BJi:FORE THE NE\V l\;IEXICO PUBLIC REGULATION COl\;lMISSION IN THE MATTER OF THE APPLICATION ) OF PUBLIC SERVICE COMPANY OF NEW ) l\IIEXICO FOR APPROVAL TO ABANDON ) SAN JUAN GENERATING STATION UNITS ) 2 AND 3, ISSUANCE OF CERTIFICATES ) OF PUBLIC CONVENIENCE AND ) NECESSITY FOR REPLACEl\;IENT PO\VER ) RESOURCES, ISSUANCE OF ACCOUNTING ) ORDERS AND DETERMINATION OF ) RELATED RATEMAKING PRINCIPLES AND) TREATMENT, ) ) PlJBLIC SERVICE COMPANY OF NE\V ) l\IIEXICO, ) ) Applicant ) ______________________________ ) Case No.13-00 _____ -UT DIRECT TESTil\;10NY AND EXHIBITS OF PATRICK J, O'CONNELL December 20, 2013
76
Embed
V )/media/Files/P/PNM... · PNM Exhibit PJ0-6 AFFIDAVIT Resume of Patrick J. O'Connell Current Load and Resource Projections Summary of Regional Haze Compliant Portfolios Revised
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
BJi:FORE THE NE\V l\;IEXICO PUBLIC REGULATION COl\;lMISSION
IN THE MATTER OF THE APPLICATION ) OF PUBLIC SERVICE COMPANY OF NEW ) l\IIEXICO FOR APPROVAL TO ABANDON ) SAN JUAN GENERATING STATION UNITS ) 2 AND 3, ISSUANCE OF CERTIFICATES ) OF PUBLIC CONVENIENCE AND ) NECESSITY FOR REPLACEl\;IENT PO\VER ) RESOURCES, ISSUANCE OF ACCOUNTING ) ORDERS AND DETERMINATION OF ) RELATED RATEMAKING PRINCIPLES AND) TREATMENT, )
) PlJBLIC SERVICE COMPANY OF NE\V ) l\IIEXICO, )
)
Applicant ) ______________________________ )
Case No.13-00 _____ -UT
DIRECT TESTil\;10NY AND EXHIBITS
OF
PATRICK J, O'CONNELL
December 20, 2013
NMPRC CASE NO. 13-00 -UT INDEX TO THE DIRECT TESTIMONY OF PATRICK J, O'CONNELL
WITNESS FOR PUBLIC SERVICE COMPANY OF NEW MEXICO
I. INTRODUCTION, PURPOSE AND KEY CONCLUSIONS ................................ l
U. PNM'S EXISTING RESOURCES .......................................................................... 5
III. COMPARISON OF POTENTIAL RESOURCE PORTFOLIOS TO COMPLY WITH THE REGIONAL HAZE RULE ................................................ 9
IV. RELATIONSHIP TO 2014-2033 IRP ................................................................... 23
V. CONCLUSIONS ................................................................................................... 25
PNM Exhibit PJ0-1
PNM Exhibit PJ0-2
PNM Exhibit PJ0-3
PNM Exhibit PJ0-4
PNM Exhibit PJ0-5
PNM Exhibit PJ0-6
AFFIDAVIT
Resume of Patrick J. O'Connell
Current Load and Resource Projections
Summary of Regional Haze Compliant Portfolios
Revised SIP Load and Resource Projections
Resource Modeling Assumptions
SJGS Unit 4 Additional Capacity Portfolio Comparison
2 3 Q.
4 A.
5
6
7
8 Q.
9
10 A.
11
12
13
14
15
16
17
18
19 Q.
20
21 A.
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
I. INTRODUCTION, PURPOSE AND KEY CONCLUSIONS
PLEASE STATE YOUR NA~IE, POSITION AND BUSINESS ADDRESS.
My name is Patrick J. O'Connell. I am Director, Planning and Resources, for
Public Service Company of New Mexico ("PNM'' or "Company"). My address is
414 Silver Avenue, S\V, Albuquerque, New Mexico 87102.
PLEASE DESCRIBE YOUR RESPONSIBILITIES AS DIRECTOR,
PLANNING AND RESOURCES.
