www.NAEPnet.org
Dec 17, 2015
www.NAEPnet.org
www.NAEPnet.org
Construction & RenovationContracts, Liens, Schedule of Values &
Payments
Stan ScottDirector of Project Management –
Texas
Hill International, Inc.
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
SchedulerContracts
Estimator
QA/QCInspection
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
ManufacturerManufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
Manufacturer
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
ManufacturerManufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
Manufacturer
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
ManufacturerManufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
Manufacturer
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
ManufacturerManufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Sub-sub
Supplier
Manufacturer
Supplier
Supplier
Manufacturer
Manufacturer
StructuralEngineer
PlumbingEngineer
ElectricalEngineerIT
Consultant
Parking Consultant
TrafficEngineer
CivilEngineerSpace
Programmer
Cost Consultant
Interiors Architect
Food Service Consultant
DesignArchitect
NetworkEngineer
Graphics & Signage
Audio VisualConsultant
Code consultant
Life Safety Consultant
Testing & Inspection
Security Consultant
Geotech Engineer
Hardware Consultant
Landscape Architect
MechanicalEngineer
Acoustical Consultant
Owner’sPM
CM
AEPM
LegalAcounting
Executives
Board
Demolition
Clearing & Stripping
Fencing Erosion Control
Termite Control
StructuralSteel
Concrete Formwork
Sealants and Caulking
Soil Treatment
Concrete Supply Plumbing
Elevators
Roofing
Glass & Glazing
Mechanical
Roof Hatches
Electrical
Rough Framing
Grading & Excavation
Paving
FlooringFire Stopping
Window WallFlashing & Sheet Metal
Ductwork
Block & Brick
Hardware
Control Wiring
TileSkylights
Fire Protection
VacuumSystems
Stucco
Millwork
Cabinets
Hauling
ToiletAccessories
Signage
Casework
Wall coverings
Carpeting
Moisture Protection
Insulation
Doors & Frames
Ornamental Iron
Drywall
Lockers
Flagpoles
Window Coverings
Cleaning
Kitchen Equipment
Landscaping and Planting
RO Water
ConcreteReinforcing
Pools & Fountains
OverheadDoors
Acoustic Ceilings
Metal Fabrications
Glass & Glazing
Insulation
Millwork
Building Specialities
Counter Tops
Sprinklers
UserUserUser
User
UserUser
UserUserUser
User
User
UserUser
User
User
UserUser
User
User
User
User
User
User
User
User
UserUser User
User
UserUser
UserUser
UserUser
User
User
User
User User
User
User
User
User
UserUser
User
User
User
User
User
Estimating
StandardsUtilities
O&M
Plan Review
ProjectControls
ParkingPrograms
DirectorFacilities
Slide Courtesy of 3D/International
Capital Projects = Many People, Multiple Teams
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
So… How do you get them on the same page?The Contract Documents are to The Contract Documents are to Construction…Construction…
What the Sheet Music is to a SymphonyWhat the Sheet Music is to a Symphony
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
The Contract Documents
• Contract Documents are a ‘suite’ of complementary documents, typically including:o Contract Agreemento General Conditionso Special Conditions
o Division 1 General Requirement Specificationso Technical Specificationso Construction Drawings
Alignment is Critical !
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Documents
• Other documents, often not considered “Contract Documents”, but just as critical to project success:o Owner Design Standards
• Consistency Desired, Should be “Enterprise – Wide”
• Certain Preferred Equipment / Systems (proprietary)
• May vary with type of projecto Housing, Parking Structures, Classroom, Research …
o Project Programo Feasibility Studyo Owner’s Project Requirements (OPR)
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Documents - Hierarchy
• At Enterprise Level
Across All Institution’s Projects
o Agreements (some tailoring to each project, but basic parameters of agreement are consistent)
o General Conditions• Those Things Common to All Projects
• Institutional Policy / Regulatory & Legal Parameters
• Concept of Rotation / Standardization / Uniformityo Add Division 1 Specifications ??
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Documents - Hierarchy
• At Project Level o Those Things Particular to a Certain Project
o Special Conditionso Division 1 General Administrative Specifications (why not
rotate to enterprise level?)o Technical Specifications (possible rotation?)o Contract Drawingso Permits, Easements, Etc.
