Top Banner
Home Posts RSS Comments RSS Search Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space Twittear 1 0 1 Me gusta Where building substructures enclose basements, parking garages, or other usable space, groundwater must be kept out. Concrete alone is rarely adequate for this purpose. Moisture can migrate through its microscopic pores, or through other pathways created by shrinkage cracks, form tie holes, utility penetrations, and the joints between concrete pours. To ensure a substructure’s resistance to water entry, two approaches are used: drainage and waterproofing. Drainage draws groundwater away from a foundation, reducing the volume and pressure of water acting on the foundation’s walls and slabs. Waterproofing acts as a barrier, stopping water that reaches the foundation from passing though to the interior. Drainage, consisting of some combination of drainage backfill (well-sorted crushed stone or gravel), drainage mat, and perforated drain piping, is used with almost every building substructure (Figure 2.60). Drainage mat is a manufactured component that may be made of a loose mat of stiff, inert fibers, a plastic egg-crate structure, or some other very open, porous material. It is faced on the outside with a filter fabric that prevents fine soil particles from entering and clogging the drainage passages in the mat. Any subterranean water that approaches the wall descends through the porous material of the mat to the drain pipe at the footing. Perforated drain piping is frequently laid around the outside perimeter of a building foundation. The pipes are 4 or 6 inches (100 or 150 mm) in diameter and provide an open channel in the crushed stone bed through which water can flow by gravity either “to day-light” at a lower elevation on a sloping site, to a municipal storm sewer system, or to a sump pit that can be automatically pumped dry whenever it fills. The pipes are laid at least 6 inches (150 mm) below the top of the basement floor slab tomaintain the groundwater level safely below that of the slab. Perforations in the pipes face downward so that water is drained from the lowest possible level. Where groundwater conditions are severe, rows of perforated pipe may be installed under the basement slab as well (Figure 2.61). Feed Enter your email address: Subscribe Delivered by FeedBurner Follow @Engineershrb Găseşte-ne pe Facebook. The Builder 63 de persoane apreciază The Builder. Plugin social Facebook Îm i place STEEL (169) CONSTRUCTION (143) FOUNDATIONS (95) BUILDINGS (40) HEAVY TIMBER FRAME CONSTRUCTION (22) PILE FOUNDATIONS (21) SOILS (17) BRIDGES (16) RETAINING WALLS (16) EARTHQUAKES (15) WOOD (12) EXCAVATIONS (11) CONCRETE (10) STRUCTURAL DAMAGE (8) Search Engineering and Construction DESIGN AND CONSTRUCTION (6) FLOORS (6) COLUMNS (5) FOOTINGS (5) GEOSYNTHETICS (5) MAT FOUNDATIONS (5) MOISTURE (5) BEAMS (4) GEOLOGY (4) BASEMENT WALLS (3) INSTRUMENTATION (3) METAL (3) PIER FOUNDATIONS (3) PROJECT (3) SHEET PILE WALLS (3) SITE EXPLORATION (3) SUSTAINABILITY (3) EARTH MATERIAL (2) EQUIPMENT (2) GROUND (2) HOLDING-DOWN SYSTEMS (2) PLATE GIRDERS (2) ROCK (2) Wood Light Frame Construction (2) ANCHORED WALLS (1) Basement (1) COMPENSATED FOUNDATIONS (1 ) CRIB WALL (1 ) FLOATING FOUNDATIONS (1) GROUNDWATER (1) SITE WORK (1) TIMBER (1) TIMBER PILES (1) Waterproofing and Drainage (1 )
7

Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space _ Engineering and Construction.pdf

Nov 09, 2015

Download

Documents

Ciprian Cipry
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 1/7

    Home Posts RSS Comments RSS Search

    Waterproofing and Drainage - building substructures enclosebasements, parking garages, or other usable space

    Twittear 1

    0

    1Me gusta

    Where building substructures enclose

    basements, parking garages, or other

    usable space, groundwater must be

    kept out. Concrete alone is rarely

    adequate for this purpose. Moisture

    can migrate through its microscopic

    pores, or through other pathways

    created by shrinkage cracks, form tie

    holes, utility penetrations, and the

    joints between concrete pours. To

    ensure a substructures resistance to

    water entry,

    two approaches are used: drainage

    and waterproofing. Drainage draws

    groundwater away from a foundation,

    reducing the volume and pressure of water acting on the foundations walls and slabs.

