Contract Transitions - Responsibility Notes for the Incumbent
- Tracy Dorsey/PMP
PM Challenge 2012Feb 22nd-23rd
2
Welcome and General Agenda
Background
General Timeline
• Transition Environment (Staff, Support companies, Customers/Projects)
• Core Transition Responsibilities
General message – We should all care and help ensure successful contract transitions. It’s not just the successors responsibility
‘Parental Style Mindset’ – Release your tasks, projects and transitioning staff as if you were sending them off to college. Well equipped and knowing that you want them to succeed.
3
Background and Company Snapshot Relative to Topic
Personal Experience• Began working in 1984 at GSFC since 1989 Employed by SGT
Inc. • Masters – Space Systems Engineering• Held many roles supporting NASA – Currently Program
Manager MSES IIA contract at Goddard Space Flight Center
Stinger Ghaffarian Technologies• Founded in 1994; Headquartered in Greenbelt, MD• 1,600 employees: engineers, scientists, IT professionals• Key Customers– NASA
– Goddard Space Flight Center
– Ames Research Center– Glenn Research Center– Stennis Space Center– Langley Research
Center– Johnson Space Center– Kennedy Space Center
– NOAA– Department of
Transportation– Air Force Space
Command– USGS
Science 5%
Program Management
10%
Engineering 61%
IT 24%
4
Transition Environment – The Framework
Timing• Contracts generally turn over every 5 -7 years• Transitions will not be in alignment with supported Projects• Procurement schedules generally won’t be fixed
Variables: Procurement delays, protest, etc.
Contractor and Staffing Mix• Some transitions and contracts can be very large and complicated• Uncertainties of employees through the process• Most likely new mixture of contractors on succession vehicle• Incumbent contractor is likely pursuing the follow-on contract in some
fashion
For the purposes of this presentation – it’s assumed the incumbent will transition follow-on the contract to a successor contractor
5
Continuity of Services ClauseFAR 52.237-3
CONTINUITY OF SERVICES (JAN 1991)(a) The Contractor recognizes that the services under this contract are vital to the Government and must be continued without interruption and that, upon contract expiration, a successor, either the Government or another contractor, may continue them. The Contractor agrees to—(1) Furnish phase-in training; and (2) Exercise its best efforts and cooperation to effect an orderly and efficient transition to a successor.(b) The Contractor shall, upon the Contracting Officer’s written notice, (1) furnish phase-in, phase-out services for up to 90 days after this contract expires and (2) negotiate in good faith a plan with a successor to determine the nature and extent of phase-in, phase-out services required. The plan shall specify a training program and a date for transferring responsibilities for each division of work described in the plan, and shall be subject to the Contracting Officer’s approval. The Contractor shall provide sufficient experienced personnel during the phase-in, phase-out period to ensure that the services called for by this contract are maintained at the required level of proficiency.(c) The Contractor shall allow as many personnel as practicable to remain on the job to help the successor maintain the continuity and consistency of the services required by this contract. The Contractor also shall disclose necessary personnel records and allow the successor to conduct on-site interviews with these employees. If selected employees are agreeable to the change, the Contractor shall release them at a mutually agreeable date and negotiate transfer of their earned fringe benefits to the successor.(d) The Contractor shall be reimbursed for all reasonable phase-in, phase-out costs (i.e., costs incurred within the agreed period after contract expiration that result from phase-in, phase-out operations) and a fee (profit) not to exceed a pro rata portion of the fee (profit) under this contract.(End of clause)
6
General Timeline
Stage 1• Phase 1) Proposal Development and Submissions
Varied timeframes as companies pursue opportunities approaching release
Synopsis, Industry Day(s), RFI, customer visits, Draft RFP, RFP• Phase 2) Board Assessments
6-9 months• Phase 3) Award Announcement and contract start
Unprotested transition could start immediately (after the debriefs)
Stage 2• Phase 4) Transition
30, 45, 60 and 90 variations (for bulk of contracts)
Stage 3• Phase 5) Contract Execution by Successor
Dependent on opportunity (5-8 years)
7
Incumbent Responsibilities (Stage 1)
Phase 1: Proposal Development and Submission
Stressors: – Proposal input, writing and reviewing demands– Project timelines don’t change due to proposal schedule– Current operating team may not be teammates on follow-on efforts
» Information, working styles and visibility practices may be adjusted near the end of an executing contract.
