www.transportation.ohio.gov John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING
15

Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

Mar 31, 2015

Download

Documents

Byron Shuker
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v

John R. Kasich, Governor

Jerry Wray, Director

Ohio Department of Transportation

CONSTRUCTION MONITORS MEETING

Page 2: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 2

Updates to the Construction Section of the LPA Manual

Preconstruction Conference Section

• Language added to include discussion of the EEO, DBE and Prevailing Wage responsibilities.

• LPA requirement to inform the general public of general project information, lane and road closures, and/or any temporary restrictions to road access that will be experienced during the construction.

Page 3: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 3

Updates to the Construction Section of the LPA Manual

Construction Contract Requirements for EEO, DBE & Prevailing Wage Compliance Section

• Interviews to be done no more frequently than once a month for single year projects

• Language added clarifying the new requirement that the project Bulletin Board be readily accessible to all employees, applicants for employment and potential employees.

• Language deleted stating that the Bulletin Board can be kept in the project Superintendent/foreman’s truck.

Page 4: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 4

Updates to the Construction Section of the LPA Manual

Recovery of Overhead and Fringe Section (added)

Language added that outlines in detail the 3 methods that the LPAs may utilize to recover overhead and fringe costs associated with force account work on federally funded projects.

Time Keeping Requirements of LPA • Time Sheets must be completed for employees • Must be prepared at least monthly• Must be signed by the employee

Page 5: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 5

Updates to the Construction Section of the LPA Manual

Construction Monitor Responsibilities Section

Invoices • A copy of the fully executed Local-let Summary and Payable

invoice should be sent to the LPA for their records.

Finalization • Language added stating that the CM will work with other District

disciplines (REA, DEC, PW/EEOCC, LPA Manager, etc.)

to complete the LPA Project Evaluation Form.

Page 6: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 6

CSFs/ OPI/ Local Programs Distribution

• CSFs – Capital Program – • Contribute towards $1.5 B

• Quarter of the Federal funds sold through LL Program

• Project Award On-Time• Local-let 85% Award On-Time• On-Time defined as actual project award occurring

no later than 30 days after locked award

Page 7: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 7

CSF/ OPI/ Local Programs Distribution

• Program Distribution• Split 20-30-30-20 (dollars awarded)

• Historically 4th Qtr. Heavy; 50%• Locals get budgets in Jan., PS & E late winter, sell in

the spring• OPI • Plan File to meet 90% on time delivery

• Plan File from the District to C.O. to meet the locked program.

• Historically 80% Goal / 88% Hit last 2 years

Page 8: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 8

LPA Process Reviews

Purpose:

• To review local practices and procedures to ensure compliance with all requirements of State and Federal laws, regulations, and policies as outlined in the Department’s Stewardship and Oversight Agreement with FHWA.

• Report recommendations and Best Practices in LPA Program Management

Page 9: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 9

Risk Factor Ratings

5 4 3 2 1

1How much will the LPA receive in Federal funds in the next two years?

> $10M$10M -

$5M$5M - $1M

$1M - $500k

<$500k

2How much has the LPA received in Federal funds in the last three years?

> $30M $15-$30M$7M-$15M

$3M-$7M <$3M

3How many projects will the LPA administer in the next two years?

10+ 7-9 5-6 3-4 0-2

4How many projects has the LPA administered in the last three years?

7+ 6 5 4 0-3

5Has a QAR been performed on the LPA in the last four years?

No       Yes

6 Is the LPA in a high risk ODOT district?* 2, 6 12, 48, 7, 3,

115, 1 9, 10

7Has the District recommended a LPA / specific project has high risk?

Yes -- -- -- No

Page 10: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 10

LPA Performance Reviews

• City of Kettering - 10/18• Seneca County Engineer - 11/21• City of Dayton - 12/14• Franklin County Engineer - 1/17• Montgomery County Engineer - 2/16• Hamilton County Engineer - 3/13• Cuyahoga County Engineer - 4/17• Stark County Engineer - 5/5• City of Toledo - 5/24

Page 11: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 11

LPA Performance Reviews

Review Team will include:

Local Programs Section (Randy Lane and Jeff Peyton)

Office of Construction Administration (Naureen Dar)

Page 12: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 12

LPA Retainage

Retainage of 8% on labor for the first 50% of the work is required on projects (ORC 153.12) 

Find that Locals typically do not co-mingle the Federal fund reimbursement with retainage – i.e. take off the top prior to invoice

There has been confusion regarding how to account for retainage and how to reimburse retainage without delaying closeout of the project with ODOT. 

Page 13: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 13

LPA Retainage

Methods for discussion:

funded locally / reimbursed with final invoice (not held for warranty period)

ORhave evidence of escrow accounts for federal participation.All funds retained shall be deposited in an escrow account (ORC 153.13) to the contractor

Require verification of accountSet up separate encumbrance to the LPA for deposit into escrowInvoice details payments to contractor and payments to lpa for retainage

Page 14: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 14

SIGNIFICANT CHANGES OF WORK

ODOT C&MS 104.02(D) AND TABLE 104.02-2

PROVIDES DECREASE FACTORS FOR SIGNIFICANT CHANGES IN UNIT BID PRICE CONTRACT ITEMS

INCOPRORATED INTO ODOT LPA BID DOCUMENT TEMPLATE

INSTEAD OF 104.02(D) AND 104.02-2 TABLE THE LPA HAS THE OPTION TO USE LANGUAGE FROM 23 CFR 635.109(A)(3)

Page 15: Www.transportation.ohio.gov John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation CONSTRUCTION MONITORS MEETING.

w w w. t r a n s p o r t a t i o n . o h i o . g o v 15

SIGNIFICANT CHANGES OF WORK

language from 23 CFR 635.109(a)(3):Significant changes in the character of work. (i) The engineer reserves the right to make, in

writing, at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project. Such changes in quantities and alterations shall not invalidate the contract nor release the surety, and the contractor agrees to perform the work as altered.

(ii) If the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character, an adjustment, excluding anticipated profit, will be made to the contract. The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the contractor in such amount as the engineer may determine to be fair and equitable.

(iii) If the alterations or changes in quantifies do not significantly change the character of the work to be performed under the contract, the altered work will be paid for as provided elsewhere in the contract.

(iv) The term “significant change” shall be construed to apply only to the following circumstances:When the character of the work as altered differs materially in kind or nature from that involved or included in the original proposed construction; orWhen a major item of work, as defined elsewhere in the contract, is increased in excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase in quantity shall apply only to that portion in excess of 125 percent of original contract item quantity, or in case of a decrease below 75 percent, to the actual amount of work performed.