I oversee PNM' s Integrated Resource Planning <md Energy Efficiency Design teams.
The Integrated Resource Planning team is resporL.;;ible for developing PNM' s resource
plans and the regulatory filings to support those resource plans, including PNM's
Integrated Resource Pl<:m ("IRP") that is required to be filed every three years with the
New Mexico Public Regulation Commission ("Commission" or ''NMPRC") tmder
17.7.3 NMAC ("IRP Rule"). The Energy Efficiency Design team develops PNM's
energy efficiency and load management program plans and the regulatory filings to
support them.
HAVE YOU PREVIOUSLY TESTIFIED IN UTILITY REGULATORY
PROCEEDINGS?
Yes. A list of the NMPRC proceedings in which I have either testified or filed
testimony is included in the statement of my expe1ience and qualifications that 1s
attached to my testimony as PNM Exhibit PJ0-1.
Q.
2 A.
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
N~1PRC CASE NO. 13-00 -UT
'WH.A.T IS THE PURPOSE OJ<"' YOUR DIRECT TESTIMONY?
My testimony demonstrates that the most cost-effective means of complying with the
Regional Haze Rule adopted by the Environmental Protection Agency ("'EPA")
pursuant to the Clean Air Act is to retire Units 2 and 3 at the San Juan Generating
Station ("SJGS") and install selective non-catalytic reduction technology ("SNCR'') on
the remaining two units in accordance with the Revised State Implementation Plan
("Revised SIP"), and replace the capacity of the retired units with a portfolio of
resources that includes nuclear, natural gas, renewable generation and additional
capacity in SJGS Unit 4. Specifically, I will:
• Describe the costo;; and benefit-> to PNM's customers of complying with the Revised
SIP as opposed to complying with the Federal Implementation Plan ("FIP") adopted
by the U.S. Environmental Protection Agency ("EPA'');
• Describe how PN'M used the IRP process to obtain public input on the plant
retirements and additions proposed in this filing and how it will use the ongoing IRP
process to help refine the selection of resource additions for which PNM will seek
Commission approval in the future: and
• Describe why it is in the public interest to approve the plant retirements and
certificates of public convenience and necessity ("CCN") for plant additions that
PNM is requesting in this case.
In the course of developing these points, I will also describe how complying with the
Revised SIP will affect PNM's existing generation resource pmtfolio and identify and
compare alternative generation resource po1tfolios that could comply with the Regional
2
2
3
4 Q.
5 A.
6
7
8
9
10
11
12
13 Q.
14
15 A.
16
17
18
19
20
21
DIRECT TESTilVIONY OF PATRICK J. O'CONNELL
NJ\!IPRC CASE NO. 13-00 -UT
Haze Rule requirements at SJGS, but at higher cost than what PNM is proposing in this
proceeding.
DO YOU HAVE ADDITIONAL EXHIBITS?
Y cs. They are as follows:
• PNM Exhibit PJ0-2: Cunent Load and Resource Projections
• PNM Exhibit PJ0-3: Summary of Regional Haze Compliant Portfolios
• PNN1 Exhibit PJ0-4: Revised SIP Load and Resource Projections
• PNM Exhibit PJ0-6: SJGS Unit 4 Additional Capacity Portfolio
Comparison
PLEASE EXI>LAIN THE DIFFERENCE BETWEEN THE REVISED SIP 1\i~D
THE FIP.
Both the Revised SIP and the FIP are implementation plans requiring SJGS to take
specified actions in order to comply with the Regional Haze Rule. Both require
investment in Pl\TM's generation fleet. The Revised SIP, in comparison to the FIP.
allows PNM to invest in a more balanced resource portfolio that will reduce overall
costs to PNM's customers and will reduce the environmental impact of the service PN11
provides. The requirements at SJGS tmder the Revised SIP and the FIP are summmized
as follows:
3
2
3
4
5
6
7
8
9
10
11 Q.
12 A.
13
14
15
16
17
18
19
20
21
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -GT
• The Revised SIP requires installation of SNCR technology on SJGS Units 1 <md 4
by the later of J <muary 31, 2016, or 15 months after the Revised SIP is approved by
EPA, and retirement of SJGS Units 2 and 3 by December 31, 2017.
