Project Name Product Release Project Manager Alex B. Project Deliverable Scope Statement: Start Date 2-Sep End Date 10-Oct Overall Progress 20% Tasks Responsible Start End Days Set kick-off meeting Alex B. 9/2 9/3 1 Agree on objectives Frank C. 9/3 9/7 4 Detailed Reqs. Jacob S. 9/7 9/12 5 Hardward Reqs. Jacob S. 9/9 9/11 2 Final Resource Plan Jacob S. 9/11 9/15 4 Staffing Alex B. 9/16 9/17 1 Techincal Reqs. Frank C. 9/17 9/21 4 DB Development Shari W. 9/22 9/24 2 API Development Shari W. 9/23 9/27 4 UI Client Alex B. 9/25 9/29 4 Testing Kennedy K. 9/24 10/2 8 Dev. Complete Jacob S. 10/2 10/5 3 Hardware Config. Alex B. 10/5 10/7 2 System Testing Kennedy K. 10/6 10/9 3 Launch 10/9 10/10 1 Or, Click
17
Embed
d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Project Name Product ReleaseProject Manager Alex B.Project DeliverableScope Statement:
Start Date 2-SepEnd Date 10-OctOverall Progress 20%
Tasks Responsible Start End Days Status
Set kick-off meeting Alex B. 9/2 9/3 1 Complete
Agree on objectives Frank C. 9/3 9/7 4 Complete
Detailed Reqs. Jacob S. 9/7 9/12 5 Complete
Hardward Reqs. Jacob S. 9/9 9/11 2 Overdue
Final Resource Plan Jacob S. 9/11 9/15 4 In progress
Staffing Alex B. 9/16 9/17 1 In progress
Techincal Reqs. Frank C. 9/17 9/21 4 Not started
DB Development Shari W. 9/22 9/24 2 Not started
API Development Shari W. 9/23 9/27 4 Not started
UI Client Alex B. 9/25 9/29 4 Not started
Testing Kennedy K. 9/24 10/2 8 Not started
Dev. Complete Jacob S. 10/2 10/5 3 Not started
Hardware Config. Alex B. 10/5 10/7 2 Not started
System Testing Kennedy K. 10/6 10/9 3 Not started
Launch 10/9 10/10 1