Top Banner
STATEMENT OF WORK Requisition #290986 Title: Double-Shell Tank Integrity Test Facility Revision Number: 1 Date: July 6, 2016 1.0 Objective Washington River Protection Solutions, LLC (WRPS) as a prime contractor to the U.S. Department of Energy is issuing this Statement of Work (SOW) to design and fabricate partial tank sections of the annulus space of Hanford Tank Farm’s double shell tanks (DSTs). The Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State. Hanford’s DSTs were built in groups, commonly referred to as tank farms. The tanks store both radioactive and hazardous waste. To monitor and maintain their condition these tanks are inspected periodically through a comprehensive tank integrity program. The work of this SOW will focus on building a facility that allows WRPS to evaluate solutions for inspecting the bottom annulus (space between tank floors of the primary and secondary tanks). The objective of this SOW is to design, fabricate, house mock-up DSTs, and host technology demonstrations. The facility housing the mock-up DST(s) will be used as a test facility for developing, testing, and evaluating non-destructive examination systems and their techniques. 2.0 Background/Introduction Hanford’s DSTs are aging and monitoring of their integrity is crucial to how TOC maintains, operates, and estimates their remaining life. This SOW will construct and house a facility to enable WRPS to develop and test non-destructive inspection techniques and equipment which will allow WRPS Operations to inspect the most difficult area of the tanks – the primary tank Page 1 of 11 (C-2 041416)
11

 · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

Apr 23, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

STATEMENT OF WORK

Requisition #290986

Title: Double-Shell Tank Integrity Test Facility

Revision Number: 1

Date: July 6, 2016

1.0 Objective

Washington River Protection Solutions, LLC (WRPS) as a prime contractor to the U.S. Department of Energy is issuing this Statement of Work (SOW) to design and fabricate partial tank sections of the annulus space of Hanford Tank Farm’s double shell tanks (DSTs).

The Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State. Hanford’s DSTs were built in groups, commonly referred to as tank farms. The tanks store both radioactive and hazardous waste. To monitor and maintain their condition these tanks are inspected periodically through a comprehensive tank integrity program. The work of this SOW will focus on building a facility that allows WRPS to evaluate solutions for inspecting the bottom annulus (space between tank floors of the primary and secondary tanks).

The objective of this SOW is to design, fabricate, house mock-up DSTs, and host technology demonstrations. The facility housing the mock-up DST(s) will be used as a test facility for developing, testing, and evaluating non-destructive examination systems and their techniques.

2.0 Background/Introduction

Hanford’s DSTs are aging and monitoring of their integrity is crucial to how TOC maintains, operates, and estimates their remaining life. This SOW will construct and house a facility to enable WRPS to develop and test non-destructive inspection techniques and equipment which will allow WRPS Operations to inspect the most difficult area of the tanks – the primary tank and refractory region between the primary tank and secondary liner. To ensure successful implementation at Hanford’s tank farms, the facility must allow full scale testing of the inspection equipment. Previous tests with equipment have shown that getting inspection equipment into the refractory slots and through the bends/corners is very difficult, and a large portion of the tank bottoms have gone uninspected. The purpose of this facility is to allow development of systems and techniques that can inspect all exposed areas of primary tank bottoms.

3.0 Scope

Build and house a test platform emulating a small fraction of two DST annulus configurations. Figure 1 and Figure 2 below are photographs of a typical DST annuls space. The test platform (mock-up tank) will be used to evaluate tank integrity methods and equipment, therefore air channel replication is critical. One or two platforms may be manufactured, but each tank model must allow use of a 24” riser through which the inspection tool will be deployed.

Page 1 of 8 (C-2 041416)

Page 2:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

Secondary Liner (annulus ceiling)

Primary Tank

Access Riser

Figure 1) Upper Inside View of DST Annulus.

Annulus Floor

Refractory Pad

Primary Tank

Air Slot

Figure 2) Lower Inside View of DST Annulus.

The air channels are used to cool tank bottoms. The designs to be fabricated for this SOW are based on AY and AZ tank farm vessels. The following is a list of specifications to be followed for the design and manufacture of the test facility.