• The FIP requires installation of selective catalytic reduction ("SCR") teclmology on
all four units of SJGS by September 21, 2016.
The Revised SIP must be approved by the EPA before it will replace the FIP. The
process that led to the two implementation plans is described in Mr. Dam ell· s
testimony.
\VHAT ARE THE PRINCIPAL CONCLUSIONS OF YOUR TESTIMONY?
First, retiring SJGS Units 2 and 3 and installing SNCR teclmology on Units l and 4 in
accordance with the Revised SIP, and replacing the retired capacity by adding nuclear,
natural gas, renewable resources and additional capacity in SJGS Unit 4, is in PNM's
customers' best interest because these actions are less costly over the 20-year planning
period th<m installing SCR technology at SJGS, as required by the FIP. Second, the
most cost-effective portfolio of resources to replace the retired coal capacity at SJGS
includes the addition of 134 MW of capacity in Palo Verde Nuclear Generating Station
("'PVNGS'') Unit 3 at a cost of $2,500/kW. Third, this most cost-effective portfolio of
resources is less risky compared to either the FIP or a portfolio that relies more heavily
on gas-fired generation rather than using PVNGS Unit 3. The Revised SIP allows PNM
to invest money that would be spent on SCR tmder the FIP on generation additions that
will reduce costs in the futme, reduce the risk associated with coal generation in PNM' s
4
2
3
4
5
6
7
8
9
10
] 1
12
13
14 15 Q.
16
17 A.
18
19
20
21
22
23
DIRECT TESTlMONY OF PATRICK J. O'CONNELL
N.MPRC CASE NO. 13-00 -UT
supply portfolio and reduce the emissions associated with generating electricity to meet
customers' needs. The most cost-effective portfolio of new resources to replace Units 2
and 3 includes nuclear, solar, gas peaking resources and additional capacity in SJGS
Unit 4. TI1e investment in these replacement resources will produce lower fuel and
operation and maintenance costs going fmward, which reduces future costs to customers
compared to compliance with the FIP. The resulting replacement resources will reduce
greenhouse gas emissions without a significant increase in reliance upon natural gas
generation so as to reduce the risk of cost increases associated with future environmental
regulations affecting greenhouse ga<; emitting sources and the risk associated with price
volatility of natural gas. These conclusions are based on a comprehensive analysis of
various resource pmtfolio options using the Strategist® modeling software and other
quantitative <md qualitative analytic tools.
II. PNl\tl'S EXISTING RESOURCES
PLEASE DESCRIBE Pl\M'S EXISTING PORTFOLIO OF GENERATION
RESOURCES.
PNM provides service to its half million customers by generating electricity at PNM-
owned power plants and by purchasing capacity and energy tmder long tenn power
purchase agreements ("PP A"), a..s well as by making short term market purcha.<;es as
needed. Electricity is delivered from generation resources to PNM' s customers through
a system of elecuic transmission and distribution lines. The current mix of generation
resources that provides NMPRC-regulated electric service includes resources
fueled by coal, nuclear and natural gas and wind and solar pO\vered resources as
5
1
2
3
4
5
6
7 8
I
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
shown on Table PJ0-1. In addition to the supply-side resources shown on this
table, PNM reduces the need for electric generation using demand-side resources
such as energy efficiency and load management programs. Other PNM programs
and tariffs encourage PNM customers to install solar photovoltaic (''PV") systems
behind their meters, which reduce the amount of electricity PNM generates to
serve its customers. Presently, over 3,800 PV systems are in place.
