Page 1: PROJECT CAMEO MTU AMERICA DEVELOPMENT PROJECT MTU … Tognum Development... · research and development for MTU America’s S2000 and S4000 series of diesel engines. The output range

P R O J E C T C A M E O

M T U A M E R I C A D E V E L O P M E N T P R O J E C T / M T U A M E R I C A / A I K E N , S C

Key Project Features:

• Precision Fuel Conditioning and Measurement

Panel, controlling fuel pressure, temperature

and measurement.

• 3D CAD Model of entire test cell, test

equipment, test articles and support

equipment.

• Driveline including high speed shafting and a

tandem (water brake & AC) dynamometer.

• Isolated Inertia Mass with dampening spring

system for vibration control.

• Engine adapter system that accommodates

over 20 different engine types/models.

• Engine water cooling system skid.

• Combustion Air intake and Exhaust after

treatment systems with quick disconnects.

• Data Acquisition and Control system.

• Test Cell acoustics engineered to meet client

requirements

Project Duration: 18 months

Completion Date: Spring 2013

Headquarters - Madison, WI - USA / Greenville, SC - USA / Troy, MI - USA / TEDA Tianjin, China / Leicester, UK / www.acscm.com / [email protected]

Project Value: $24,600,000

Project Overview:

ACS provided turnkey delivery, including the

design, construction, equipment fabrication and

integration and commissioning services for a new

engine research and development test center in

Aiken, South Carolina. The project consisted of

a Development Building with two R&D test cells

as well as a new Mechanical/Electrical building

providing all new facility systems required to

support the test cells. The project will support the

research and development for MTU America’s S2000

and S4000 series of diesel engines. The output range

of these engines is 550 kW up to a maximum of 4500

kW.

ACS Services:

ACS held a single-source contract for test facility

design and construction management; equipment

design and component specification, equipment

build, procurement, and contractor installation;

integration of equipment, facility, and control

systems; and commissioning.

Related Documents