YOU ARE DOWNLOADING DOCUMENT

Please tick the box to continue:

Transcript
Page 1: T.Chirica - Forum Invest Financing Crisis And Nuclear

1

FINANCING CRISIS AND NUCLEAR

ENERGY REVIVAL

Dr. Teodor CHIRICA, Director General & CEO

NUCLEARELECTRICA SA

12TH

of NOVEMBER 2008

BUCHAREST, ATHENEE PALACE

ENERGY IN CENTRAL AND

EASTERN EUROPE

Page 2: T.Chirica - Forum Invest Financing Crisis And Nuclear

CONTENTS

• International Context - Status and

Projections

• Romania – Nuclear Energy Today and New

Developments - Cernavoda 3 & 4

• Nuclear Energy Vulnerabilities, the

Economic Crisis and Mitigation of Risks

• Conclusions

• References

Page 3: T.Chirica - Forum Invest Financing Crisis And Nuclear

3

INTERNATIONAL CONTEXT

Interest in new nuclear power is being pushed by (a)

growing energy demand, (b) energy supply security,

and (c) concerns over climate change;

Main issues:

– Consolidation: about six countries able to export

complete nuclear power plants — Canada, France,

Japan, Russia, South Korea and the US;

– Unbalance between demand and offer;

– Re-start after a long slow-down period:

Lack of production capacity for some critical

components;

Deficit of experienced work-power.

– Increasing cost of the investment;

– Recent crisis impact on costs;

– Technology: Transition to the Third Generation.

Page 4: T.Chirica - Forum Invest Financing Crisis And Nuclear

4

STATUS AND PROJECTIONS

STATUS:

June 2008: 439 nuclear power units/ operating

in 30 countries/ total capacity of 372 GW

2.6 billion MWh: 16% of the world’s electricity

OECD/NEA PROJECTIONS:

The NEA has projected global nuclear capacity

to 2050 using low and high scenarios. The

outcome is:

By 2050, global nuclear capacity is projected to

increase by a factor of between 1.5 and 3.8.

Under the high scenario, the nuclear share of

global electricity production would rise from 16%

today to 22% in 2050.

Page 5: T.Chirica - Forum Invest Financing Crisis And Nuclear

5

JAN 2008

NUCLEAR – 17%

FEB 2008

NUCLEAR – 16%

MAR 2008

NUCLEAR – 18%

ROMANIA – NUCLEAR ENERGY TODAY

IV/2008 - ENERGY STRUCTURE

Page 6: T.Chirica - Forum Invest Financing Crisis And Nuclear

NUCLEARELECTRICA: 10 YEARS OF

SUCCESSFUL OPERATION!

CERNAVODA NPP - UNITS 1 & 2

Cernavoda 1 & 2 operational data: 2007 – SEP 2008

Unit MWe Energy Production

(MWh brut)

Capacity Factor

[%]

Lifetime

CF [%]

2007 IX/ 2008 2007 IX/2008

C# 1 706.5 5,518,346 3,654,999 97.62 79.20 87.90

C# 2 706.5 961,986 4,463,461 93.23 96.40 95.80

706.5 MW(e)

UNIT # 1 UNIT # 2

704.8 MW(e)

Feb MarJan May JunApr Aug SepJul Nov DecOct

UNIT # 1UNIT # 2

Page 7: T.Chirica - Forum Invest Financing Crisis And Nuclear

NUCLEARELECTRICA SA

CERNAVODA NPP

UNITS 1 & 2

PROJECT COMPANY

PCO

UNITS 3 & 4

NUCLEARELECTRICA:

OPERATION & MAINTENANCE

INVESTORS

100%51%49%

NUCLEARELECTRICA - CERNAVODA 3 & 4

SHARING A SITE!

