Willie J Viljoen Director Marwillcor Project Control Services Pty Ltd South Africa
Willie J ViljoenDirector
Marwillcor Project Control Services
Pty Ltd South Africa
2
• The following slides illustrate the importance of the 11 main Criteria or Project Management Processes, that are required to function satisfactory, for Project Controls to be effective.
• The 11 Criteria, or Processes are based on Earned Value Management Principles as described by the PMI, the PMBOK, Prince 2, AACE (International).
Project Management for large Power Generation Projects
3
Project Management for large Power Generation Projects
For this presentation the 11 main criteria have been grouped into 5 processes.
1.An agreed, integrated, deliverable-orientated, Work, organisational and cost Breakdown Structure (in short the WBS).
2.An agreed, high-level schedule, based on 100% of the authorised scope of the WBS.
4
Project Management for large Power Generation Projects
The 11 main criteria have been grouped into 5 processes for ease of use.
3.An agreed Performance Measurement Baseline against which progress is assessed and performance and status can be established (in short the PMB).
4.Establish under-performance areas as early as the 15% completion mark.
5
Project Management for large Power Generation Projects
The 11 main criteria have been grouped into 5 processes for ease of use.
5.Provide forecasts: Estimate At Completion for cost & time at agreed intervals (in short the EACc & EACt).
6
J F M A M J J A S O N D J F M
3311 22 5544
Process no. 1:An agreed, integrated, deliverable-orientated, Work, organisational and cost Breakdown Structure.
Project Management for large Power Generation Projects
Copy of WBS typical Power generation.xlsx
7
EP
CM
Prj. Mng
QC
SHEQ
750
654=
750=
290=
150=
300=
=1 900
2 500
1 700Civil
ME&I
Boiler
1 600
1 000
1 750
150
360
250
200
765
564
200
200
200 200
200 250
Power Gen. Project
R 23 600
Unit 1 ACC Silo
5 333 3 700 3 880
EXAMPLE: Integrated Work Breakdown Structure
Deliverable
(1) Detailed WBS Element Description; (2)
Schedule; (3) EV Milestones; (4) Estimate
(Budget); (5) Assumptions; (6) Long Lead
Items; (7) Risk Register
Objective: A Signed-off Agreed Scope,
Schedule & Budget (CBE)
Pla
nn
ing
Lev
el 1
Lev
el 2
Lev
el 3
Schedule Alignment
Pa
ckg
s
A Control Account consists of:
(1) Scope; (2) Schedule & (3) Budget
Costs are collected & progress is
assessed at Control Account level
What are the
elements that will
make the deliverables
(assets) successful?
What are the
deliverables (assets)
that will make the
project successful?
RPlanning & Work
Packages
WBS is DeliverableOrientated
8
750
000=
750=
290=
150=
300=
=1 900
2 500
1 700ME & I contractor
Piping contractor
Civil contractor
Prj. Mng 1 600
QC 1 000
SHEQ 1 750
150
360
250
200
000
000
200
200
200 200
200 250
Project ABCR 23 600
Crushers Conveyors Sub Station
5 333 3 700 3 880
EP
CM
Project Management for large Power Generation Projects
Schedule Alignment
A Control Account consists of:
(1) Scope; (2) Schedule & (3) Budget
Pla
nn
ing
Lev
el 1
Lev
el 2
Lev
el 3
Contracts
WBS is DeliverableOrientated
9
J F M A M J J A S O N D J F M
3311 22 5544
Process no. 2:An agreed, High-Level Schedule, based on 100% of the authorised scope in item (number 1 above).
