptive Method
§ Performance Method
§ Tiers
§ Performance calculation can show percentages above minimum
Chapter 4
49
4.303.1 - 20% Water savings
§ Requires a 20% reduction of indoor water use.
§ Provides a prescriptive and performance method.
Mandatory effective date for 20% reduction is July 1, 2011
Concerns over availability of fixtures and performance
Chapter 4
50
4.303.1 - 20% Indoor water savings
How to comply method #1Prescriptive Method
§ Table 4.303.2
§ Showerheads ≤ 2.0 gpm @ 80 psi
§ Lavatory Faucets ≤ 1.5 gpm @ 60 psi
§ Kitchen Faucets ≤ 1.8 gpm @ 60 psi
§ Urinals ≤ .5 gal/flush
§ Waterclosets ≤ 1.28 gallon effective flush rate
Chapter 4
51
4.303.1 20% - Indoor water savingsHow to comply method #2Performance Method
§ Use the performance calculation worksheets in Chapter 8 or other calculation acceptable to the enforcing agency.
§ Fixtures used in performance calculation are limited.
§ Water closets
§ Urinals
§ Lavatory Faucets
§ Showerheads
Chapter 4
52
4.303.2 - Multiple Showerheads Serving One Shower
§ The sum of multiple showerheads shall not exceed the flow rate specified in Table 4.303.2 (2.0 gpm @ 80 psi), or the shower shall be designed for only one showerhead to operate at a time.
§ Exception: When using the performance method, the maximum flow rate for multiple showerheads shall not exceed 2.5 gpm @ 80 psi.
Chapter 4
53
4.303.3 Plumbing Fixtures and Fittings
§ Specifies acceptable performance standards for plumbing fixtures with reduced water usage.
Chapter 4
54
4.303.3 - Plumbing Fixtures and Fittings
How to comply§Install a fixture that meets the standards listed in Table 4.303.3.
§Obtain alternate approval from the enforcing agency for use of fixtures not listed.
Chapter 4
56
4.304.1 - Irrigation Controllers
§ Requires irrigation controls to be weather- or soil moisture-based and automatically adjust irrigation in response to changes in plants’ needs as weather conditions change, or have rain sensors or communication systems that account for local rainfall.
Chapter 4
57
4.304.1 - Irrigation Controllers
How to comply§Applies to controllers installed at time of final inspection.
§Automatically delay watering cycle due to rain.
§Can be communication based.
§Can be based on plant watering needs.
§Can be based on soil moisture.
Chapter 4
59
4.406.1 - Joints and Openings
§ Establishes a requirement to fill spaces around pipes and other penetration in the building with materials that will prevent the passage of rodents.
Chapter 4
60
4.406.1 - Joints and Openings
How to comply§Use metal plates or covers.
§Use cementitious material to seal opening.
§Other methods approved by the enforcing agency.
Chapter 4
61
4.408.1 through 4.408.2.2 - Construction Waste Reduction, Disposal and Recycling
§ Requires at least of 50% of nonhazardous construction and demolition debris to be recycled and/or salvaged, or;
§ Compliance with a local waste ordinance which is more stringent.
§ Exceptions:§ Soil and land clearing debris are exempt.
§ Alternate methods or exceptions may be approved due to local constraints.
Chapter 4
62
4.408.1 through 4.408.2.2
How to comply§Comply with local waste management ordinance.
§Develop a waste management plan and submit for approval to the enforcing agency.
§Provide documentation of compliance.§ HCD is developing additional forms.
§ Sample forms are provided in Chapter 8.
Chapter 4
63
4.410.1 - Building Maintenance and Operation
§ Requires educational materials, operation and maintenance manuals are provided to ensure buildings and equipment are properly maintained.
§ Other information such as landscape design and maintenance, public transportation options, recycle opportunities, special inspection reports, and energy incentive programs.
Chapter 4
64
4.410.1 - Building Maintenance and Operation
How to comply§Develop a manual and place it in the home at the time of final inspection.
§Media shall be approved by the enforcing agency.
§HCD is developing a sample standard format for the manual.
Chapter 4
65
4.410.1 - Building Maintenance and Operation
Chapter 4
State provided format:
http://www.hcd.ca.gov/CALGreen.html
67
4.503.1 - Fireplaces
Requires gas fireplaces to be direct-vent, wood and pellet stoves to comply with EPA limits or comply with a local ordinance, whichever is more prohibitive.
Chapter 4
68
4.503.1 - Fireplaces
How to comply§Install direct vent gas fireplaces.
§Install a pellet or wood stove which meets US EPA Phase II emission standards.
§Comply with local ordinance.
