INSTALLATION INSTRUCTION
Date: 5/12/15
Channell Commercial Corporation Page 1 of 2 02002743 Rev A
Install Channell BULK Vaults
Installation Considerations
This Installation Instruction provides general information useful for installing the Channell BULK line of below-grade handhole vaults. This guide cannot anticipate all situations that could be encountered in the field and thus represents information applicable to common installation conditions. Please consult local company practice for proper product configuration for each application.
Site Preparation
1. Ensure that all local, state, federal, OSHA and company-specific regulations are met prior to beginning andthroughout the installation process.
2. Plan the excavation approximately 12 to 16 inches in length and width larger than the actual dimensions ofthe handhole to be installed. (See Figure 1)
3. Excavate the hole 6 to 8 inches in depth more than the overall height dimension of the handhole with thecover in place. Tamp the floor of excavated pit using either a hand tamp tool and/or a mechanical tamper.(Remember: if the handhole is to be set in concrete, the polymer ring must be included in this dimension.)
4. Place 5 to 6 inches of 3/4" crushed rock over the entire floor. The rock should be free of soil and otherorganic matter. This important step prevents subsistence of the vault over time, aids in drainage, andprovides a solid foundation for the handhole. (See Figure 2)
a. As an alternative, a dry mix of cement and crushed rock ina 1:10 ratio may be used to forma higher strength foundation.
b. NOTE: Do not use "pea gravel" or other "round stone" for this step.
5. a. Place the handhole body into the pit. (See Figure 3)b. Center the handhole body in the excavated pit parallel to the sidewalk and/or curb if applicable.c. Level and adjust the height of the handhole body to grade, as required, by adding more crushed rock.
FOR THE PURPOSE OF THIS ILLUSTRATION, THIS HANDHOLE IS BEING PLACED AT A SITE THAT WILL HAVE A FUTURE SIDEWALK; THEREFORE, THE COMPOSITE RING IS REQUIRED. THE RING IS ONLY REQUIRED AT SITES WHERE THE HANDHOLE IS BEING PLACED IN AND SURROUNDED BY CONCRETE.
6. Place the cover on the handhole body to prevent the backfill dirt from entering the inside of the handhole.The cover should be level with the ground. Bolting of the cover is recommend but is not a requirement forthis step; however, the cover must always be bolted down prior to departure of the site. (See Figure 4)
7. The excess soil removed from the excavated pit shall be used during the backfill of the pit.The backfill shall be tamped continuously during the filling process to prevent settling around the sides ofthe handhole. (See Figure 5)
During the filling process of the soil around the handhole, stones that are 3” and larger shall be removedfrom the soil and not used.
8. The final backfill shall be tamped with a slope away from the handhole. All excess backfill material shallbe removed from the installation site. (See Figure 6)
Channell Commercial Corporation Page 2 of 2 02002743 Rev A
Install Channell BULK Vaults
Figure 1 Figure 2
Figure 3 Figure 4
Figure 5 Figure 6
ICN OSP Construction Punchlist Rev 1.2.xlsx 1 December 7, 2017
Request Date:Completion Date:
Contractor Contact/#
County Township/Range/SectionCity or Nearest City Distance to CityStreet/Highway or Address Nearest Cross Street
Acceptable Y/N or NA
Locations of Issue(use station #)
If buried; depth:
Crushed rock base for handholes:
Wire mesh on top of rock:
Conduits:
Conduits plugged:
Pull rope in conduit:
Locate wire conduit plugged:
Minimum of 6" above rock:
Cables properly coiled (not protruding into lid):
Backfilled and Compacted:
Sufficiently Tamped (no settling):
Marker/TriView set with 5' height in DOT ROW:
ICN placard installed in lid
ICN cable tags on cable.