    Waterproofing acts as a barrier, stopping water that reaches the foundation from

    passing though to the interior.

    Drainage, consisting of some combination of drainage backfill (well-sorted crushed

    stone or gravel), drainage mat, and perforated drain piping, is used with almost every

    building substructure (Figure 2.60). Drainage mat is a manufactured component that

    may be made of a loose mat of stiff, inert fibers, a plastic egg-crate structure, or some

    other very open, porous material. It is faced on the outside with a filter fabric that

    prevents fine soil particles from entering and clogging the drainage passages in the

    mat. Any subterranean water that approaches the wall descends through the porous

    material of the mat to the drain pipe at the footing. Perforated drain piping is

    frequently laid around the outside perimeter of a building foundation. The pipes are 4

    or 6 inches (100 or 150 mm) in diameter and provide an open channel in the crushed

    stone bed through which water can flow by gravity either to day-light at a lower

    elevation on a sloping site, to a municipal storm sewer system, or to a sump pit that

    can be automatically pumped dry whenever it fills. The pipes are laid at least 6 inches

    (150 mm) below the top of the basement floor slab tomaintain the groundwater level

    safely below that of the slab. Perforations in the pipes face downward so that water is

    drained from the lowest possible level. Where groundwater conditions are severe,

    rows of perforated pipe may be installed under the basement slab as well (Figure

    2.61).

    Feed

    Enter your email address:

    Subscribe

    Delivered by FeedBurner

    Follow @Engineershrb

    Gsete-ne pe Facebook.

    The Builder

    63 de persoane apreciaz The Builder.

    Plugin social Facebook

    mi place

    STEEL (169) CONSTRUCTION(143) FOUNDATIONS (95)BUILDINGS (40) HEAVY TIMBER FRAMECONSTRUCTION (22) PILE FOUNDATIONS (21)

    SOILS (17) BRIDGES (16) RETAINING WALLS

    (16) EARTHQUAKES (15) WOOD (12)

    EXCAVATIONS (11) CONCRETE (10)

    STRUCTURAL DAMAGE (8)

    Search

    Engineering and Construction

    DESIGN AND

    CONSTRUCTION (6) FLOORS (6) COLUMNS (5)

    FOOTINGS (5) GEOSYNTHETICS (5) MAT

    FOUNDATIONS (5) MOISTURE (5) BEAMS (4)

    GEOLOGY (4) BASEMENT WALLS (3)

    INSTRUMENTATION (3) METAL (3) PIER

    FOUNDATIONS (3) PROJECT (3) SHEET PILE WALLS

    (3) SITE EXPLORATION (3) SUSTAINABILITY (3)

    EARTH MATERIAL (2) EQUIPMENT (2) GROUND (2)

    HOLDING-DOWN SYSTEMS (2) PLATE GIRDERS (2)

    ROCK (2) Wood Light Frame Construction (2)

    ANCHORED WALLS (1) Basement (1) COMPENSATED

    FOUNDATIONS (1) CRIB WALL (1) FLOATING

    FOUNDATIONS (1) GROUNDWATER (1) SITE WORK (1)

    TIMBER (1) TIMBER PILES (1) Waterproofing and Drainage

    (1)

  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 2/7

    Figure 2.60 Two methods of relieving water pressure around a building substructure by drainage.

    The gravel drain (left) is hard to do well because of the dif culty of depositing the

    crushed stone and back ll soil in neatly separated, alternating layers. The drainage

    mat (right) is easier and often more economical to install.

    Figure 2.61 For a high degree of security against substructure ooding, drainage both around and

    under the basement is required, as seen here in a section view. Above-slab drainage is used

    in buildings with mat foundations.

    On most foundations, some form of water-repelling barrier is also used to protect

    against the pas-

    sage of groundwater. Dampproofing is a moisture-resistant cement plaster or asphalt

    compound commonly applied to residential basement walls and to other substructures

    where groundwater conditions are mild or waterproofing requirements are not critical.

    Cement plaster dampproofing, or parge coating, is light gray in color and troweled on.

    Asphalt or bituminous dampproofing is dark in color and is applied in liquid form by

    spray, roller, or trowel. Dampproofing is less expensive and less resistant to water

    passage than true waterproofing.

