Habitat for Humanity Building a Home in 10 Weeks
Site Preparation
Week 1 Floor System
Week 1 Exterior Walls
Week 2 Exterior & Interior Walls
Week 2 Walls & Trusses
Week 2 Trusses & Roof
Week 3 Roofing, siding & porches
Week 4 Roofing, siding & porches
Week 5 Sub-contractors electric, plumbing & HVAC
Week 5 Exterior work
Week 6 Sub-contractor Insulation & Sheetrock
Week 7 Painting & Trim Begins
Week 8 Trim & Interior Doors
Week 9 Finish Trim & Install Cabinets
Week 9 Install Appliances, Finish Trim
Week 10 Landscaping
Week 10 Finishing & Cleanup
Week 10 Final Cleanup
Dedication