Page 8: T.Chirica - Forum Invest Financing Crisis And Nuclear

Cernavoda 3 & 4 PROJECT ESTIMATED COST

Unit Installed

capacity

(MWe)

Technology Estimated

Budget

Expected

Commissioning

Date

C# 3 720 CANDU-6 EUR about

4.0 Billion

2015

C# 4 720 CANDU-6 2016

NUCLEARELECTRICA - CERNAVODA 3 & 4

PROJECT ESTIMATED COST

Cernavoda NPP 3 & 4: 2.5 billion Euro cost 2004/ 4.0 Billion

2008;

Duke Energy (US): two Westinghouse AP1000 of 2234 MWe:

4 – 6 Billion US$ cost 2005/ $11 billion, excluding financing

costs and inflation cost 2008 (WNN, 07 November 2008);

South Carolina (US) – VC Summer NPP: $9.8 billion price for

two Westinghouse AP1000s cost 2008 (Nucleonics Week,

Volume 49 / Number 22 / May 29, 2008

Page 9: T.Chirica - Forum Invest Financing Crisis And Nuclear

9

Capital construction for Power Projects costs

increased by 100% between I/2005 and IV/2007,

but:– Falling commodity prices due to an anticipated

economic slowdown, may reverse the trend of quickly

rising nuclear power plant construction costs;

– A slowdown in the global economy or a recession could

reduce the labor costs as well.

Financing costs – impact of the economic crisis;

Public opinion is veering in favor of nuclear

power even in countries with moratorium or

phase-out laws due to safe operation record and

better communications efforts;

NUCLEAR ENERGY VULNERABILITIES:

COSTS AND PUBLIC OPINION

Page 10: T.Chirica - Forum Invest Financing Crisis And Nuclear

2008 EUROBAROMETER

Page 11: T.Chirica - Forum Invest Financing Crisis And Nuclear

11

No significant impact over operating units;

Impact on capital spending, financing difficult to

obtain, and financing costs would be higher, for

new nuclear constructions, but:

– Companies’ plans not affected, but some delays are to be

expected;

– Main Projects are at an early stage and by the time of

financial close, two or three years away, is expected the

markets to recover;

– Earliest start of Cernavoda 3 and 4: 2010 - 2011.

The fundamentals of energy demand will support

the nuclear revival despite the financial crisis:

– Nuclear energy represents for Romania a least cost

option, main contributor to security of supply strategy

and CO2 reduction: Cernavoda 3 & 4 and next NPP;

– Interest of Investors to stay in the Project.

IMPACT OF THE FINANCING CRISIS

Page 12: T.Chirica - Forum Invest Financing Crisis And Nuclear

12

Different situations for nuclear plant financing:

– Loan guarantees to secure financing (ex. DOE

guarantees provided to regulated utilities in US);

– Parent companies support of back-up PPA provided to

unregulated commercial generating plant - require more

equity and less debt, and greater security for debt;

– ―Investment‖ through partnerships of varied companies,

like Finnish cooperative Teollisuuden Voima Oy (TVO) - in

which TVO is using proceeds from its existing two

reactors, plus the third once it is finished, to repay debt).

Project finance – NOT AGREED BY THE BANKS for

Nuclear Projects;

The financial crisis can be expected to influence

the European debate on energy market rules, such

as loan guarantees or other - EU rules currently

prohibit state aid except in certain circumstances.

STRUCTURING FINANCING

Page 13: T.Chirica - Forum Invest Financing Crisis And Nuclear

13

Promoters of two new nuclear projects in Europe

have abandoned attempts at pure project financing:

– Bulgaria - the Bulgarian Energy Holding: merge of

NEK, Kozloduy NPP and other 3 companies,

allows cash flows from operation to support debt

service for the new VVERs to be build at Belene:

– BEH: €4.3bn assets and annual revenues more than €1.8bn;

– Romania - the original standalone project to build

Cernavoda 3 & 4 has been converted into one

where the government will take 51%, based on

high portion of equity financing, increasing the

project’s financeability:

Compliance with EU competition rules to be demonstrated

(the market economy operator test);

Turkey’s recent attempt to start its first NPP with

project financing failed, as only one vendor

submitted a valid bid;

STRUCTURING FINANCING (cont’d)

Page 14: T.Chirica - Forum Invest Financing Crisis And Nuclear

14

Cost uncertainties associated with past nuclear

construction projects may add a premium of 3%-

5% to financing of nuclear plants compared to

other power plants:

– Lenders may also require further protection

such as government guarantees;

Ex. DOE’s loan guarantee program is designed to

promote innovative generation technologies that have

little or no greenhouse gas emissions - the

department is authorized to provide $18.5 billion in

loan guarantees for new reactor construction;

– Sponsors and lenders are worried about a

revenue shortfall that could arise from project

delays and financing cost overruns.

