Slide 1 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Implementing aRisk Management Process
Compliantwith ISO 14971:2007
&How to Address the Seven
Deviations Identified inEN ISO 14971:2012
Slide 2 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
“Show me where it’s required”
• Clause 7.1 in ISO 13485 states:
“The organization shall establish documented requirements for risk management throughout product realization. Records arising from risk management shall be maintained .”
Slide 3 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
14971 Plus - http://bit.ly/ShopCSA
Slide 4 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
14971 Plus =Standard + Gap + Bonus Tools
Slide 5 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Bonus Tools in 14971 Plus
Slide 6 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Top 5 Risk Management Mistakes
1. Not reading the Annexes2. Using Annex C, Questions 1-34 as your only
form of Hazard Identification3. Using only some of the tools in Annex G4. Too much energy spent during design upon
identifying P1 vs. P2 (see Figure E1, Annex E)5. Not updating risk management
documentation.
Slide 7 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Hazard vs. Harm
• Clause 2.3 – Hazard is a “potential source of harm”[ISO/IEC Guide 51:1999, definition 3.5]
• Clause 2.2 – Harm is a “physical injury or damage to the health of people, or damage to property or the environment”[ISO/IEC Guide 51:1999, definition 3.3]
Slide 8 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Definition of Risk
• Clause 2.16 – Risk is the “combination of the probability of occurrence of harm and the severity of that harm.”
Slide 9 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
When are risks reviewed?• Adverse Events (Injury & Death)• Defects in Manufacturing Trend Data• Material Changes• Labeling Changes• Changes to Instructions• Changes in the Intended Use• Process Changes• Customer Complaints• Supplier Changes• Supplier Process Changes• Design Changes• Service Trend Data• Corrective Actions & Preventive Actions (CAPA)
Sales
Shipping
Finance
MarketingEn
gine
erin
g
RiskManagement
Manufacturing
Slide 10 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Management is a Process
4 – Risk Analysis
5 – Risk Evaluation
6 – Risk Control
7 – Residual Risk Acceptability
8 – Risk Management Report
9 – Production & Post-production Info
RiskAssessment
RiskManagement
Slide 11 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Overview of BS EN ISO 14971:2007
• Begins on Page 5 and ends on Page 14
• Key elements I look for when I’m auditing:– Is there an Annual review of effectiveness required?– Is the Risk Management File defined in the procedure?– Does the procedure discuss risk controls and option analysis?– Is the risk of risk controls mentioned?– Is there a requirement for the overall acceptability of residual
risks and a risk / benefit analysis?– Does the procedure include collection of post-production
information?
Slide 12 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Mitigation vs. Control
• In the 2007 version of ISO 14971, the term “mitigation” was removed.
• Mitigation implies elimination of risks, while control implies reducing and monitoring risks.
Slide 13 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Concept of Product Lifecycle
• Clause 2.7 – Lifecycle is “all phases in the life of a medical device, from the initial conception to final decommissioning and disposal”
ObsolesceSustainingMarket Growth
Commercial Release
PilotPhaseDesign
Pre-Production Post-Production
Slide 14 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Management / Design Controls
• Clause 7.3.2e) of ISO 13485 states that Risk management shall be an Input into Design & Development
• Clause 6.3 of ISO 14971 requires verification of effectiveness of risk controls
• Clause 6.7 of ISO 14971 requires verification of completeness of risk controls
Slide 15 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Design Risk Management Tasks
15
DHFBegins
ProductLaunch510(k)
Design Transfer
ConceptPhase
FeasibilityPhase
DevelopmentPhase
PilotPhase
ReleasePhase
HazardIdentification
Risk ControlOption Analysis
RiskAssessment Risk Control
Effectiveness Verification
RiskManagement
Plan
Slide 16 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Design Risk Management Tasks
16
DHFBegins
ProductLaunch510(k)
Design Transfer
ConceptPhase
FeasibilityPhase
DevelopmentPhase
PilotPhase
ReleasePhase
Risk / BenefitAnalysis
Risk ManagementReport
(continued)
Slide 17 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
2009 Corrections
• Annex ZA/ZB/ZC
• Flow Diagram Correction
Slide 18 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
MDD Requirements
• Annex I, Essential Requirement (ER) 1:– “… any risks which may be associated with their
intended use constitute acceptable risks when weighed against the benefits to the patient…”
– “This shall include…reducing, as far as possible, the risk of use error due to the ergonomic features of the device and the environment in which the device is intended to be used (design for patient safety)…”
Slide 19 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviation #6 in 2012 EN Version
Deviation as to the first risk control option
• Clause 6.2 of ISO 14971 requires the manufacturer to “use one or more of the following risk control options in the priority order listed: (a) inherent safety by design...”
• ER 2 of the MDD requires the manufacturer to “eliminate or reduce risks as far as possible (inherently safe design and construction)"
Slide 20 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
MDD Requirements
• Annex I, Essential Requirement (ER) 2:– “In selecting the most appropriate solutions, the
manufacturer must apply the following principles in the following order:• eliminate or reduce risks as far as possible (inherently
safe design and construction),• where appropriate take adequate protection measures
including alarms if necessary, in relation to risks that cannot be eliminated,• inform users of the residual risks due to any
shortcomings of the protection measures adopted.”