Handholes set level to grade:
Concrete resotred:
Located within ROW:
Warning Markers Placed (5' height in DOT ROW):
Trash & Debris Removed:
PROJECT LOCATION
Iowa Communciations Network OSP Post-Construction Punch List
Comment: (provide labeled pictures of any issues)Installation / Items
Backfilled:
Soil restored:
Sufficiently Tamped (no settling):
Equipment damage to lawn restored:
Conduit installed at proper depths:
Handhole Installation:
Bore Pits, Trenches, and Excavations:
Project Name:OSP Log # and/or RFS #:Requested by:Completed by:Contractor:
ICN OSP Construction Punchlist Rev 1.2.xlsx 2 December 7, 2017
Acceptable Y/N or NA
Locations of Issue(use station #) Comment: (provide labeled pictures of any issues)Installation / Items
Bulk Head Installed.
Panel Labeled
Fibers Spliced and Stored Properly
Exterior Conduit secured:
Penetrations Sealed:
Locate pedestal installed if required:
Armored cable:
Fiber Panel:
#10 ground extended to ground bar:
#10 grounded properly (lug):
Installed level:
Comments:
Cable Routed Correctly (on outside of ladder rack)
#6 Bare Copper bonded to rod with Ground Clamp:
#10 or #12 Tracer Wire bonded within splice enclosure:
All wires bonded at pedestal:
Directions Labeled:
Cable(s) locate appropriately:
TriView ____ SIP ____ Hideout ____ Tii ____ Other ____
Ground rod installed in Handhole:
Bend radius' maintained:
ICN cable tags on cable.
Slack loops installed per SOW.
Building Entrance/Terminations: (if two sites note location)
Locate Facilities:
Cable Installation:
Coils/Meter marks verified against redlines.
Any cable damage:
Locate materials per ICN standards.
Page 1 of 4 STANDARD INSTALLATION REQUIREMENTS:
General Requirements: 1. The contractor shall pothole all existing utilities.2. Provide the owners of any natural gas utility 48 hours advance notice that work is scheduled in the vicinity of their lines/mains so
that they can provide standby and protect services.3. Maintain proof of notification to and receipt of notification by the gas utility.4. Permits and coordination
4.1. Secure all necessary state and local (city, county, etc.) permits, public or private easements, facility permits, usage permits,and any other permit required by an Authority Having Jurisdiction (AHJ).
4.2. ICN will obtain and provide copies of IDOT permits. 4.3. If permits are required to be in the name of the owner rather than the contractor, the contractor shall prepare the permit for the
owner's signature. 4.4. Coordinate installation with all owners and AHJ over the route, the fiber, Right-of-Way and buildings in which end points
will be located. 4.5. Failure to coordinate with the AHJ and to obtain all necessary permits is at the peril of the contractor. 4.6. Right-of-Way Permit fees are an authorized extra above the quoted bid price. Excavation permits shall be by the contractor. 4.7. Ensure all facilities are placed within the public Right-of-Way.
5. Ensure that personnel working in the ROW are equipped with and use proper safety equipment and attire.6. All tools and test equipment required to do a project shall be provided by the Contractor or its subcontractor(s). Security of tools
and test equipment shall be the responsibility of each worker. The ICN shall not be responsible for the security of any propertyleft on ICN’s property or on property controlled by the ICN or the State of Iowa.
7. Contractor shall be responsible for instructing its employees in safety measures considered appropriate for the job. In addition,the Contractor shall not permit placing or use of tools or materials in traffic lanes or other locations. The tools or materials shallnot be placed in such a manner so as to create safety hazards to State employees, contracting agency employees, the public orthemselves.
8. Excavations and Trenches: The ICN requires all open excavations or trenches to be monitored and attended to duringconstruction per. The ICN requires all open excavations and trenches backfilled the same day. If the contractor is required toleave an excavation or trench open, then the contractor shall properly fence and/or cover the excavation for safety. Contractorshall follow all OSHA requirements for excavation and trench safety.
9. Contractor and its employees shall comply with all OSHA regulations. The contractor shall comply with all applicable State andFederal Laws.
