Trevi Systems Introduction
• Trevi Systems Inc. is a 3 year old Petaluma, Calif. developer of
Forward Osmosis water purification systems for desalination
of seawater, brackish water as well as produced water,
industrial and municipal waste water.
• Trevi has several patents pending on Forward Osmosis Systems using an ultra low
electrical energy approach.
• We are a team of 25 people, with 8 PhD’s on staff.
• We have just moved into a new 30,000 sq ft R&D facility.
• Funding primarily from friends and family in the North Bay.
What’s the Problem with Reverse Osmosis
Desalination?
Maintenance on large pumps is significant problem.
Water pre-treatment critical for RO systems to avoid membrane fouling.
Energy consumption of large pumps is a significant expense.
- The Cost -
Forward Osmosis Desalination Basic FO Process
PUMP
SALINE
WATER
SEMI-PERMEABLE
MEMBRANE
BRINE
PRODUCT
WATER
CONCENTRATED DRAW
SOLUTION
DILUTE DRAW SOLUTION
WASTE HEAT/
ELECTRICITY
Low Pressure = Low Fouling
Low Electrical = Low OPEX
Low Temperature = Low CAPEX
• Forward Osmosis system energy
efficiency/performance tested at US Navy Port
Hueneme facility.
• Pilot testing started Oct 2012, complete Oct,
2013. Report by Carollo Engineers (ADC
Coalition member), water quality testing by
NSF International.
Trevi Systems Inc. Proprietary & Confidential
PILOT TEST
Naval Facilities Engineering Command
Seawater Desalination Test Facility
Port Hueneme, California
– Deep well injection reserved for very high salinity feeds only.
– Reverse Osmosis unable to desalinate high TDS waters >40,000ppm.
Industrial/Agriculture Systems: Food and Beverage (brewery), boiler water, waste incinerators
Business parks with private water treatment
Municipal waste water treatment systems .
Agriculture – Brackish water desalination – Agriculture
Aquaculture pond s
Semiconductor and other industrial water users.
Oil and Gas:
SEA water Desalination: Islands and “eco-resorts”
Renewable Energy or low GHG desalination.
Expensive RO desalination, electricity >40c/kWh.
Large Thermal power plants
Trevi Systems Proprietary & Confidential
Target Markets
Persian Gulf Status
• Persian Gulf historically a rich fishing ground.
• Iran, Iraq, Kuwait, Bahrain, Qatar, UAE
& Saudi Arabia border it.
• Takes 8-9 years to replenish the sea north of the
Straits of Hormuz.
• Fresh water inflow from the north minimized by
damming of the Euphrates river. 1.7millian arable
acres will be lost.
• 65% of desalination is in the Gulf, 1483 plants using
1 in every 4 barrels of oil to produce water.
• 24 tons of chlorine, 65 tons of anti-scalants and 300kg of copper are discharged daily.
• Pollution is significant and rising – “Peak Salt” is approaching.
Masdar Abu Dhabi, UAE
Cost of Water / Price of Electricity
100,000 m3
Trevi Systems Inc. Proprietary & Confidential
$0.3
$0.4
$0.5
$0.6
$0.7
$0.8
$0.9
$1.0
$1.1
$1.2
$1.3
$1.4
$0.06 $0.15 $0.24
Pri
ce o
f W
ate
r ($
/m3)
Price of Electricity ($/kWh)
Cost of Water RO vs FO - Cogen
Waste Heat FO 100,000 m3 RO 100,000 m3
RO 3.2kWh/m3