1 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Rural Wings
Ariane Muller & Laurent Thomasson
TWISTER overview- Current status, main outcomes, lessons learned -
Rhodes, 05/07/2006
2 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
TWISTER key elements
Three-year EC programme (FP6, Call 1) started 1st of February 2004
TWISTER deploys and operates validation sites in rural areas throughout Europe combining bidirectional satellite broadband services with wireless local networks
The validation site period corresponds to 18 months starting from the satellite terminal equipments installation
Target application areas: in the domains of
– Agriculture
– Education
– Community services
– Health care
– e-business
3 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
TWISTER ConsortiumRepresentative of the whole supply chain
Ouranos-Networks
4 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Summary of major TWISTER achievements
More than 100 validation sites deployed through the enlarged
Europe
More than 50 validation sites are hybrid networks coupling
satellite access with wireless local terrestrial networks
More than 10 countries concerned (France, Spain, Italy,
Denmark, Ireland, Greece, Malta, Poland, Romania, Croatia,
Bosnia, Hungary)
Already 10 validation sites have ended their validation period of
18 months
5 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Example of TWISTER validation siteDordogne (France)
6 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Typical validation site deployment process- Strongly recommended to apply it to Rural Wings -
Validation site user and service requirements report
Site survey
Validation site network design
Prerequisites for installation
On-site installation
Validation site acceptance test
Usage and evaluation period
At this stage of Rural Wings, only these aspects are being addressed
Budget constraints per site
7 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Lessons learned from TWISTER Encountered Critical Points
Site Survey
Geographical topology matters
Network Architecture Design
Technical constraints and equipment costs
Site Installation
Who will be responsible of site installation and when?
How to do acceptance test review?
Maintenance
Who will intervene?
Who will reboot or replace the equipment?
Supervision
Who will supervise the system and send alert?
Monitoring
How to estimate the usage of the pilot site?
8 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Network Operations Structure
Hotline & end-user support
– A phone number to call in case of network problems
– Need for a local site administration
– Definition of roles and procedures
Network monitoring and management
– Creation of a Network Operations Centre
– Remote supervision and configuration of validation sites
Maintenance procedures
– Definition of roles and procedures in case of equipment
replacement
Contractual aspects
– Equipment & services are provided by TWISTER to the
validation site users
– To establish the rights and responsibilities of each partner
– Creation of an « End-user agreement » and « Validation site
agreement »
9 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
TWISTER Anomaly Distribution per Kernel Validation Site from January to December 2005
10 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Example of TWISTER usage evaluation
2
3
1
Number of sessions and duration
Total Online Duration 2005: 5,15 years in 30.000 sessions
Volume of data exchanged (source Aramiska)1788 Gbytes since June 2004
Protocol Distribution
11 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Way forward for Rural Wings wireless networks- Critical points to address in the coming weeks -
Detailed user requirement forms necessary
– Form templates to be provided by EADS Astrium
Mid of July 06 (Ariane Muller)
– To be fulfilled by National Coordinators
September 06
Guidance for installation requirements
– To be provided by EADS Astrium
End of July 06 (Ariane Muller)
– To be used by National Coordinators for installation activities
- EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Support needed from other partnersWireless network deployment issues: environmental conditions
Conditions of wireless transmission Line of sight and topography Meteorology Opened zone of Fresnel Relative elevation of sites Vegetation
Physical constraints Possibilities of mast installations Points accessibility (roof, tower, etc…) Cable length between antenna and wireless unit
13 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Support needed from other partnersWireless network deployment issues: environmental conditions
Electrical conditions– Verify quality of electrical network – Use of UPS equipment is recommended
Temperature & Humidity operating– Outdoor equipment: use specific equipment with adequate temperature
and humidity operating range– Indoor equipment: select sites with air conditioning or warming for
central point (no direct sun, no attic, …) Visual aspects
– Respect design of building when it is possible (hidden antennas, …)
– Pay attention to ancient monuments : castle, tower, ancient house, church,…
14 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Support needed from other partnersChecklist for initial site layout
– Indicate building positions on map
– Identify high points
– Is a special authorization necessary to install antenna ? (historic building,…)
– Identify type of user (single user, multi-user, etc.)
– Identify connection priorities
15 - EADS Astrium Proprietary & Confidential -
- EADS Astrium Proprietary & Confidential - 05/07/2006, Rhodes
Rural WingsEADS Astrium contribution
Thank you for your attention