Chapter 4
69
4.504.1 - Covering of Duct Openings and Protection of Mechanical Equipment During Construction
Requires duct openings, permanent mechanical equipment and other components that will be used to move air in the building after occupancy to be protected from contamination during construction.
Chapter 4
70
4.504.1 - Covering of Duct Openings and Protection of Mechanical Equipment During Construction
How to comply§Cover return and supply openings with plastic or sheet metal.
§Wrap or protect equipment stored on the jobsite for future installation.
§If necessary, plan for alternate space conditioning systems during construction.
Chapter 4
72
4.504.2 - Finish Material Pollutant Control
Limits pollutants from the off-gassing of finish materials inside a residence.
Tables are provided that establish limits on the emissions of VOCs in adhesives, paints, and other coatings.
VOC limitations are also included for carpet, carpet cushions and carpet pad adhesives.
Chapter 4
73
4.504.2 - Finish Material Pollutant Control
§ A table addressing the formaldehyde limits was developed based on maximum allowable limits recently established by the California Air Resources Board (ARB).
§ Ensures these levels are met by including a mandatory verification component which requires certification or documentation.
Chapter 4
74
4.504.2 - Finish Material Pollutant Control
How to comply§Collect material specification sheets and make them available at time of inspection.
§Product labels.
§Use the specification sheet HCD is developing as a compliance aid for this section.
Chapter 4
75
4.505.2 - Concrete Slab Foundations
§ Provides explicit requirements for the installation of vapor barriers in slab on grade foundations to address moisture and mold issues that can negatively affect indoor air quality as well as damage floor coverings.
§ Allows equivalent methods to be used provided the same protections will be maintained.
Chapter 4
76
4.505.2 – Concrete Slab Foundations
How to comply§Follow the prescriptive requirements in this section.
§Obtain approval from the enforcing agency for an alternate design.
§Use the design specified by a licensed California architect or engineer.
§Specifies an aggregate base of ½” or larger material must be used as a capillary break and clarifies that the vapor retarder must be placed above the aggregate and in direct contact with the concrete slab.
Chapter 4
77
4.505.3 - Moisture Content of Building Materials
§ Requires the moisture content of construction materials and insulation to be verified prior to approval to enclose wall and floor cavities with drywall or other finish surfaces.
§ HCD currently adopts sections of the CBC which specify maximum grading and mill certification levels of moisture in framing materials.
§ This section requires field verification and protection during wet weather.
Chapter 4
78
4.505.3 – Moisture Content of Building Materials
How to comply§Cover building materials to protect them from rain.
§Ensure the building is weather tight before insulating.
§Use other precautions necessary to ensure the building materials are kept dry.
§Test for moisture levels.
Chapter 4
79
4.506.1 - Bathroom Exhaust Fans
§ Requires exhaust fans in any room that contains a bathtub or shower and exhaust directly to the outside.
§ Unless acting as a whole house ventilation system.§ Fans must be ENERGY STAR compliant.§ Humidistat controls.§ R303.3 Bathroom 3sq.ft. 50% openable
Chapter 4
80
4.506.1 - Bathroom Exhaust Fans
How to comply§Install a whole house ventilation system.
§Install ENERGY STAR fans with humidistat controls in each bathroom.
§A bathroom is a room that contains a bathtub or a shower or a combination of the two.
Chapter 4
81
4.507.1 – Openings – Whole House Fans
§ If a whole house fan is installed requires the louvers or covers to have a minimum insulation of R-4.2.
Chapter 4
82
4.507.1 - Openings – Whole House Fans
How to comply§ Insulate louvers or covers to R-4.2
§ Install a fan with an insulated R-4.2 cover.
§ Use a fan with insulated duct connected to penetrations in the conditioned envelope.
Chapter 4
83
4.507.2 - Heating and Air-conditioning System Design
§ Establishes minimum requirements for heating and air conditioning design.
§ Heat loss and heat gain.Duct system sizing.
• Equipment selection.
§ Allows designers flexibility to design based on local conditions.
Chapter 4
84
4.507.2 - Heating and Air-conditioning System Design
How to comply§Heat loss and heat gain calculation using software or hand calculations or an equivalent.
§Duct system design to ensure adequate air flow is provided to address the heat loss and gain in each area of the home.
§Select equipment which will provide the necessary air flow and level of conditioning to satisfy the loads, function within the duct design criteria and within the equipment limitations.
Chapter 4
86
702.1 - Installer Training
§ Establishes minimum requirements for heating and air conditioning installers.
Chapter 7
87
702.1 - Installer Training
How to comply§Certification or training as a HVAC systems installer through a program acceptable to the enforcing agency.