Project Management for large Power Generation Projects
10
Mth 16Mth 01 Mth 13Mth 04 Mth 07 Mth 10
Total Proposed Project Duration
All
Pro
ject
Pa
cka
ge
s
(WP
+P
P)
&
Co
ntr
act
s
tha
t w
ill
en
sure
th
e
pro
ject
’s s
ucc
ess
Package 9
Example:
An agreed High-Level Schedule
Package 8
Package 7
Package 6
Package 5
Package 4
Package 3
Package 2
Package 1
100 % of the authorised scope, logically linked
Work Packages Include:
1. Clear Scope
2. High level Schedule
3. Budget / Costs
Planning Packages:
During the early stages, the
Scope, Schedule and Budget
for “far in the future”
packages might be a best
estimate only
11
Project Management for large Power Generation Projects
J F M A M J J A S O N D J F M
3311 22 5544
Process no. 3:An agreed Performance Measurement Baseline (PMB) against which progress is assessed and performance and status can be established.
12
Mth 16Mth 01 Mth 13Mth 04 Mth 07 Mth 10
Total Proposed Project Duration
All
Pro
ject
Pa
cka
ge
s
(WP
+P
P)
&
Co
ntr
act
s
tha
t w
ill
en
sure
th
e
pro
ject
’s s
ucc
ess
Package 9
EXAMPLE: An agreed Performance Measurement Baseline
Package 8
Package 7
Package 6
Package 5
Package 4
Package 3
Package 2
Package 1
Control
Account
200
180
200
120
800200 600 1200 1400 1500
Performance
Measurement
Baseline
100 % of the authorised scope, logically linked
The PMB, is also called: The monetary value for
the work to be performed-
Planning Packages:
During the early stages,
the Scope, Schedule
and Budget for “far in
the future” packages
might be a best
estimate only
13
Mth 16Mth 01 Mth 13Mth 04 Mth 07 Mth 10
Total Proposed Project Duration
EXAMPLE: The final Performance Measurement Baseline (PMB).
Contract 5
Contract 4
Contract 3
Contract 2
Contract 1
200
180
120
600200 450 1000 1200 1300
Performance
Measurement
Baseline
Hig
h Le
vel
Sch
edul
e As contracts are placed, schedules are agreed,
which establishes the final Performance
Measurement Baseline (PMB).
Control Accounts: Weighted milestones are used
to assess Progress and Earned Value, and
measure Performance.
As contracts are placed, schedules are agreed, which
establishes the final Performance Measurement Baseline
The PMB, is also called: The monetary value for
the work to be performed-
90
14
Project Management for large Power Generation Projects
J F M A M J J A S O N D J F M
3311 22 5544
Process no. 4:Establish under-performance areas as early as the 15% completion mark.
15
15%
Anticipated CPI:
Anticipated SPI:
Establish under-performance areas as early as the 15% completion mark
Preferred Profile
16
Project Management for large Power Generation Projects
J F M A M J J A S O N D J F M
3311 22 5544
Process no. 5:Provide forecasts: Estimate At Completion for cost & time (EACc & EACt) at agreed intervals.
17
Earned Schedules
Provide forecast forSchedule at agreed intervals
Schedule – Slip 3,5 weeks
Schedule Variance
(SV)
18
Provide forecast for Cost at agreed intervals
19
1. An agreed, integrated, deliverable-orientated, Work, organisational and cost Breakdown Structure.
2. An agreed, high-level Schedule, based on 100% of the authorised scope in item (number 1 above).
Let’s recap the 5 processes
supporting effective
Project Controls!
Project Management for large Power Generation Projects
20
3. An agreed Performance Measurement Baseline (PMB) against which progress is assessed and performance and status can be established.
4. Establish under-performance areas as early as the 15% completion mark.
Project Management for large Power Generation Projects
21
5. Provide Forecasts: Estimate At Completion for Cost & Time (EACc & EACt) at agreed intervals.
Project Management for large Power Generation Projects
22
• Ensure that the 5 main processes are implemented and continuously visible throughout the execution phase of the project.
• No extra manpower is required to maintain the 5 processes. It is basic Project Management Principles and Teamwork that are required.
Project Management for large Power Generation Projects - in summary
23
• There is no software on the market that “fixes” bad Project Management.
• The referred processes in this presentation has to be established and functioning for any cost engineering software to perform to its expectations.
Project Management for large Power Generation Projects - reminders