    Waterproofing, unlike dampproofing, can prevent the passage of water even under

    conditions of hydrostatic pressure. It is used where groundwater conditions are

    severe or the need to protect subgrade space from moisture is critical. Waterproof

    mem-branes are most commonly formulated from plastics, asphalt compounds, or

    synthetic rubbers and come in a great variety of forms.

    Liquid waterproofing is applied by spray gun, roller, or squeegee and then allowed

    to cure in place. It is easy to install and easy to form around complex shapes. When

    fully cured, the finished membrane is seamless and fully bonded to the underlying

    substrate. However, because liquid membranes are formed in the field, they are

    subject to uneven application, and the surfaces to which they are applied must be

    clean, smooth, and dry to ensure reliable adhesion of the membrane.

    Preformed sheet membrane waterproofing may be adhered or mechanically fastened

    to substructure walls

    or laid loosely over horizontal surfaces (Figure 2.62). Fabricated under controlled

    factory conditions, sheet membranes are reliably uniform in material quality and

    thickness.

    Search

    Blog Archive

    2015 (4)

    2014 (31)

    2013 (400)

    December (4)

    November (4)

    October (4)

    September (5)

    August (4)

    July (5)

    June (3)

    May (9)

    UpDown Construction

    Backfilling - Construction

    SHALLOW FORST-PROTECTED

    FOUNDATIONS

    Basement Insulation

    Waterproofing and Drainage - building

    substructure...

    GEOTEXTILES - CONSTRUCTION OF

    BUILDING

    UNDERPINNING - Stabilizing the

    Foundations of a Bu...

    Buildings Seismic Base Isolation

    Pile Materials - Foundations.

    April (14)

    March (25)

    February (53)

    January (270)

  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 3/7

    Figure 2.62 A diagrammatic representation of the placement of sheet membrane waterproo ng

    around a basement. A mud slab of low-strength concrete was poured to serve as

    a base for placement of the horizontal membrane. Notice that the vertical and

    horizontal membranes join to wrap the basement completely in a waterproof enclosure.

    However, they can be more difficult to form around complex shapes, and the seams

    between sheets, which are sealed in the field, may be subject to lapses in quality.

    Sheet membranes that are loosely laid or mechanically fastened can be used over

    substrates that will not bond with liquid-applied or adhered sheet membranes. They

    are also a good choice where substrate cracking or movement may be expected,

    because such movement is less likely to stress or damage the membrane. An

    advantage of adhered membranes (both sheet and liquid) is that in the case of a

    defect, water cannot travel far under the membrane, limiting the extent of water

    damage that may occur and simplifying the tracing of leaks.

    Bentonite waterproofing is made from sodium bentonite, a naturally occurring, highly

    expansive clay. It is most often applied as preformed sheets consisting of dry clay

    sand-wiched within corrugated card-board, geotextile fabric, or plastic sheets (Figure

    2.63). When bentonite comes in contact with moisture, it swells to several times its

    dry volume and forms an impervious barrier to the further passage of water. Bentonite

    sheets can be placed directly on the soil under a concrete slab on grade or

    mechanically attached to uncured, damp concrete walls. In slurry form, bentonite can

    be sprayed even onto highly irregular, rough stone walls. The swelling behavior of

    bentonite clay also allows it to adjust to cracking and movement in the substrate.

  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 4/7

    Figure 2.63 Waterproo ng in progress on a concrete foundation. Leftmost: the

    bare foundation wall remains exposed. Middle: bentonite waterproo ng panels

    are fastened in place. These panels are lined on the outer face with a black-

    colored, high-density plastic that adds to the waterproo ng qualities of the panel.

    Right: drainage mat has been installed over the waterproo ng. The mats outer

    face of lter fabric is lightly dimpled, telegraphing the egg crate structure of

    the underlying molded plastic panel. The top edge of the mat is secured in

    place with an aluminum termination bar that holds the panel in place and keeps

    dirt and debris from falling behind the panel. Lower right: white perforated

    drain piping can be seen, temporarily supported on wood blocking and

    running alongside the footing. (Photo by Joseph Iano)

    Integral waterproofing includes cementitious plaster or crystalline admixtures for

    concrete or mortar

    that react chemically to stop up the pores of these materials and render them

    watertight. It may be applied

    to the surface of existing concrete or masonry or used as an admixture in new

    concrete. Unlike most other waterproofing materials, many integral waterproofing

    materials can be applied as negative side waterproof-

    ing, that is, applied to the inner side of a concrete wall acting to resist water passage

    from the opposite side.

