Top Banner
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin
19

Where We Are Now

Feb 09, 2016

Download

Documents

sagira

Where We Are Now. Rationale for Reducing Project Duration. Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Where We Are Now

Reducing Project Duration

CHAPTER NINE

Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.

McGraw-Hill/Irwin

Page 2: Where We Are Now

9–2

Where We Are NowWhere We Are Now

Page 3: Where We Are Now

9–3

Rationale for Reducing Project DurationRationale for Reducing Project Duration

• Time Is Money: Cost-Time Tradeoffs–Reducing the time of a critical activity usually incurs

additional direct costs.•Cost-time solutions focus on reducing (crashing)

activities on the critical path to shorten overall duration of the project.

–Reasons for imposed project duration dates:•Time-to-market pressures•Unforeseen delays•Incentive contracts (bonuses for early completion)•Imposed deadlines and contract commitments•Overhead and public goodwill costs•Pressure to move resources to other projects

Page 4: Where We Are Now

9–4

Options for Accelerating Project CompletionOptions for Accelerating Project Completion

• Resources Not Constrained–Adding resources–Outsourcing project

work–Scheduling overtime–Establishing a core

project team–Do it twice—fast and

then correctly

• Resources Constrained–Fast-tracking–Critical-chain–Reducing project scope–Compromise quality

Page 5: Where We Are Now

9–5

Explanation of Project CostsExplanation of Project Costs

• Project Indirect Costs–Are costs that cannot be associated with any

particular work package or project activity.•Supervision, administration, consultants, and interest

–Are costs that vary (increase) with time.•Reducing project time directly reduces indirect costs.

• Project Direct Costs–Are normal costs that can be assigned directly to

a specific work package or project activity.•Labor, materials, equipment, and subcontractors

–Increase with use of crashing activities increases

Page 6: Where We Are Now

9–6

Seeking Optimal Project Duration Seeking Optimal Project Duration to Minimize Project Costto Minimize Project Cost

Compute total costs for each specific duration Compute total costs for each specific duration and evaluate the tradeoff between project cost and evaluate the tradeoff between project cost and duration. and duration.

Search critical activities of lowest direct-cost Search critical activities of lowest direct-cost increase to shorten project duration.increase to shorten project duration.

Identifying direct costs to reduce project timeIdentifying direct costs to reduce project time

Gather information about direct and indirect Gather information about direct and indirect costs of each specific project duration. costs of each specific project duration.

Page 7: Where We Are Now

9–7

Project CostProject Cost–Duration Graph–Duration Graph

FIGURE 9.1

Page 8: Where We Are Now

9–8

Constructing a Project CostConstructing a Project Cost–Duration Graph–Duration Graph

• Find total direct costs for selected project durations.

• Find total indirect costs for selected project durations.

• Sum direct and indirect costs for these selected project durations.

• Compare additional cost alternatives for benefits.

Page 9: Where We Are Now

9–9

Constructing a Project CostConstructing a Project Cost––Duration Graph Duration Graph

• Determining Activities to Shorten–Shorten the activities with the smallest increase

in cost per unit of time.

–Assumptions:•The cost relationship is linear.•Normal time assumes low-cost, efficient

methods to complete the activity.•Crash time represents a limit—the greatest time

reduction possible under realistic conditions.•Slope represents a constant cost per unit of

time.•All accelerations must occur within the normal

and crash times.

Page 10: Where We Are Now

9–10

Activity GraphActivity Graph

FIGURE 9.2

Page 11: Where We Are Now

9–11

CostCost–Duration Trade-off Example–Duration Trade-off Example

FIGURE 9.3

Page 12: Where We Are Now

9–12

CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)

FIGURE 9.3 (cont’d)

Page 13: Where We Are Now

9–13

CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)

FIGURE 9.4

Page 14: Where We Are Now

9–14

CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Page 15: Where We Are Now

9–15

Summary Costs by DurationSummary Costs by Duration

FIGURE 9.5

Page 16: Where We Are Now

9–16

Project CostProject Cost–Duration Graph–Duration Graph

FIGURE 9.6

Page 17: Where We Are Now

9–17

Practical ConsiderationsPractical Considerations• Using the Project Cost–Duration Graph

– For cost-duration tradeoff decision

• Crash Times– It is more difficult to estimate than normal time and cost

• Linearity Assumption– However, usually crashing is “all or none.” It is not as practical to do partial

crashing of an activity.

• Choice of Activities to Crash Revisited– In addition to choosing the cheapest crashing method, other factors such as risk

and resource availability (at the time of need) should be considered as well.

• Time Reduction Decisions and Sensitivity– A project is sensitive if it has several critical or near-critical paths.

– Compression of projects with several near critical paths reduces scheduling flexibility and increases the risk of delaying the project.

Page 18: Where We Are Now

9–18

What if Cost, Not Time Is the Issue?What if Cost, Not Time Is the Issue?

• Commonly Used Options for Cutting Costs–Reduce project scope

–Have owner take on more responsibility

–Outsourcing project activities or even the entire project

–Brainstorming cost savings options

Page 19: Where We Are Now

9–19

Key TermsKey Terms

CrashingCrash pointCrash timeDirect costsFast-trackingIndirect costsOutsourcingProject cost–duration graph