§Work is performed under the direct supervision of a person with acceptable training.
§Examples are provided.
Chapter 7
88
702.2 - Special Inspection
§ Establishes minimum requirements for third party inspectors acting on behalf of the enforcing agency.
§ Similar to structural special inspections.
Chapter 7
89
702.2 - Special Inspection
How to comply§Demonstrate competence to the enforcing agency in the discipline being inspected.
§No financial interest in the project.
90
Chapter 8Compliance Forms and Worksheets
§ Sample forms for construction waste management plans.
§ Water use worksheets.
§ More compliance forms will be added.
98
§ Lawrence Berkeley Laboratory
§ 10 years
§ 643 buildings
§ 26 states
§ 100 million sq. ft.
National Study
99
Median commissioning costs: $1.16 per sq. ft. for new construction, 0.4% total construction costs.
13% Median energy savings
National Study
100
§ Capital costs savings from “right-sizing” equipment.
§ Averts premature equipment failure.
§ Improves worker comfort.
§ Ensures building owners get what they paid for.
§ Detects and corrects problems that would eventually surface as long-term maintenance or safety issues.
Commissioning Benefits
101
§ Buildings under 10,000 sq. ft.
§ Balancing of HVAC systems
§ Verification of Compliance
Commissioning Requirements
102
§ Buildings 10,000 sq. ft. or more§ Owner’s or Owners Representative’s Project
Requirements (OPR)§ Basis of Design (BOD)§ Commissioning plan§ Functional performance testing§ Documentation and training§ Systems manual§ Systems operations training§ Verification of compliance§ Commissioning report
Commissioning Requirements
1044/26/2011
Visit VCA Web Site at
www.vcagreencode.com
for
Commissioning solutions
or email
VCA Green Code
106
Five Divisions§ Division 5.1 - Planning and Design§ Division 5.2 - Energy Efficiency§ Division 5.3 - Water Efficiency and Conservation§ Division 5.4 - Material Conservation and Resource
Efficiency§ Division 5.5 - Environmental Quality
Chapter 5 Non-Residential Mandatory Measures
107
5.102 - Storm water soil-loss prevention plan § State Storm water NPDES Construction
Permit 99-08-DWQ
§ Local Ordinance
§ No State permit is required
§ BMP’s approved by local agency
Chapter 5
Division 5.1 – Planning and Design
108
5.106.4 – Bicycle parking
§ Short-term bicycle parking spaces = 5% of visitor vehicle parking capacity
§ Long-term bicycle parking = 5% of total tenant-occupant vehicle parking capacity
Chapter 5
109
§ Stall marking for 8% of total parking capacity (ref: table 5.106.5.2)
§ Vehicles defined in Section 5.102
§ Not necessarily preferential location
Chapter 5
5.106.5.2 – 5.106.5.2.1Designated parking for clean air vehicles
110
5.106.8 - Light pollution reduction§ Reference the California
Energy Code lighting standards
§ Exceptions for emergency lighting and security
5.106.10 - Grading & paving§ Keep surface water from
entering building§ Grading shown on
construction plans
Chapter 5
112
Division 5.2 – Energy Efficiency
§ Mandatory Measures are Regulated by the California Energy Commission
§ Mandatory provisions are found in Part 6 of Title 24
Chapter 5
113
Division 5.3 – Water efficiency and conservation
Indoor Water Use
§ 5.303.1 - Separate water meters
§ Buildings in excess of 50,000 square feet where tenants use more than 100 gallons per day
§ Excess consumption more than 1,000 gallons per day
Chapter 5
114
Division 5.3 - Water efficiency and conservation
Indoor Water Use
§ 5.303.2 - 20% Savings of potable water§ Performance or prescriptive standards, using tables
5.303.2.2 or 5.303.2.3
§ Multiple showerheads serving one shower
§ Wastewater reduction of 20%
§ Standards for plumbing fixtures and fittings
§ Standards referenced in Table 5.503.6
Chapter 5
115
5.304 - Outdoor Water Use§ Water budget – Currently required
by DWR or local agency for landscapes 2,500 square feet and over
§ Separate meter for outdoor potable water use for landscape areas between 1,000 & 5,000 square feet
§ Irrigation design for landscapes between 1,000 to 2,500 square feet
Chapter 5
Division 5.3 - Water efficiency and conservation
116
5.407 - Water Resistance and Moisture Management§Exterior weather protection currently in Title 24 or by local ordinance
§Design for moisture control
§Prevent spray from sprinklers on structures
§Prevent entries and openings from water intrusion
Chapter 5