    Blind-side waterproofing is installed prior to the pouring of concrete walls. This

    occurs most commonly when a substructure wall is built close to a propertys edge,

    and excavation cannot be enlarged beyond the property line to permit workers access

    to the outer face of the wall after its construction.

    Drainage matting is first applied directly to the excavation sheeting, and then any of a

    number of possible waterproofing membranes are applied over the drainage mat.

    Later, the concrete wall is poured against the membrane. The sheeting remains

    permanently in place (Figure 2.64).

  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 5/7

    Figure 2.64

    Blind-side waterproo ng is used where there is no working space between a sheeted excavation and the

    outside of the foundation

    wall. The drainage mat and waterproof membrane are applied to the sheeting; then the basement wall is

    poured against them.

    Joints in construction require special attention to ensure water-tightness. Preformed

    waterstops made of plastic, synthetic rubber, or metal can be cast into the mating

    concrete edges of both moving and nonmoving joints to block the passage of water

    (Figures 2.65 and 2.66). Waterstops for nonmoving joints such as between concrete

    pours of a wall or slab can also be made of strips of bentonite or mastic that are

    temporarily adhered to the edge of one pour. After the adjacent pour is complete,

    these stops remain embedded in the joint, where they form a watertight barrier

    (Figure 2.67).

    Figure 2.65 A synthetic rubber waterstop is used

    to seal against water penetration at

    movement joints and at joints between

    pours of concrete in a foundation. The

    type shown here is split on one side so

    that its halves can be placed at against

    the formwork where another wall will join

    the one being poured. A fter the concrete

    has been poured and cured and the

    formwork has been removed from the

    rst wall, the split halves are folded back

    together before the next wall is poured.

    Most waterproofing systems are inaccessible once building construction is complete;

    they are ex-

    pected to perform for the life of the building, and even small defects in installation can

    allow the passage of large volumes of water.

    For these reasons, waterproofing membranes are inspected carefully during

    construction and horizontal membranes are often flood tested (submerged for an

    extended period time while leak-checking is performed) to detect the presence of

    defects while repairs can still be easily made. Once inspection and testing are

    complete, membranes are covered with a protection board, insulation board, or

    drainage matting to shield the membrane from prolonged exposure to sunlight and to

    prevent physical damage during soil backfilling or subsequent construction operations.

  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 6/7

    Categories: BUILDINGS, Waterproofing and Drainage

    Figure 2.66

    A rubber waterstop ready for the next pour of a concrete wall, as diagrammed in

    Figure 2.65. (Courtesy of Vulcan Metal Products, Inc., Birmingham, A labama)

    Figure 2.67

    A bentonite waterstop is adhered to

    a concrete footing prior to casting

    of the concrete wall above. Later,

    if groundwater seepage occurs, the

    bentonite will swell to fully seal the joint

    between the two pours. The waterstop

    is positioned to the side of the steel

    reinforcing bars closer to the walls

    exterior, also protecting the reinforcing

    from moisture and corrosion. However,

    because of bentonites expansive force,

    the waterstop must not be positioned

    too close to the surface of the wall, or

    when it swells, it could cause portions of

    concrete to split away or spall.

    Related Post:Waterproofing and Drainage

    Denison HydraulicRepair.

    Denison Hydraulic Pump & MotorRepair Experts. In-House Shop.

  • 27.02.2015 Waterproofing and Drainage - building substructures enclose basements, parking garages, or other usable space | Engineering and Construction

    http://www.thecivilbuilders.com/2013/05/waterproofing-and-drainage-building.html 7/7

    Newer Post Older Post

    BUILDINGS

    0 comentarios:

    Post a Comment

    Enter your comment...

    Comment as: Google Account

    Publish Preview

    Home

    Engineering and Construction | Based on the Design by Tricks-Collection | Unlimited Entertainment like TV Shows and Movies collections

    ROOF LIVE LOAD

    LIVE LOADS IN A BUILDING

    DEAD LOADS IN A BUILDING

    DBB METHODINVITATIONAL BIDDING

    DBB METHODCOMPETITIVE SEALED PROPOSAL

    DBB METHODCOMPETITIVE SEALED BIDDING

    DESIGN-BID-BUILD PROJECT DELIVERY METHOD

    (BUILDING) PROJECT PREDESIGN PHASE

    BUILDING PROJECT DELIVERY PHASES

    A NATURALLY GROWN BUILDING MATERIAL