On contract (Incumbent) Responsibilities– Ensure current work continues at a high level (technical and management)– Increase communications with staff – technical and management level
flows. Contract performance should never be compromised – Ensure follow-on contract teaming arrangements don’t adversely affect
ongoing contract performance
8
Phase 2: Board Assessments
Stressors: – Hallway rumors, expectations, realities of contract ending, employee
uncertainties
On Contract Responsibilities– Continue communications to executing team, continue to stress focus on
assigned task and commitments. – In most cases technical incumbent team will not be adversely impacted by
a transition – convey the message.– Begin to refine preparatory documents that will be needed for transition
» Task lists, staffing list, property list, ITAR documents and critical project schedules.
» Have a checklist for every task, work with your NASA Technical Monitors
Incumbent Responsibilities (Stage 1)
9
Incumbent Responsibilities (Stage 1)
Phase 3: Award Announcements
Stressors– Realities of contract ending are cemented– Employee uncertainties have peaked if communications have been
lagging
On Contract Responsibilities– Meet with your current COTR/CO and make sure everyone is on the same
page with regard to the transition– Generate a proposed schedule for phase out activities– Work with your current Civil Servant Task monitors
» Descopes and expectations» Task continuations on succession vehicle (lose visibility but you still
have obligations to your current staff. Is everyone getting picked up on the follow-on vehicle)
» Realize and help staffers manage change (Internally and/or attending open houses of successor)
10
Incumbent Responsibilities (Stage 2)
Phase 4 On Contract Responsibilities
• The Transition
Stressors: – Employee uncertainties, some early staff movements are realistic
to assume– Continue efforts to ensure no interruptions in work or
performance– Maintain trust with current customers through the last day– Follow-on contract may not be straight forward succession
11
Working the Transition (Core Transition Team Makeup)
Civil Servant Team (most likely will consist of)
Contract Manager or ownerContracting Officer (CO)Contracting Officer's Technical
Representative (COTR)Resource Analyst (RA)Representatives from other Major-Use
OrganizationsChief Information Officer's (CIO)
Information Technology (IT) PersonnelSecurity Personnel
• Entity ensures the governments best interest is maintained and serves as official executer of the transition
• Should work very closely with incumbent in ensuring a readiness posture for the transition. A close relationship will usually yield the most effective set of information and possibilities for a smooth transition.
Incumbent Contractor TeamProgram ManagerBusiness ManagerContracts ManagerCorporate assigned Transition
Manager
• Execute transition to governments satisfaction
• Execute transition consistent with FAR 52.237-3 – Continuity of Services (JAN 1991)
12
Working the Transition
On Contract Responsibilities and more elements
Schedule a meeting with the govt, your transition manager and the successor • Handle requests as appropriate (i.e. current support, contractor team mix, meet
weekly)Finalize Inventory for everything on contract task
• Staffers, subcontracts, equipment, badges• Readdress and Review critical schedules or milestones• Document and prepare to disposition all technical equipment, intellectual
property, software, data, licenses and customized scripts that will be transferred.
Identify all contractor-owned technical equipment, intellectual property, software, data, and end items that must be removed from NASA facilities and ensure the government understands
Establish a definite check-out procedure for all incumbent contractor employees, technical equipment, intellectual property, software, data, and end items that reside on or at a government facility.
Facilitate subcontract phase out procedures• Dependent on size of contract this could be a large effort
13
On Contract Responsibilities and more elements
Task monitors to need access dependencies which might cause some tasks not to transition on day one
– Large procurement in process, TAA’s, Critical phase of a projects– All successor transition teams aren’t equal– Understand your existing task values as it relates to EAC
» Government will need to obligate funding to new vehicle
Additional Notes– Training – Certification information where appropriate (if any key records held
outside of Satern) – IT Security (Badge transfer process – some badges may not be transferred)– Clearances (Transfers may have to occur- corp and Govt. security need to be
involved)– ITAR and TAA (3-6 month process)– Property (GFE listing)– Final task reports
» add element to final monthly (disposition all deliverables and property held under task order)
Working the Transition
14
Incumbent Responsibilities (Stage 3)
Phase 5 On Contract Responsibilities
• Contract Execution by Successor Stressors:
– You and your Business Manager are the only ones left
Responsibilities– Complete any remaining final task reports– Final 533’s, Close up trailing costs and invoice processing – Execute any remaining tasks due lagging issues (ie ITAR, Critical schedules
or government’s convenience)
15
Transition Success has to be focused goal
Transition Environment is complex• (Staff, Support companies, Customers, Projects)
Transition Elements and Core Responsibilities
Make it a success and everybody wins in a variety of ways
Conclusion
• Thanks (Shelley Johnson/SGT and MSES Management Team)
• Questions, Comments ?