Each Project Each Project Each Project
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Documents – Form Documents
• American Institute of Architects (suite)• Consensus Docs (suite)• Associated General Contractors• Professional Engineers• Various Other Associations• Institutional (in-house)
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Form Contracts• AIA Bookstore lists 27 various documents at:
• http://www.topfloorstore.com/software_h/sft-dwn-g70.shtml• From Agreements to Applications for Payment to Waivers of
Claim to Certified Payroll forms
• Consensus Docs lists 6 Series of Documents at:• https://www.consensusdocs.org/Catalog OR through• https://www.coaa.org
• COAA Members get a 20% Discount• The “General Contracting” Series includes 25 separate
forms plus instructions.• Other “Series” include Collaborative Contracting, Design –
Build, Construction Management, etc.
• In both cases, these are Copyrighted documents, each sold individually for ONE-TIME USE
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Form Contracts
• AIA Documents tend to enhance Designer’s Positions
• Consensus Docs tend to focus on COMPROMISE between the partieso Because they were collaboratively
developed by large committeeso COAA has it’s “Gold Standard” of comments
and suggested modifications for Owners
• So… what’s best for the Owner ??
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Form Contracts
• Owners should NEVER use form contracts from ANY source withouto Modifying them to suit their unique needs and
processeso Ensuring that they align with the Owner’s regulatory
environmento Assessing them for appropriate allocation of Risks
• Each party to an agreement is uniquely positioned to address specific risks – a good contract allocates Risks to those most suited to handle them
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Institutional Contracts
• Practically ALL institutions with repetitive building programs utilize IN-HOUSE documents created by their legal counsel.o Often patterned after AIA Documents, buto Addressing the unique needs of a particular
institution• Federal & State Governments
• Municipalities
• Higher Education Systems
• Large Corporate Owners
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Agreements
• Generally the same across projects of the same owner, and cover basic terms at a relatively high level…o Scope of Work (* this would be tailored to project)
o What Constitutes “Contract Documents”o Definitionso General Responsibilities of the Partieso Overall Price and Time Period for Performance (* this
would be tailored to project)
o Time, Payments, Changes (General Parameters)
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Agreements
• Continued…o Bonds & Insuranceo Dispute Resolution & Venue for Litigationo Terminationo Indemnity o Special Certifications (* this may be tailored to the project)
o Other Terms & Conditions
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract General Conditions
• Again, generally the same across projects of the same owner, and cover the same basic terms as the Agreement, but with a little more detail…o Definitionso Laws Governing Constructiono General Responsibilities of parties (more specific)o Sub-contracting Plans (HUB / MBE) o Bonds & Insurance (type of policy; amounts of
coverage)
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract General Conditions
• Continued…o Contract Documents (what are included?)o Safety Requirementso Quality Controlo Project Scheduling (Time), Payments, Changeso Completion & Acceptanceo Warranty & Guaranteeo Suspension & Terminationo Dispute Resolution (process identified)
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Special Conditions
• Generally tailored specifically to the project, may differ from project to project, focus on issues particular to the project and/or administrative procedures to be followed. Typically includes issues such as…o Owner’s Separate Contractso Prevailing Wage Rates & Determinationo Weather Data and Conditions at Siteo Owner Special Cash Allowances
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Special Conditions
• Continued…o Temporary Field Office Structures, Improvements and
Temporary Utilities for construction durationo Project Fencing and /or Signageo Builder’s Risk Endorsementso Site Access and Limits of Construction, Parking and
On-Site Activity Limitationso On-going Activities / Operationso Security & Responsibility for Workforce
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Special Conditions
• Continued…o Administrative Processes for Communications, RFIs,
Submittals, Payments, Changeso Protection of Site Amenities & Work in Progresso Project Surveying, Shoringo Cutting and Patching of Sleeveso Asbestos Abatemento Sustainability Issueso Environmental Controlso BIM and Technology Requirements
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships
• Each Document Addresses an Issue in ever-increasing level of detail o Some Institutional Owners seek to combine their General
Conditions within their Contract Agreements• Nothing wrong with that, in some ways it is easier
• However, the parties that execute a Contract Agreement are NOT NORMALLY the parties that implement the Work…o That’s one reason separate documents are often
developed. o A basic understanding is needed for the Parties to Agree,
but more detail is required to implement the Work
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships
• Concept of “Rotation”o Many Owner Institutions seek to eliminate re-creating
documents for every project – they “rotate” them up to an Enterprise (or Program) Level
• They also seek to reduce the influence of the A/E in outlining Administrative Procedures, and thereby minimize conflicts with provisions of their contracts and General Conditions, so they…
o Create standard / “uniform” Division 1 Specifications
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships
• Concept of “Rotation”oHINT: This Concept can be applied to ALL
Institutional Processes, not just Contract Documents • Whatever is done the same way, repeatedly on
multiple occasions, can be performed, or “established” across the Enterprise Level and not re-developed for each project or each occurrence.
