Page 1: 2008 NACE Western Regional Symposium – Pavement Preservation

October 3, 2008Laughlin Nevada

Stephen B. Urbanek, P.E.County of Sonoma Department of Transportation and Public Works

PROMOTINGPAVEMENT PRESERVATION IN SONOMA COUNTY

Page 2: 2008 NACE Western Regional Symposium – Pavement Preservation

Challenges

System Size and Condition

Funding

Approach to Pavement Management

Page 3: 2008 NACE Western Regional Symposium – Pavement Preservation

Sonoma County

Population

Service Area

Lane Miles Arterials Collectors Locals

Page 4: 2008 NACE Western Regional Symposium – Pavement Preservation

1,371 Centerline Miles to Maintain

Page 5: 2008 NACE Western Regional Symposium – Pavement Preservation

PCI by Class

Page 6: 2008 NACE Western Regional Symposium – Pavement Preservation

Challenges

System Size and Condition

Funding

Approach to Pavement Management

Page 7: 2008 NACE Western Regional Symposium – Pavement Preservation
Page 8: 2008 NACE Western Regional Symposium – Pavement Preservation

How we compare…

COUNTY PCI Ctr. LineMiles

Annual Revenue Per

Mile

MTCE Employee

s

Miles per Employee

Number of Paid Vehicle Registrations

Contra Costa 83 657 $ 28,243 80 8.2 818,086

Santa Clara 75 685 $ 28,018 130 5.2 1,385,167

Alameda 69 470 $ 35,976 58 8.1 1,125,186

San Mateo 65 316 $ 43,006 59 5.3 660,865

Solano 58 600 $ 17,111 52 11.5 329,012

Napa 54 446 $ 15,677 33 13.5 116,477

Marin 48 420 $ 26,156 46 9.1 219,844

Sonoma 44 1387 $ 20,831 91 15.2 413,168

Page 9: 2008 NACE Western Regional Symposium – Pavement Preservation

Annual Funding Scenarios for Road Network

PCI Changes with Expenditure ($ millions) for All Roads

40

45

50

55

60

65

70

75

2007 2008 2009 2010 2011 2012

PC

I

$120

$20

$15

$10

$5

Page 10: 2008 NACE Western Regional Symposium – Pavement Preservation

Challenges

System Size and Condition

Funding

Approach to Pavement Management

Page 11: 2008 NACE Western Regional Symposium – Pavement Preservation

The Old Way…

Focus on Rehabilitation and Reconstruction

Reactive and political

Results showed limited improvement to the system pavement condition

Page 12: 2008 NACE Western Regional Symposium – Pavement Preservation

In Ten Years…

By the year 2017 the County’s roads would require almost total reconstruction

Page 13: 2008 NACE Western Regional Symposium – Pavement Preservation
Page 14: 2008 NACE Western Regional Symposium – Pavement Preservation

Pavement Preservation Strategy Change “Worst First” Past Practice

Perform Life Cycle Analysis

Promote Preservation First

Page 15: 2008 NACE Western Regional Symposium – Pavement Preservation

Maintenance Strategy

Develop technical expertise

Encourage innovation

Understand Systems Approach

Page 16: 2008 NACE Western Regional Symposium – Pavement Preservation

The New Way…

Page 17: 2008 NACE Western Regional Symposium – Pavement Preservation

The New Way…

Page 18: 2008 NACE Western Regional Symposium – Pavement Preservation

Pavement PreservationPreventive Maintenance Prolongs the life of the road Lowers the cost of maintaining the road

Page 19: 2008 NACE Western Regional Symposium – Pavement Preservation

The New Way…

Page 20: 2008 NACE Western Regional Symposium – Pavement Preservation

Field Review of Treatment Options

Page 21: 2008 NACE Western Regional Symposium – Pavement Preservation

The New Way…

Page 22: 2008 NACE Western Regional Symposium – Pavement Preservation

Treatment Options…Our Tool Box Crack Sealing Fog Seals Rejuvenating Seals Slurry Seals Micro Seals Chip Seals Asphalt Rubber Chip Seals Thin Overlays

Page 23: 2008 NACE Western Regional Symposium – Pavement Preservation

The New Way…

Page 24: 2008 NACE Western Regional Symposium – Pavement Preservation

Remaining service life

Remaining service life in 10 years if all county roads if no preventive maintenance is performed

Page 25: 2008 NACE Western Regional Symposium – Pavement Preservation

2008 Pavement Preservation Program Analysis

Project Treatment Project Cost Per

Programmed Treatment Length (Miles)Life (years) Mile-Years Cost Mile Year

Overlays 2 20 40 $ 2,100,000 $ 52,500

Asphalt Rubber Chip Seals 37.13 10 371 $ 3,500,000 $ 9,426

PASS Chip Seals (Co. Prcd.) 19.25 7 135 $ 1,000,000 $ 7,421

Rejuvenating Seals 12.57 3 38 $ 100,000 $ 2,652

Total 70.95 584

Network Need 1,371

Deficit 787 $ 6,700,000

Page 26: 2008 NACE Western Regional Symposium – Pavement Preservation

The New Way…

Page 27: 2008 NACE Western Regional Symposium – Pavement Preservation

2008 Pavement Preservation Program

Page 28: 2008 NACE Western Regional Symposium – Pavement Preservation

Old = $9,000,000

250 Mile Years $36,000/Mile Year

Comparison – Old and New Strategies

New = $7,600,000

584 Mile Years$13,000/Mile Year

Page 29: 2008 NACE Western Regional Symposium – Pavement Preservation

What’s Next?

1.Define a prioritized portion of the road network

2.Develop funding options for the remainder of the road network

Thank you!