Table PJ0-1 PNM' E . f G ti R 1 s .XIS mg en era on esources
PNM Share Operating In-Service
Resources Fuel Ty[!e PNM Share ofCapaciti Agent Date
OVIW's2
San Juan Coal 46.4 o/c 783 1973-1982 PNM
Palo Verde Units Nuclear 10.2% 268 1985-1986 APS
1&2 Four Comers Coal 13% 200 1969-1970 APS Units 4 & 5
Afton Natural Gas 100% 230 ' 2002 PNM
Reeves Natural Gas lOO% 154 1958-1962 PNM
Lordsburg Natural Gas 100% 80 2002 PNM
Luna Energy Natural Gas 33.3% 185 2006 PNM Facility
Delta (PPA) Natural Gas N/A 138 2001 Delta-Person LP
Valencia (PPA) I Natural Gas N/A 14:"i 2008 SWG
Valencia Power LLC
NMWEC (PPA) Wind N/A 204 2003 I Next Era Resources
PNM Solar PV Solar I 00 r;1c, 22.5 2011 PNM
PNM Solar PV Solar 100 0{; 21.5 2013 PNM
Lightning Dock Geothermal 100% 10 2014 Cyrc LLC
TOTAL 2,441
6
I
I
I
I
I
I
1 Q.
2
3
4 A.
5
6
7
8
9
10
ll
l2
13
14
15 Q.
16
17
18
19 A.
20
21
22
23
DIRECT TESTIJ\!IONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
DOES Pl\M HAVE APPLICATIONS PEl'iTIING AT THE COJ\it\DSSION TO
ACQUIRE GE~'ERATION RESOURCES L'J ADDITION TO THE
RESOURCES REQUESTED IN TillS CASE?
Yes. PNM has requested approval to construct an additional 23 MW of solar PV
capacity at various New Mexico locations and to purchase the full output of the Red
Mesa Wind facility, a 102 MW wind facility located in Cibola County, New Mexico. If
approved, these resources will provide electricity to PNM's customers by January 1,
2015. Also pending before the Commission is PNM's request for a CCN for the La Luz
Energy Center, a 40 MW natural gas peaking plant that PNM intends to constmct in
Valencia County, New Mexico, and bring on line before the 2016 summer peak. For
resource planning purposes I have a'>sumed that these applications will be granted. The
need for these resources is not related to or affected by the retirement of SJGS Units 2
and 3.
EXCEPT FOR THE RETIREMENT OF SJGS UNITS 2 Al~U 3 AS
REQl!'ESTED IN TillS CASE, DID PNM A._'iSUJ\!IE THAT ALL EXISTING
RESOURCES WILL BE AVAILABLE THROUGH THE 20-YEAR
PLAl'JNING PERIOD?
Yes. As discussed in Mr. Hom's testimony, PNNl will renew or purchase ownership of
the leased portions of its interest in PVNGS Units 1 and 2 at the end of the initial or
extended lea-;e terms, which will occur dUling the 20-year plamling period. PNM has
obtained Connnission approval to purchase Delta, so that resource is modeled as an
owned resomce that remains in PNM' s portfolio through the planning period. The New
7
2
3
4
5
6
7
8
9
lO Q.
11
12 A.
13
14
15
16
17
18
19
20
21
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NlVIPRC CASE NO. 13-00 -UT
Mexico Wi11d Energy Center PP A and the Valencia PPA both expire in 2028, within the
20-year planning period, but, for resource modeling, I am assuming in all scenarios that
these resources remain in PNM's pmtfolio. Sin1ilarly, PNM's demand response
program contracts expire prior to the summer peak in2017, but I am assmning the DR
resources remain or are replaced with something similar in PNM' s portfolio. However,
before the PPAs and demand response contracts expire, PNM will evaluate the most
cost effective alternative and will only renew a PP A if the tenns and conditions are
better than any available altemative.
PLEASE DESCRffiE S.JGS'S CONTRffiUTION TO PNM'S EXISTING
GENERATION PORTFOLIO.
SJGS provides the most capacity and energy of any of PNM's supply resources. It
provides approximately 34% of PNM's capacity to meet summer peak demand as
shown in PNM Exhibit PJ0-2, PNM's current load and resource table. SJGS
supplies approximately 50.1% of the energy to serve PNM' s retail customers.