10. Contractor shall comply with all Iowa One Call requirements as provided by Iowa Code, Chapter 480.11. Provide all labor and supervision for the project.12. Provide and install materials needed to result in a fully functional system meeting ICN standards, whether or not the materials or
methods are specifically mentioned in this document. See the list of ICN-furnished materials.13. Install cable route markers furnished by ICN. Where possible, install markers adjacent to poles, buildings or in other protected
areas.14. A copy of this Scope of Work and the Engineering Plan for this project shall be on site and available any time work is being
performed. Failure to have the required documents on site may result in ICN requiring the contractor to stop working until therequired documents are on-site.
15. Subcontractors shall meet the same qualifications stated for Contractors. Contractor shall obtain approval of the contractingagency’s project manager prior to using a subcontractor on any project.
16. Restore all damage to private property, Right-of-Way, ICN property, and any other property damaged in the course of the work.16.1. Any disruption of grass in an individual’s yard or in a private maintained area of the public right of way (the area between
the sidewalk and the street curb) must be restored through re-sodding. Any disruption of the grass in the median way or an unimproved shoulder must be restored either through re-sodding or re-seeding as required by the ROW owner.
16.2. Areas shall be restored to original or better condition. 16.3. Dirt shall be mechanically compacted around handholes and pits. 16.4. Lawns shall be sodded with like grass. 16.5. Contractor is responsible for watering the sod until it has knitted to the ground beneath. 16.6. All debris shall be removed from the construction areas including but not limited to: construction materials, trash, large
objects or stones within backfilled areas, etc.
Duct Installation Requirements
REV. 10-02-18
Page 2 of 4 1. HDPE duct shall be no less than 48 inches deep.2. Duct shall be installed in the public Right-of-Way.3. When crossing Iowa Highway in DOT Right-of-Way, duct shall be no less than 48 inches below grade under the roadway and
shoulders. HDPE may be used under the roadway and shoulders if installed at a minimum depth of 48”.4. Should it be necessary to cross private property, the Contractor may apply to the ICN for an exception, and request permission to
secure an easement. The easement is required to be in the name of ICN and the contractor shall have the easement prepared by aLand Surveyor licensed in the state of Iowa. Contractor shall be responsible for all fees unless previously authorized by the ICN.
5. At the conclusion of the project, provide and leave a pull rope in all ducts, conduits and pathways, including indoor, outdoor, newand existing.
6. Dirt shall be mechanically compacted at all duct splices, bore pits and around handholes.7. Ground shall be restored to the condition found prior to construction and debris removed prior to sodding or seeding.8. All conduits shall be plugged via duct seal or other method upon completion of cable installation.9. If Schedule 40 PVC conduit is utilized, all angles (45, 90 degree or other) require fittings to long sweep to accommodate
minimum cable bend radiuses.10. The ICN requires pictures by the contractor and/or on- site inspection by ICN staff prior to completion of the project where pipe
and fittings are not exposed; i.e. underground, behind a wall, etc.
Handhole Requirements 1. Install handholes so that the lid is level and flush with the surrounding natural grade. The lid SHALL NOT extend above the
surrounding natural grade.2. Provide ¼” opening hardware cloth type screen wire below the handhole.3. Provide 5-6 inches of ¾” crushed rock below the handhole. Rock shall be compacted. Gravel shall extend a minimum of 6 inches
beyond the outside walls of the handhole. DO NOT USE pea gravel or other round stone.4. Do not place gravel inside handhole above the hardware cloth.5. Conduit shall extend a minimum of 6” above the hardware cloth/gravel.6. Failure of the contractor to install handholes as specified will cause the contractor to return and re-install the handhole according
to this specification before payment for the project is made.7. Handhole installations shall follow ICN standard typical installation; see typical drawing.