• This can even work for Technical Specifications where the same materials / systems are desired – “big-box retail”, for example, uses this approach with great success.
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships
• Metaphor for Relationship of Contract Documents – “Layers of an Onion”o Two Examples
• Time & Schedules
• Payments
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 1
• Time / Project Scheduleso Contract Agreement
• Time Limits are of the Essence of this Agreement
• Owner & Contractor to perform expeditiously …
• Prior to commencement…Contractor shall submit CPM Schedule
• Develop a CPM for Team Review & Owner approval
• Identify major milestones & Owner-managed work
• Comply with specified requirements
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 1
• Time / Project Scheduleso General Conditions
• Contract Time is Essential Element of Contract• Schedule Requirements and Updating• Meaning / Limits of Acceptance by Owner• Ownership of Float• Completion of Work & Owner recourse if not on schedule• Modification of Contract Time, Concurrent & Excusable Delay• No Damages for Delay (?)• Liquidated Damages
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 1
• Time / Project Scheduleso Special Conditions
• Weather allowances if applicable
• Project Float Requirements
• Type of Computerized Software
• Any deviations and/or amendments to General Conditions or Specifications due to unique nature of project, such as phasing or minimal requirements for very small projects.
o Requirements included in Special Conditions are dependent on having a separate Schedule Specification
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 1
• Time / Project Scheduleso Division 1 General Requirements Specification
• Includes most provisions of Agreement & General Conditions
• Levels of CPM Development at Phases of Project
• Logic Approach of Schedule, Naming Conventions, Activity ID, Time Limits of Activities, Sorting Capabilities
• Types of Reporting, Report Layouts & Timing of Submissions
• Baselines & Targeting, Float Management
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 2
• Payments – Contract Agreemento Relation to Schedule of Valueso Allowable Expenses including Travelo Retainage, Taxes, Assessment of Liquidated Damageso Reasons for Withholding Paymentso Partial Payment does not construe acceptance by Ownero Right to Audito Issues specific to payment at various phaseso Meaning of Acceptance of Final Payment by Contractor
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 2
• Payments – General Conditionso Relation to Schedule of Values; no payment without accepted
SOVo Preliminary Pay Worksheet (Application); Site Reviewo Required Attachments (CPM, HUB/MBE Status)o Application includes Affidavit of Payment of Debtso Certification of A/Eo Owner’s Duty to Pay; Rights to Withhold Paymento Stored Materials provisions for paymentso Retainage provisions including time of release
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 2
• Payments – Special Conditions o Wage Rates for Payment of Laboro Certifications and Affidavits included with Payment
Requestso Administrative Requirements unless such is covered in
Division 1 General Requirements Specifications (*)
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 2
• Payments – Division 1 Specifications o Generally a Project Administration Spec or equivalento Administrative Requirements unless such is covered in
Division 1 General Requirements Specifications (*)• Detailed Process for Initial and Monthly Payments
• Contract Price Breakdown (SOV); how to organize it?
• All attachments required for Payment
• Process of Review, Correct and Submit; Number of copies, etc.