PNM's next largest jurisdictional resources, PVNGS Units 1 and 2, provide
approximately 12% of PNM's capacity and 20% of the energy to serve PNM's retail
customers. SJGS is an economic base load generation resource providing both capacity
and energy used to provide reliable, cost-effective customer service.
8
1
2
3 4 Q.
5
6 A.
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
III. CO.MPARISON OF POTENTIAL RESOURCE PORTFOLIOS TO
COMPLY WITH THE REGIONAl. HAZE RULE
PLEA.'-;E DESCRIBE THE PURPOSE OF THIS PART OF YOUR
TESTIMONY.
In this pmt of my testimony I will show that the Revised SIP and a combination of
nuclear, gas, renewable resources and additional capacity in SJGS Unit 4 results in the
most cost-effective resource portfolio for PNM's customers. The analysis is based on a
compmison of estimated utility costs over a twenty year period. Another consideration
in the analysis is the risk that actual costs over the planning period will vary significantly
from the projections used in the modeling. Consequently, I will compare different
resource po1tfolios to show their potential to minimize the risk that future costs could he
significm1tly different than estimated today due to volatile natural gas prices m1d a range
of future costs associated with m1ticipated environmental regulation. I will compare four
resource portfolios that would meet the requirements of the Regional Haze Rule and
enable PNM to maintain reliable electric service. The four portfolios are presented in
PNM Exhibit PJ0-3 m1d are described as follows:
• Comply with the Regional Haze Rule as required by the Revised SIP by installing
SNCR on SJGS Units 1 and 4, retiring Units 2 m1d 3, and replacing the retired
capacity with a mix of resources including PVNGS Unit 3, new solar generation, a
gas peaking plant m1d additional capacity in SJGS Unit 4;
• Comply with the Regional Haze Rule as required by the Revised SIP by installing
SNCR on SJGS Units l and 4, retiring Units 2 and 3, <.md replacing the retired
9
2
3
4
5
6
7
8
9 Q.
10
11 A.
12
13
14
15
16
17
18
19
20
21 Q.
22
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
capacity with new solar generation, gas peaking capacity and additional capacity in
SJGS Unit4;
• Comply with the Regional Haze Rule as required by the FIP by installing SCR on
all four units at SJGS (no replacement capacity is needed in this case); and
• Comply with the Regional Haze Rule by retiring all fom units at SJGS and
replacing the retired capacity with PVNGS Unit 3 and a combination of natural gas
and renewable energy resources.
HO\V DID PNNI IDENTIFY THE 1\-IOST COST -EI<'FECTIVE
REPLACEMENT PO\VER PORTFOLIOS?
PNM used an integrated planning approach to detennine the most cost-effective
portfolios for each of the Regional Haze Rule compliance strategies. This involved
assessing the costs and production impacts of installing SNCR or SCR at SJGS as well
as evaluating potential replacement resources for tmit retirements at SJGS. Resources
were analyzed not just as stand-alone resources, but also considering their effect on
overall system costs. In addition to PVNGS Unit 3, gas peaking, solar generation and
additional capacity in SJGS Unit 4, Pm1 considered other types of natural gas capacity
and wind resources while a.;;smning continued growth of PNM's energy efficiency
resources and distributed generation.
VVHAT DOES YOUR A.~ALYSIS SHO\V AS THE lVIOST COST-EFFECTIVE
REGIONAL HAZE CO.MPLIA.1"JCE PORTFOLIO?
10
A.
2
3
4
5
6
7
8 Q.
9 A.
10
11
12
13
14
15
16
17 Q.
18
19 A.
20
21
22
DIRECT TESTIMONY OF PATRICK .J. O'CONNELL
Nl\'IPRC CASE NO. 13-00 -UT
TI1e most cost-effective of the four portfolios is the first- meeting the Regional Haze
Rule requirements through the Revised SIP and replacing the retired SJGS capacity with
PVNGS Unit 3. solar generation, a gas peaking unit and additional capacity in SJGS
Unit 4. rD1is portfolio is the lowest in cost and provides the best protection against the
risks of future cost increases due to volatile natural ga-. prices and anticipated
environmental regulation.