RISKS MITIGATION

Page 15: T.Chirica - Forum Invest Financing Crisis And Nuclear

15

Use of principles such as shared investment and

phased financing could mitigate that risk:

Shared investment:

– Proper risk allocation among stakeholders

(Owners, Vendors, Banks, Government): a key

to successfully financing a nuclear project;

Cernavoda 3 & 4: shared investment risk among

Nuclearelectrica, with the support of the State, and

private investors (5 electric utilities and on industrial

consumer);

– Investors off-take the electricity generated

(proportionally to the stake in the project), at

cost, and market it at their own risk;

this allows also dealing with future electricity price

volatility risk and security of supply.

RISKS MITIGATION (cont’d)

Page 16: T.Chirica - Forum Invest Financing Crisis And Nuclear

Phased financing:

– Construction risk is the overriding risk for new

nuclear units - the main risk is completion on

time & on budget;

– Operation risk: Investors are more ―comfortable‖

with the risks of operation, basically reduced to

operational and market risks (revenue stream);

Different financing phases may also have different

capital structures, for examples:

Recourse to shareholders during construction

phase;

Non-recourse financing may be used upon the

beginning of commercial operation.

RISKS MITIGATION (cont’d)

Page 17: T.Chirica - Forum Invest Financing Crisis And Nuclear

Some Global Nuclear Energy Partnership (GNEP)

members are working to put international

mechanisms into place to help finance

construction of nuclear power plants;

Two principal targets are:

– International financial institutions, such as the World

Bank, and

– National export credit agencies (ECAs).

ECAs’ existing terms are not optimal to stimulate

new nuclear power plant development:

– The present approach allows a 15-year payback period

for nuclear export credits - the proposal under

consideration could stretch that period out to 30 years;

TENDENCIES TO CHANGE GLOBAL RULES

FOR NUCLEAR FINANCING

Page 18: T.Chirica - Forum Invest Financing Crisis And Nuclear

18

SECOND ROMANIAN NPP

Romanian Government is considering a second NPP to be

commissioned after 2020, as far as the nuclear energy

represents the main contributor to security of supply

strategy and CO2 reduction:

– 2 to 4 units, up to an overall site capacity of about 2,400 MW;

– Sites on the internal rivers from energy deficit regions, as well

as Danube River could be considered;

– Reactor Type – Third Generation (750 – 1,200 MWe/unit): EPR,

AP1000, OPR 1000+, APR1400, ACR 1000, (Enhanced CANDU-6)

etc.;

– Impact of the future European Directive on Nuclear Safety;

Page 19: T.Chirica - Forum Invest Financing Crisis And Nuclear

19

CONCLUSIONS

The Nuclear Program in Romania, part of the national

and European energy policy: sustainable

development, security of energy supply and

competitiveness;

Completion of Cernavoda 3 & 4 - an excellent

opportunity utilizing the existing expertise from the

previous nuclear units, considering the unique hands-

on experience that Nuclearelectrica has;

Support from the political class is crucial,

considering that the completion of such projects are

covering more than one elections cycle.

Page 20: T.Chirica - Forum Invest Financing Crisis And Nuclear

20

CONCLUSIONS (cont’d)

Companies’ plans for new nuclear construction not

affected by the crisis, but some delays are to be

expected;

New tendencies in nuclear projects financing

(state guarantees, ECAs, MDB);

European Nuclear Energy Policy is needed,

consistent with other geographical areas (US,

Russia, China, India);

Page 21: T.Chirica - Forum Invest Financing Crisis And Nuclear

21

REFERENCES

1. Nucleonics Week - Volume 49 / Number 41 / October 9, 2008

– Nuclear energy revival vulnerable on costs, public opinion

2. Nucleonics Week - Volume 49 / Number 42 / October 16,

2008

– Impact of financial crisis on global nuclear revival seen as

moderate;

– Asian industry seeks explanation for rising construction costs

3. Nucleonics Week - Volume 49 / Number 43 / October 23,

2008

– US working with allies to change global rules for nuclear

financing

4. Structuring Nuclear Projects for Success, WNA Report,

London, 2008

5. Nuclear Energy Outlook 2008, OECD/Nuclear Energy

Agency, NEA No. 6348, 2008

6. Energy and Natural Resources – Central and Eastern

European Nuclear Energy Outlook, KPMG Energy and

Utilities Center of Excellence Team, Budapest, 2008

Page 22: T.Chirica - Forum Invest Financing Crisis And Nuclear

22

Thank you !


Related Documents