Fiber Installation Requirements 1. Install fiber according to industry “Best Practices”.2. The contractor shall not violate the manufacturer’s minimum installation bend radius when the cable is under tension, or the
minimum installed bend radius.3. To prevent exceeding the manufacturer’s maximum pulling tension during installation of the fiber optic cable, the contractor shall
use a “Break-away” pulling swivel when installing cable.4. The “Break-Away” function shall activate at or below the maximum pulling tension specified by the cable manufacturer.5. The contractor shall test all strands of the fiber, on the reel, prior to beginning fiber installation. Confirm that all strands meet
manufacturer’s loss specifications.6. The contractor shall field verify all lengths and existing conditions prior to starting construction.7. Slack loops in handholes shall be coiled, installed, and secured to avoid damage to the coil and not interfere with lids.8. Slack loops at splices shall be coiled to match the existing fiber cable tails and allowance for splice preparation.9. ICN Fiber in all handholes shall be labeled with ICN wrap around cable tags or other labeled cable tags.
Building Entry Requirements 1. Weather-seal all penetrations.2. Use mortar or similar cement to seal penetration of brick or cement block.3. Firestop penetrations of any fire-rated floor, wall or ceiling.4. Replace the Firestop material in any existing Firestopped penetration used by the contractor.5. All outdoor conduits, of any length, shall be Galvanized Iron Pipe (GIP). EMT, PVC and plastic are prohibited.6. Immediately upon installation, seal the ends of all ducts with duct seal or expansion foam to prevent siltation or filling with
moisture. This applies to both new and existing ducts.7. Exterior exposed conduit shall be Galvanized Iron Pipe. EMT and plastic prohibited.8. At the conclusion of the project, ensure that a pull rope is left in ALL pathways, both inside and outside, new and existing.
Locate Facility Requirements 1. Tracer wire shall be continuous.2. Splices in the tracer wire are not allowed. If tracer wire is accidentally severed, request permission from ICN to splice.
REV. 10-02-18
Page 3 of 4 3. Wire splices only in handholes.4. Use either an epoxy splice kit, Scotch 3M 3832 or a Molex PermaSeal Butt Spice. 10-12 Ga. Splice materials SHALL be
designed for underground applications.5. Leave the wire splice visible in the handhole.6. Route a ground wire from the ground inside the building, through the entry to the TII 163 terminal.7. Secure all riser conduits with 3 each two-hole conduit straps.8. Wire the pedestal/terminal so that locates may be performed in any direction and from the far end.9. Do not leave any exposed tracer wire or ground wire.10. Permanently ground the tracer wire at the handhole on the furnished ground rod.11. At the conclusion of the project leave the tracer wire shield shorted to ground in the locate terminal.12. Use tracer wire that is rated for direct burial where required. THHN insulation is acceptable for placement within duct,
handholes, or enclosures, or any location not in direct continuous contact with soil or water.13. Label all wires in the locate terminal/pedestal/TriView. (I.e. “Ground”, “Facing DMACC”, “Facing North” etc.)14. Failure to label the locate wires will cause the contractor to return and properly label the wires before payment for the project is
made.15. Bond tracer wire(s) within splice enclosures utilizing a 3M 4460-D\FO Shield Bonding Kit.16. Route tracer wire(s) out of splice enclosure through a single port utilizing a FOSC closure sealing kit.17. At splice locations with no locate pedestal, tracer wires shall be bonded together, within the splice enclosure.18. At each end of any tracer wire, use appropriate-sized ring terminal (crimp) connectors.
DELIVERABLES/ACCEPTANCE: 1. Contractor shall provide construction redline as-builts with:
1.1. Offsets to fixed objects to the cable/conduit running line, handholes and new facilities.1.2. Meter marks of cable installations at handhole entry/exit, splice locations, building entries, etc.1.3. Depths of cable and/or conduit installation.1.4. One original set of as-built drawings must be provided within two (2) weeks after completion of construction for the ICN
management records. Redline as-built drawings must be complete. 2. Contractor shall provide splicing redline of all splicing completed and validation that the splice plan was followed.3. Contractor is responsible to locate fiber until acceptance by the ICN. Acceptance includes:
3.1. Submission of construction and splicing red line drawings by contractor.3.2. Assignment of link number by the ICN (if applicable).3.3. Submission of final as built drawing by the ICN to the ICN Network Maintenance Provider.3.4. Submission to Iowa One Call and the ICN Network Maintenance Provider’s contract locater.3.5. The measurements in the Statement of Work are estimates and need to be verified by the contractor.