Division 5.4 – Material conservation and resource efficiency
117
5.408 - Construction Waste Reduction, Disposal and Recycling
§Construction waste diversion –establish a waste management plan
§Construction waste management plan (WMP)
§Documentation (see sample forms in Chapter 8)
§Exception for isolated jobsites
Chapter 5
Division 5.4 – Material conservation and resource efficiency
118
§ Construction waste reduction of at least 50%
§ Exception to allow alternate waste reduction method
§ 100% of excavated soil and land clearing debris
Chapter 5
5.408 - Construction Waste Reduction, Disposal and Recycling
120
5.410 – Building Maintenance and Operation
§ Recycling by occupants – required by law since 1991
§ Sample ordinance
Chapter 5
121
Division 5.5 – Environmental Quality
5.503 - Fireplaces
§ Direct-vent sealed gas fireplaces
§ Sealed wood-burning fireplaces
§ Wood burning stoves
Chapter 5
122
5.504 - Pollutant Control
§ Covering of duct openings
§ Protection of mechanical equipment during construction
Chapter 5
Division 5.5 – Environmental Quality
123
5.404 - Finish material pollutant control(low VOC-emitting products)§Adhesives and sealants and caulks§Paints and coatings§Aerosol Paints and Coatings§Carpet systems, including cushion and carpet adhesives§Composite wood products – formaldehyde limits, Air Resources Board standards§Resilient flooring – 50% of resilient flooring§Verification of compliance may be record of product data or other methods acceptable to the enforcing agency
Chapter 5
Division 5.5 – Environmental Quality
124
§ 504.5.3 - Air filters at least MERV 8
§ 5.504.7 - Environmental tobacco smoke control –outdoor areas for smoking
§ Local ordinance may apply
Chapter 5
Division 5.5 – Environmental Quality
125
5.505 - Indoor Moisture Control
§ Reference Title 24, Part 2, CBC Section 1203 and Chapter 14
5.506 - Indoor Air Quality § Outside air delivery - by California Energy Code, local
code, or Title 8, whichever is more restrictive§ Carbon dioxide (CO2) monitoring – for buildings with
demand control ventilation per the California Energy Code
Chapter 5
Division 5.5 – Environmental Quality
127
5.507 - Environmental Comfort
§ Acoustical Control based on ASTM E90 and ASTM E413
§ Exterior noise transmission – depends on project location
§ Interior sound – minimum STC 40 for separations
Chapter 5
Division 5.5 – Environmental Quality
128
5.508 - Outdoor Air Quality
§ Ozone depletion and greenhouse gas reductions
§ No Chlorofluorocarbons (CFCs)
§ No Halons
Chapter 5
Division 5.5 – Environmental Quality
129
DSA – Green Code for K-14 schools
• The DSA used the Building Standards Commission’s (BSC) Green Code as a basis to determine what provisions would apply to public schools and community colleges
• Additional vetting of proposals was done with the DSA Advisory Board’s Green Committee, CASH, and CHPS
• For an overview of the mandatory and voluntary provisions, see the Application Checklist DSA-SS in Chapter A5 appendix
• DSA-SS provisions do not have “tiers” for voluntary reach standards as shown in the BSC application checklist for commercial buildings
• Mandatory measures do not apply to every new construction or modernization project; see the Administration Chapter 1, Section 105 for specifics
• Resources on DSA Website www.dsa.dgs.ca.gov
130
• Grading and Paving
• Minimum Energy Code
• 20% Indoor Water Savings
• 20% Wastewater Savings
• Weather Protection
• 50% Construction Waste Reduction
• Recycling areas
• Covering of duct openings during construction
• Low VOC materials
• Merv 8 Filters
• Sustainable Sites
• Energy Efficiency
• Water Efficiency
• Materials & Resources
• Indoor Environmental Quality
• Grid neutral = production/consumption
• 35%• 75%• 100%
DSA-SSMandatory Voluntary
133
For localities that wish to adopt more stringent standards than the mandatory measures.
Meant to assist the state in achieving its greenhouse gas emission and net zero energy goals.
Tier 1 and Tier 2
134
Meet mandatory requirements.
Meet prerequisites for each Chapter – as outlined in Appendix A4 (residential) and Appendix A5 (nonresidential).
Implement the required number of “elective” measures for each Chapter, as noted in A4 and A5.
Local jurisdiction sets final policy.
Reaching Tier 1 or Tier 2
135
Pass an ordinance to adopt Appendix chapters as is or local amendment.
Must be approved by CEC before sending to CBSC.