Slide 21 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Proposed Regulations
• Annex I, Essential Requirement (ER) 2:– “To reduce risks, the manufacturer shall manage the risks so
that the residual risk associated with each hazard as well as the overall residual risk is judged acceptable. The manufacturer shall apply the following principles in the priority order listed:
a) identify known or foreseeable hazards and estimate the associated risks arising from the intended use and foreseeable misuse;
b) eliminate risks as far as possible through inherently safe design and manufacture;
c) reduce as far as possible the remaining risks by taking adequate protection measures, including alarms; and
d) provide training to users and/or inform users of any residual risks.”
Slide 22 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Management Responsibilities
Clause 3.2• Commitment by top management to risk management
process– Adequate Resources– Qualified personnel for risk management
• Policy for determining criteria for risk acceptability– Criteria based upon applicable regulations and International
Standards– Accounts for accepted state of the art and stakeholder concerns
• Review the suitability of the risk management process to ensure continuing effectiveness – May be part of the quality management system review
Slide 23 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Management PlanClause 3.4 • The plan shall include at least the following:
– the scope of the planned risk management activities, identifying and describing the medical device and the life-cycle phases for which each element of the plan is applicable
– assignment of responsibilities and authorities– requirements for review of risk management activities– criteria for risk acceptability, based on the manufacturer's policy for determining acceptable risk,
including criteria for accepting risks when the probability of occurrence of harm cannot be estimated
– verification activities– activities related to collection and review of relevant production and post-production information
• For each risk management plan the manufacturer should choose appropriate risk acceptability criteria– May implement a matrix indicating which combinations of probability of harm and severity of harm are
acceptable or unacceptable
• The risk management plan is part of the risk management file– Record of the changes shall be maintained in the risk management file
Slide 24 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Management File
Clause 3.5 • File for each medical device • The risk management file shall provide
traceability for each identified hazard to:– the risk analysis– the risk evaluation– the implementation and verification of the risk control
measures– the assessment of the acceptability of any residual
risk(s)
Slide 25 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Hazard Identification
Clause 4.3• Documentation on known and foreseeable
hazards associated with the medical device in both normal and fault conditions
• Maintained in the risk management file
Slide 26 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviations #1 in 2012 EN Version
Treatment of Negligible Risks
Catastrophic Critical Serious Minor Negligible 5 4 3 2 1
Frequent 5 Unacceptable Unacceptable Unacceptable Unacceptable ALARPProbable 4 Unacceptable Unacceptable Unacceptable ALARP ALARP
Occasional 3 Unacceptable Unacceptable ALARP ALARP ALARPRemote 2 Unacceptable ALARP ALARP ALARP Acceptable
Improbable 1 ALARP ALARP ALARP Acceptable Acceptable
Rating↓®
Severity
Must implement risk controls for all risks.
Slide 27 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk EstimationClause 4.4• Reasonably foreseeable events that can result in a hazardous situation shall be considered and the
resulting hazardous situation(s) shall be recorded– Hazardous situations can arise from slips, lapses and mistakes
• For each identified hazardous situation, the associated risk(s) shall be estimated using available information or data. – Where the probability of the occurrence of harm cannot be estimated, the possible consequences shall be listed
for use in risk evaluation and risk control• Any system used for qualitative or quantitative categorization of probability of occurrence of harm or
severity of harm shall be recorded in the risk management file• Risk estimation can be quantitative or qualitative• Information or data for estimating risks can be obtained, for example, from:
– published standards– scientific technical data– field data from similar medical devices already in use, including published reported incidents– usability tests employing typical users– clinical evidence– results of appropriate investigations– expert opinion– external quality assessment schemes
Slide 28 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
P1 & P2 from Annex E
Slide 29 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviation #4 in 2012 EN Version
Discretion as to whether a risk-benefit analysis needs to take place
Catastrophic Critical Serious Minor Negligible 5 4 3 2 1
Frequent 5 Unacceptable Unacceptable Unacceptable Unacceptable ALARPProbable 4 Unacceptable Unacceptable Unacceptable ALARP ALARP
Occasional 3 Unacceptable Unacceptable ALARP ALARP ALARPRemote 2 Unacceptable ALARP ALARP ALARP Acceptable
Improbable 1 ALARP ALARP ALARP Acceptable Acceptable
Unacceptable Requires a Risk / Benefit Analysis
Rating↓®
Severity
Slide 30 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Evaluation
Clause 5
Risks are Acceptable?(see Clause 3.2)
Slide 31 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviation #5 in 2012 EN Version
Discretion as to the risk control options/measures
• Risk Controls options shall beimplemented regardless of severityor probability of occurrence
Slide 32 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Control Option Analysis
Clause 6.2• The manufacturer shall identify risk control measures that are appropriate