4. Only written modifications to this Scope of Work are binding - Verbal changes to this scope of work by any person or personsare not binding, unless confirmed in writing.
5. Final payment will not be processed until all deliverables are received and accepted.
REV. 10-02-18
CABLE COILS NOT SHOWN
NOTES:-LOCATE (TRACER) WIRE: #10 or #12 AWG SOLID COPPER WIRE-GROUND WIRE: #6 OR #8 AWG SOLID BARE COPPER WIRE-ONE LOCATE WIRE PER FIBER CABLE AT SPLICE ENCLOSURE-LOCATE WIRE(S) TO BE BONDED INSIDE SPLICE ENCLOSURE WITH 3M SCOTCHLOK SHIELD BONDING KIT-LOCATE WIRE(S) TO BE ROUTED OUTSIDE OF SPLICE ENCLOSURE WITH FOSC CLOSURE SEALING KIT-LOCATE WIRE(S) TO BE ROUTED VIA DUCT TO LOCATE PEDESTAL AND TERMINATED AT TERMINAL BOARD-GROUND LOCATE PEDESTAL TO GROUND ROD WITH SOLID BARE COPPER WIRE AND GROUND CLAMP-SECURE LOCATE PEDESTAL BY PLACING OVER STEEL POST-SET PEDESTAL AT OR NEAR RIGHT-OF-WAY, IF POSSIBLE-MINIMUM HEIGHT OF INSTALLED PEDESTAL MUST BE 5 FEET
S
P
L
I
C
E
TYPICAL INSTALLATION OFTRI-VIEW LOCATE PEDESTAL
TRACER WIRE TERMINATION DETAIL
Termination of the locate wire at either a pedestal,puck, or in a splice case shall be made in the
following fashion:
Strip off a minimum of ¾” of insulation. Using aneedle nose pliers bend a wire “eyelet” on the wireend in a clockwise manner. Use a flat washer on
both sides of the wire eyelet when cinching it downon the stud. Flat washers shall be of appropriate sizesuch that the hole matches the diameter of the studand the outside diameter of the flat washer matches
reasonably close to the eyelet diameter.
IOWA COMMUNICATIONS NETWORK
36"
35
1
2
"
24" X 36" X 36" HAND HOLE
HANDHOLE PLACEMENT TYPICAL
5-6"
6" min.
35"
1
2
"
24"
12" min.
35
1
2
"
24"
40
3
8
"
28
3
4
"
35
7
8
"
3"
R
I
G
H
T
-
O
F
-
W
A
Y
4' TYP.
5' MIN.
DUCT FOR TRACER
& GROUND WIRES
(LOC. PED. ONLY)
SEE INSTALLATIONINSTRUCTIONS FOR
PROPER PLACEMENT OFCHANNELL BULK
HANDHOLE
IOWA COMMUNICATIONS NETWORK
R
O
W
6" ±
5'
6" ±
3'±
METAL SIGN &
U-CHANNEL POST
WARNING MARKER INSTALLATION DETAIL
6" ±
6" ±
R
O
WR
O
W
5'
5'
FIBERGLASS
MARKER
TRIVIEW
MARKER
EACH 9" x 12" METAL WARNING SIGN SHALL BE
ATTACHED AS FOLLOWS:
· TWO: 1/4-20 x 2 SS HEX HEAD BOLT
· TWO: 1/4 SS FLAT WASHER
· TWO: 1/4-20 SS NYLON INSERT LOCK NUT
POST
3'±
IOWA COMMUNICATIONS NETWORK