Tier 1 and Tier 2: Adopting
137
Tier 1 Prerequisites, Residential: examples§ Exceed CEC 2008 Energy Efficiency Standards by 15%
§ 65% reduction in construction waste
§ 20% permeable paving
§ 10% recycled content
§ Cool roof – meet Tier 1 Solar Reflective Index requirement
§ Reduced flow rate for kitchen sink faucets: max = 1.5 gallons per minute at 60 psi
§ 20% cement reduction
138
Tier 1 Elective Requirements - Residential
At least two Planning and Design elective measures (Div A4.1)
At least four Energy Efficiency elective measures (Div A4.2)
At least one Water Efficiency and Conservation elective measure (Div A4.3)
At least two Material Conservation and Resource Efficiency elective measures from (Div A4.4)
At least one Environmental Quality elective measure (Div A4.5)
139
Tier 2: Note
The measures for Tier 2 status are very stringent.
Cities, counties and cities and counties considering adoption of Tier 2 as mandatory should carefully consider the stringency of each measure and ensure that the measures are achievable in their location.
140
Tier 2 Prerequisites, Residential: examples§ Exceed CEC 2008 Energy Efficiency Standards by 30%
§ 75% reduction in construction waste
§ 30% permeable paving
§ 15% recycled content
§ Cool roof – meet Tier 2 Solar Reflective Index requirement
§ Reduced flow rate for kitchen sink faucets; dishwasher must be Energy Star compliant, 5.8 gals per cycle max.
§ 30% cement reduction
141
Tier 2 Elective requirements, Residential
§ At least four Planning and Design elective measures
§ At least six Energy Efficiency elective measures
§ At least two Water Efficiency and Conservation elective measures
§ At least four Material Conservation and Resource Efficiency elective measures
§ At least one Environmental Quality elective measure
142
§ Meet all mandatory requirements.
§ Meet Tier 1 or Tier 2 prerequisites.
§ Comply with additional elective measures as follows:§ 10 electives for Tier 1§ 17 electives for Tier 2
§ Application Checklist§ Mandatory provisions§ Provisions required for compliance with tiers
Tiers – Residential Summary
145
Tier 1 Prerequisites, Nonresidential: examples
§ Exceed CEC code by 15 percent
§ 30 percent water savings
§ 65 percent construction waste reduction
§ 10 percent recycled materials (% of materials cost)
§ Cool roof meets Tier 1 SRI standard
§ Designated parking – 10 percent of total spaces for fuel efficient vehicles
+ 5 electives
146
Tier 2 Prerequisites, Nonresidential: examples
§ Exceed CEC code by 30 percent
§ 35 percent water savings
§ 80 percent construction waste reduction
§ 15 percent recycled materials (% of materials cost)
§ Cool roof meets Tier 2 SRI standard
§ Designated parking – 12 percent of total spaces for fuel efficient vehicles
+ 15 electives
147
§ Meet all mandatory requirements.
§ Meet Tier 1 or Tier 2 prerequisites.
§ Comply with additional elective measures as follows:§ 5 electives for Tier 1§ 15 electives for Tier 2
§ Application Checklist§ Mandatory provisions§ Provisions required for compliance with tiers
Tiers – Nonresidential Summary
152
How to comply § Review CALGreen guide§ State generated docs§ Understand intent
§ Consult with local building official§ Local generated docs§ Local amendments§ Local guidelines
Comparison
154
Commissioning (Cx) comparison
CALGreen Commissioning§ 10,000 sq. ft. § One level
LEED Commissioning§ Two levels§ Fundamental Cx seeking certificate§ Can equal CALGreen
§ Enhanced Cx
Comparison
155
Commissioning (Cx) comparison
LEED Fundamental Cx seeking CALGreen compliance§ CALGreen requires§ Irrigation system§Water reuse§ System documentation§ System training
160
www.bsc.ca.gov
California Building Standards Commission
162
www.bsc.ca.gov
California Building Standards Commission
163
www.bsc.ca.gov
California Building Standards Commission
Non-Residential Guide
164
California Department of Housing and Community Development
www.hcd.ca.gov
165
California Department of Housing and Community Development
www.hcd.ca.gov
Guide to the California Green Building Standards Code(Low-Rise Residential)
166
California Department of Housing and Community Development
www.hcd.ca.gov
Partial list of HCD compliance docs
167
More Resources
4/26/2011
Whitepaper
Complimentary CALGreen WhitepaperProvides:
•Information for Cities, Architects,and Developers
•Current State information•Valuable resources•Assist with implementation ideas•Helps design professionals to met
city requirements
Email: [email protected]
169
October 17-19, 2011 Pasadena Convention Center
April 18th: In-depth CALGreen Commercial & Residential Workshops as part of the Pre-Summit Curriculum at the Green CA Summit