for reducing the risks to an acceptable level– Risk control measures can reduce the severity of the harm or reduce the probability
of occurrence of the harm, or both• The manufacturer shall use one or more of the following risk control options
in the priority order listed:– inherent safety by design– protective measures in the medical device itself or in the manufacturing process– information for safety
• The risk control measures selected shall be recorded in the risk management file
• If, during risk control option analysis, the manufacturer determines that required risk reduction is not practicable, the manufacturer shall conduct a Risk/Benefit Analysis of the residual risk (see Clause 6.5)
Slide 33 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Implementing Risk Controls
Clause 6.3• The manufacturer shall implement the risk control
measure(s) selected (see Clause 6.2)• Implementation of each risk control measure shall be
verified– Verification shall be recorded in the risk management file
• The effectiveness of the risk control measure(s) shall be verified and the results shall be recorded in the risk management file– Verification of effectiveness can include validation activities
Slide 34 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviation #3 in 2012 EN Version
Risk reduction “as far as possible” (ALAP)vs. “as low as reasonably practicable” (ALARP)
Catastrophic Critical Serious Minor Negligible 5 4 3 2 1
Frequent 5 Unacceptable Unacceptable Unacceptable Unacceptable ALARPProbable 4 Unacceptable Unacceptable Unacceptable ALARP ALARP
Occasional 3 Unacceptable Unacceptable ALARP ALARP ALARPRemote 2 Unacceptable ALARP ALARP ALARP Acceptable
Improbable 1 ALARP ALARP ALARP Acceptable Acceptable
ALARP As Low as Reasonably Practicable
Rating↓®
Severity
Slide 35 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Residual Risk Evaluation
Clause 6.4
Pre-Market Phase
Clinical Evidence
Residual Risk
PMS & PMCF Studies Quantify Residual
Risks
Slide 36 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk/Benefit Analysis & Evaluation of Overall Acceptability of Risk
Clause 6.5• If the residual risk is not acceptable using the criteria established in the risk management
plan and further risk control is not practicable, the manufacturer may gather and review data and literature to determine if the medical benefits of the intended use outweigh the residual risk– If the medical benefits do not outweigh the residual risk, then the risk remains unacceptable– If the medical benefits outweigh the residual risk, then proceed to Clause 6.6
• The manufacturer shall decide which information for safety is necessary to disclose the residual risk
• Results shall be recorded in the risk management file
Clause 7• After all risk control measures have been implemented and verified, the manufacturer shall
decide if the overall residual risk posed by the medical device is acceptable using the criteria defined in the risk management plan
• If the overall residual risk is not judged acceptable, perform a Risk/Benefit Analysis (see Clause 6.5 above)
• Results of the overall residual risk evaluation shall be recorded in the risk management file
Slide 37 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviation #2 in 2012 EN Version
Discretionary power of manufacturers as to the acceptability of risks
• All Risks shall be included in a risk / benefit analysis—not just the risks above a certain threshold.
Slide 38 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risks arising from Risk Control Measures
Clause 6.6• The effects of the risk control measures shall be
reviewed with regard to:– the introduction of new hazards or hazardous situations– whether the estimated risks for previously identified
hazardous situations are affected by the introduction of the risk control measures
• Any new or increased risks shall be managed• Results of this review shall be recorded in the risk
management file
Slide 39 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Deviation #7 in 2012 EN Version
Information of the users influencing the residual risk
• No risk reduction shall be attributed to information provided to the user
Slide 40 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Completeness of Risk Control
Clause 6.7• The manufacturer shall ensure that the risk(s)
from all identified hazardous situations have been considered
• The results of this activity shall be recorded in the risk management file
Slide 41 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Risk Management Report
Clause 8• Prior to release for commercial distribution of the medical
device, the manufacturer shall carry out a review of the risk management process. This review shall at least ensure that:– the risk management plan has been appropriately implemented– the overall residual risk is acceptable– appropriate methods are in place to obtain relevant production and
post-production information• The results of this review shall be included in the risk
management file• The responsibility for review should be assigned in the risk
management plan to persons having the appropriate authority
Slide 42 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
ClinicalEvaluation
Post-Market Surveillance
RiskAnalysis
Post-Market Surveillance (PMS) Report Identifies
Areas Requiring Changes
Instructions for Use (IFU) Needs to Reflect
Information Found in Risk Management Report
(RMR) & Clinical Evaluation Report (CER)
The Lifecycle Loop
Production & Post-Production Information
Clause 9
Slide 43 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Other Requirements
• Residual Risks May Require a Post-Market Clinical Follow-up (PMCF) Study as required by Annex X, 1.1c of the MDD(MEDDEV 2.12/2 rev 2)
• Clinical Evaluations shall conclude that “any risks associated with the use of the device are acceptable when weighed against the benefits to the patient.”(MEDDEV 2.7.1 rev 3)
Slide 44 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013
Q & A
Slide 45 of 45
Robert Packard, Consultant
www.MedicalDeviceAcademy.com
[email protected] 17th 2013