Ocenn Dopravn stavba roku 2007Nov tv na spolenosti
Vizualizace
Aspe
Civil and Structural
Schenker Liberec
Design
Valbek, spol. s r.o.
Owner
Schenker spol. s r.o.
Start of construction
August 2004
Completion of construction
March 2005
Total Cost
150 mil. CZK
SchenkerIndustrial Zone
Liberec South
8/14/2019 Pozemni Stavby En
2/6
For the industrial area a new construcon of three separate
buildings - administrave building and storage and transit halls wascompleted. To supplement the buildings all necessary supporngfacilies such as parking areas and access roads were constructed.Valbek provided all necessary design documentaons, permingand construcon support necessary for successful compleon.
SchenkerIndustrial ZoneLiberec - South
8/14/2019 Pozemni Stavby En
3/6
Ocenn Dopravn stavba roku 2007
Nov tv na spolenosti
Vizualizace
Aspe
Civil and Structural
BentelerIndustrial zone
Rumburk
Benteler Rumburk
Design
Valbek, spol. s r.o.
Owner
Benteler Automotive R, k.s.
Start of construction
October 2004
Completion of construction
May 2005
Cost
340 mil. CZK
8/14/2019 Pozemni Stavby En
4/6
New 4 stage assembly hall with adjoining two story administrave
building was designed in the industrial zone. The structural design andlayout of the assembly hall allows for further expansion. To supplementthe industrial zone and new assembly all necessary supporngfacilies such as parking areas and access roads were constructed.Valbek provided all necessary design documentaons, permingand construcon support necessary for successful compleon.
BentelerIndustrial zoneRumburk
8/14/2019 Pozemni Stavby En
5/6
Ocenn Dopravn stavba roku 2007Nov tv na spolenostiVizualizaceAspe
Ski area
Jetd and Vesec
Design and Renderings
Valbek, spol. s r.o.
Owner
CITY OF LIBEREC
Contractor
For majority SS Liberec
Start of construction
September 2003
Completion of construction
2008
Cost
1,5 bil. CZK
Ski areaJetd and Vesec
Liberec
Civil
The rederings for FIS World Championship in Liberec 2009 incorpo-
rated desired alternaves for design of the ski jumping hill and cross-
country stadium in Vesec. As the design was underway the 3D models
helped designers and the owner in decision-making process.
In the recent years the owner had decided to complexly retrot theenre sporng area on the Jested Mountain. Aer the repairs of K120and K90 ski jumping hills in the years of 1997 and 1999, the ski slopeswere altered for higher capacity, lighng was installed throughout the
whole area and the possibility of using snow-cannons was added. Aretenon pond was built in the lower part of the area in order to sup-
ply the snow-cannons.
8/14/2019 Pozemni Stavby En
6/6