Construction Specifications: Materials of construction

o Carbon steel (CS) tank wallso Air channel material should be either Kaolite 2000-LI or a material having

similar physical properties (hardness) to Kaolite 2000-LI refractory Full scale where required for verification of test equipment performance

Page 2 of 8 (C-2 041416)

Page 3:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

Annulus gap (30”) Refractory configuration

Construction Drawing H-2-64301 and H-2-67244 will be furnished as a guide

o Partial wall height (~20 feet)o Partial radial arc

Incorporate both air channel designs in one slice of tanko Full Tank bottom radiuso Black-out capable; field implementation will be in an area with no lighting (the

tank annulus), the ability to work in either a lit or unlit tank annulus should be made easy (less than two hours to implement)

Air channels (refractory configuration)o One set of AY configuration to centero One set of AZ configuration to center

Sufficient to accommodate at least one prototypical air channel path to the center of the tank for both AY and AZ configurations (see Figure 3); have both left and right hand corners at the first radius

Riser access to annuluso One 24” risero Minimum of 24” extension above secondary liner top

Black out abilityo Ability prevent light penetration into annulus and air channelso Less than two hours to implement in either direction, lit or no light

Carbon Steel Primary Tanko ASMT A537 or equivalento Bottom – 1/2” CS plateo Knuckle – 7/8” CS with 12” radiuso Wall – 3/4” and 1/2” CS plateo Ideally this section should be easily removable to allow for accurate assessment

of damage to air channelso Construction Drawing H-2-67317 will be furnished as a guide

Carbon Steel Secondary Liner (outer tank) o ASTM A537 or equivalento Bottom CS plate 3/8” thicko Bottom knuckle – 1/2” CS with 12” radiuso Wall – 3/8” CS plate Tank radius of 40’ (30” annulus space between primary

tank and secondary liner) o Construction Drawing H-2-67317 (Sheet 1 and 2) will be furnished as a guideo Wall – 3/8” CS plate Tank radius of 40’ (30” annulus space between primary

tank and secondary liner) o Construction Drawing H-2-67317 (Sheet 1 and 2) will be furnished as a guide

Space/Utilitieso Electrical

Capable of being modified to support testing (no formal specifications)o Pneumatic

Clean dry airo City watero Indoors

Climate control if practicalo Adequate room for a minimum of 10 people working on and/or reviewing the

system at one timeo Provide manned access to the top of riser during demonstration activities

Page 3 of 8 (C-2 041416)

Page 4:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

θ = 15Σ(117.0” @ radius of 447”)

Radius = 447.0”

AY Tanks AZ Tanks

θ = 15Σ(117.0” @ radius of 447”)

Radius = 447.0”

1st Radius

Figure 3) AY Air and AZ Tank Farm Channel Configurations

The schedule of work to be performed should include at a minimum following activities: Drawings

o 30% Design Review (informal)o 90% Design (final)o As-Built; incorporating any changes made during construction

May be redlined (i.e., not formally incorporated) Procurement of long lead items Construction

o Starto Hold point for inspection of refractory layer (air channels) prior to placement of

primary tank bottomo Complete

Demonstration Support Needs:The contractor shall provide field support to periodic equipment demonstration activities as schedule by WRPS. Support shall include:

Access control to the test facility area Manage facility and operations safety in accordance with WRPS principles and

requirements Supply of necessary support utilities as required Standby support to change test facility configuration (e.g. install black out curtains or

provide access to riser top) The first field support is expected to be needed by September 1, 2016 with an estimated 3

additional field demonstrations occurring periodically through September 1, 2017

4.0 Submittals

In support of the work scope established in Section 3.0 above, submittals are listed on the Master Submittal Register (MSR).

Page 4 of 8 (C-2 041416)

Page 5:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

Submittals shall be provided using the TOC Incoming Letter of Transmittal (form A-6005-315). All transmittal subject headings shall contain, at a minimum, the subcontract number, submittal number, and submittal description.

Submittals shall be provided in electronic format unless available only as a hard copy. Electronic submittals may be sent to [email protected] or delivered via a WRPS designated File Transfer Protocol (FTP) site. Electronic formats must be non-password protected in one of the following formats:

Microsoft® Office Compatible Moving Picture Expert Group (MPEG) Portable Document Format (PDF) Extensible Markup Language (XML) Tagged Image File Format (TIFF) HyperText Markup Language (HTML) Graphics Interchange Format (GIF) Comma Separated Values (CSV) Joint Photographic Experts Group (JPEG) Text (TXT) Windows Media Video (WMV)

NOTE: Please review the submittal process with the WRPS technical contact before submission of the first submittal to ensure the process is understood.

5.0 Acceptance Criteria

Subcontract work products and services shall meet applicable standards as referenced in 6.2 below. All deliverable documentation shall be complete, accurate, legible, and reproducible. Before delivery, design media and documents shall be reviewed by qualified Subcontractor personnel for technical adequacy and appropriate content. The Subcontractor shall attest, in writing, to the accuracy and completeness of the information contained in the final deliverables.

Dimensions of the riser, tank annulus, and air channels in the refractory pad will be verified on the final product. Material and methods of construction will be verified. The facility will be operator friendly and available to both WRPS and vendors supporting WRPS’s review of equipment to be or under development for testing on the mock-up tank.