• Where to submit, who takes action, what timing constraints on payment process…
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Contract Document Relationships - Example 2
• Payments – Division 1 Specifications o Continued…
• Notarized Signatures, Certifications
• Release of Lien & Claim
• Affidavit of Debts Paid
• Backup Documentation required for General Conditions Cost Items, Stored Materials
• Certified Payroll requirements
• Conditions pertaining to Release of Retainage
• Conditions pertaining to Final Payment
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Liens
• Liens, more often referred to in legal context as “Mechanic’s Liens”:o Serve to support payment of contract funds to the
actual subcontractors and suppliers that furnish material and labor to the project.
o Mechanic’s Lien laws vary from state to state and can be quite complex
o Generally result in a “lien” or an “encumbrance” placed on the property being built or improved.
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Liens
• Public Owners:o Generally a lien on a public project serves no real
purpose - sense there would be little intent to sell that property
o But Public Owners still have a duty to see that payments reach their intended target
• Payment Bonds normally required for Public Projects in Texas (often in association with Performance Bonds)
• Retainage of earned funds serves as protection to Owner and helps assure subs are paid
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Liens
• Private Owners:o Much more at risk of liens against their propertyo Same risk mitigation techniques are available to
them:• Payment Bonds
• Retainage (normally 10%) of earned funds from payment to Prime Contractoro If a private owner does withhold 10% retainage in
Texas, then their obligation to any/all subs is legally limited to the amount of retained funds
o If multiple subs file liens, this still gets very tricky
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Liens
• All Owners:o Should get an Affidavit from the Prime Contractor with
each and every progress payment attesting to payment of debt and claim
o Should get a Release of Lien and Claim from the Prime and ALL SUBCONTRACTORS prior to issuing Final Payment
o Should pay attention to Notices of Non-Payment from Subcontractors & Suppliers
• Should understand what these mean & respond to them
• Should confirm their resolution prior to continued payment
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Schedule of Values (SOV)
• Otherwise known as “Contract Price Breakdown”o Along with the CPM Schedule, is one of the 2 most
important documents in managing a construction project• The SOV should align with the CPM, using
common nomenclature and organizationo Is a line-item listing of the various work items,
equipment, materials and labor required to complete a project; each with a monetary value
• The total of the individual line item prices must equal the total contract amount
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Schedule of Values (SOV)
• Otherwise known as “Contract Price Breakdown”o Is used:
• As outline for generating progress payments,
• To determine the value of various systems and building components for facility maintenance / renewal programs
• For reporting of values to certain agencies where required. THECB Componentization for example.
o Is applicable to all Contracting Methods, from lump sum to GMP and/or Cost – Plus contract amounts.
o Should identify both labor and material costs for every aspect of the work that has both components.
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Schedule of Values (SOV)
• Includes the entire scope of the contracto Preconstruction services / Design services if applicable o General Conditions costs of field operations,
management & supervisiono Cost of Work activities, systems, materialso Contingencies & Allowanceso Fees
• Is Best Developed on a Spreadsheet
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Schedule of Values (SOV)
• Is Organized byo Classification of Work (CSI / MasterFormat)
• With Subtotals for Classificationso Building and/or Area
• If project includes Multiple Buildings, that should be the first level of organization – so you can tell at a glance the building completion status
o Floor and/or Section/Quadrant of the floor
• The Guiding Principle Should Be:o Each Line Item of Work is observable in its entirety from a
single location
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Schedule of Values (SOV)
• Example Spreadsheet
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Payments
• The Progress Payment Form is Developed from the Schedule of Values Spreadsheeto With Additional Columns for:
• Prior Amounts Earned and Percentage
• This Period’s Amount Earned and Percentage
• Total as of This Period’s Amount Earned and Percentage
• Retainageo The Organization and the Guiding Principles are the
same as for the Schedule of Values
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Payments
• General Conditions Cost Items should be supported by invoices for equipment / services and by payroll reports for management / supervision expenses
• Cost of Work Items should be reviewed in the field to determine percent complete for each line item
• Contingencies are paid only via change order as approved by Owner
• Fees Paid should represent the Percent Complete of the entire Project
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Payments
• Percent Complete on the Pay Application should equate to the Percent Complete on the CPM Schedule o Both for each individual line item, ando For the project as a whole
• Contracts normally identify cause for Owner to reduce and/or withhold payments
• Owners should obtain release of lien and claim with each payment
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation
Payments
• Example Spreadsheet
Facilities InstituteJuly 9 - 12, 2012Houston, Texas
Construction & Renovation