AESO Connection Process
Stage 2: Connection
Proposal
Stage 3: NID & Facility
Application
Stage 4: Applicaton Filings& AUC Approval
Stage 5: Construct &
Prepare to Energize
Stage 6: Energize,
Commission & Close
GATE 2
July2017
GATE 3
Q12018
GATE 4
Q32018
GATE 5
2019
WeAre
Here
CommercialOperation
Q4 2019