Unless otherwise approved by Tank Operating Contractor (TOC), all electrical control panels and electrical equipment [a general term including material, fittings, devices, appliances, luminaries (fixtures), apparatus, and the like, used as a part of, or in connection with, an electrical installation] delivered or brought onto the facility in performance of this subcontract must be listed or labeled by an organization currently recognized by OSHA as a Nationally Recognized Testing Laboratory (NRTL).

1. For any system or completed assembly containing electrical systems, the subcontractor shall provide evidence of NRTL listing along with labeling. If a category for the assembly does not exist (e.g. custom-made equipment) the subcontractor shall provide information necessary for WRPS evaluation based on compliance with the provisions of the National Electric Code (NEC) containing the following information:

A. Provide a complete list of components/parts used in the fabrication of the assembly along with the Underwriter’s Laboratory (UL) file number associated with each part number.

B. Provide a summary of conditions of acceptability for any “Recognized” components used in the fabrication of the assembly.

Page 5 of 8 (C-2 041416)

Page 6:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

C. For any unevaluated component, provide descriptive literature to verify the use of the unevaluated component, including product specification and a description of its intended application.

For Industrial Control Panels, the subcontractor shall fabricate and certify the control panel in accordance with the provisions of UL508A and affix his label to completed assembly.

6.0 Configuration Management and Standards

6.1 Configuration Management Requirements

Configuration management requirements for this Release are based upon the types of engineering services being procured and include the TOC standards listed in Section 6.2 Applicable Standards and the statements below.

The Subcontractor is responsible for performing constructability review(s) on the Subcontractor’s design products. The constructability review(s) shall include a check for interferences and fit-up and consider the as-installed configuration as well as interim configurations during the installation process.  In the event that the Subcontractor cannot adequately perform a constructability review due to incomplete or inadequate as-built or field walk-down information, the Subcontractor shall notify the Buyer’s Technical Representative to determine an acceptable alternate technical approach.

6.2 Applicable Standards

No WRPS standards are applicable. The vendor will follow their fabrication standards.

APPLICABLE CODES AND STANDARDS

Number Title1. UL508A

7.0 ESH&Q Requirements

7.1 Quality Assurance Requirements

The subcontractor shall follow standard commercial quality practices.

7.1.1 Supplier Quality Assurance Program

This section is not applicable.

7.1.2 Supplier Quality Assurance Program Changes

This section is not applicable.

7.1.3 Quality Assurance Oversight

WRPS personnel will co-ordinate with the subcontractor to conduct scheduled and periodic oversight of activities or products associated with this scope of work.

Page 6 of 8 (C-2 041416)

Page 7:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

7.1.4 Quality Assurance Requirements for Analytical Laboratory Services

This section is not applicable.

7.2 Price-Anderson Amendments Act Requirements

This 7.2 section and the General Provisions Article 2.11 entitled, Price-Anderson Amendments Act (PAAA), are both determined to be not applicable.

7.3 Special ESH&Q Requirements

Hanford Site access is not authorized for work to be completed under this SOW.

8.0 Verification/Hold Points

Construction of the mock-up tank(s) will following fabrication of air cooling channels for WRPS inspection.

9.0 Reserved

10.0 Work Location/Potential Access Requirements

Not Applicable.

11.0 TrainingNot Applicable

12.0 Qualifications

Welders must be certified by the American Welders Association or equivalent as deemed acceptable by the WRPS Project Manager.

13.0 Special Requirements

Use of Government Vehicles

There is no anticipated need for any Subcontractor employees to use a Government-furnished vehicle in the performance of this statement of work. The Subcontractor’s employees, therefore, are specifically prohibited from driving any Government-furnished vehicles under the performance of this statement of work unless this statement of work is formally so modified by the parties and the employee(s) will present a valid driver’s license to the BTR for review.

Government Property

Pursuant to the Subcontract General Provisions article entitled, “Management of Subcontractor-Held Government-Owned Property,” the following Government-owned property will be provided to the Subcontractor. The Subcontractor will be responsible for managing the Government-owned property as required in the Subcontract General Provisions:

No Government-Owned Property will be provided. Items manufactured under this SOW are considered Government-Owned Property.

The subcontractors may be required to submit handling and storage procedures as follows:

Page 7 of 8 (C-2 041416)

Page 8:  · Web viewThe Tank Operations Contractor (TOC) manages twenty-eight carbon steel, double-shell, million gallon waste storage tanks located at the Hanford site in Washington State.

Procedures regarding the housekeeping and operation of facility utilities (e.g., water, electric etc.).

14.0 Reporting/Administration

Status meetings will be held weekly during the duration of the design and fabricate tasks. Meeting minutes will be written for each weekly meeting (may be performed by either the Vendor or WRPS).

15.0 Workplace Substance Abuse Program Requirements

A Workplace Substance Abuse Program is not required for this SOW.

Page 8 of 8 (C-2 041416)