PLEASE DESCRIBE PVNGS.
PVNGS is located west of Phoenix, Arizona, and is the nation's largest nuclear
generating station. The three units at PVNGS came on line between 1986 and 1988
and have operating licenses that extend through 2047. PNM owns 10.2% of each
of the units at PYNGS. but only Unit 1 and Unit 2 have CCNs to serve PNM's
NMPRC jurisdictional customers. As discussed by PNM witnesses Mr. Sategna,
Mr. Ortiz and Mr. Hom, PYNGS Unit 3 is a resource that is currently "excluded"
from PNM' s jurisdictional generating resources.
WHAT COST DID YOU ASSUl\'IE FOR PALO VERDE lJNIT 3 IN YOUR
A.1"'Al. YSIS?
I assumed that PNM would add Palo Verde Unit 3 at a cost of $2,500/kW, or $335
million. This is the value at which PNNI is willing to offer this resource for use as
certificated plant to serve NMPRC jurisdictional customers, as explained in Mr.
Dan1ell's testimony. I will show that PVNGS Unit 3 is the most cost effective SJGS
11
1
2
3
4 Q.
5 A.
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
DIRECT TESTIMONY OF PATRICKJ. O'CONNELL
NMPRC CASE NO. 13-00 -UT
replacement option for PNM' s customers at a cost significantly higher than the
$2,500/kW proposed by PNM.
HO\V DID PNM DETElli'VIL~TE PORTFOLIO COSTS?
For this analysis, PNM used the Strategist® modeling software. Strategist® is a
comprehensive long-range resource planning tool for electric utilities. The Strategist®
model utilizes a proprietary, dynanlic programming algorithm to conduct a rigorous
evaluation of up to 5,000 mlique resource portfolios and selects and ranks the resource
pmtfolios based on various user-specified criteria. Strategist® is capable of modeling a
wide range of resource alternatives such as energy efficiency <md demand side
alternatives. storage technologies, renewable <.md thennal generating units, various types
of power purchase and sales agreements and the electric market. Strategist® identifies the
least-cost resource portfolio according to the net present value ("NPV") of total utility
cost that meets user-designated constraints such as reserve margin. loss of load hours,
emissions mandates, constmction lin1itations and renewable portfolio standards.
Strategis{9 input data includes fuel price projections, new resource construction costs,
demand <md energy forecasts and shapes, energy efficiency projectiom, resource
petfonnance characteristics such a-; dispatchability, transmission capacity attributes,
resomce retirements, planned outages and others. Strategist@ optimizes portfolio
selection by calculating capital requirements, fuel costs and O&M costs using economic
dispatch to meet demand and energy requirements for each of the thousands of portfolio
options and ranking each by the net present value of total utility cost. Strategist@
12
1
2
3
4
5
6
7
8
9
lO
11
12 Q.
13
14
15 A.
16
17
18
19
20
21
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
Nl\IPRC CASE NO. 13-00 -UT
considers both the existing resource portfolio and new resource options when
detennining the most cost effective portfolio for a given scenmio.
The model output, as summarized in PNM Exhibit PJ0-3, includes the NPV of the
portfolio over the 20-year analysis period, study period loss of load probability, which is
a mea<;ure of the portfolio's reliability, and the range of the risk that the cost of the
po11folio over the 20-year period will be higher or lower due to fluctuations in electricity
energy and demand requirements, natural gas prices and environmental regulations.
Additionally, Strategist® provides a summary of resource type and capacity utilization of
existing and new resource additions by year over the 20-year plmming period.
·wiLL RESOURCES IN ADDITION TO PVNGS UNIT 3 Al'ID ADDITIONAL
CAP A CITY IN SJGS UNIT 4 BE REQuiRED IF lJNITS 2 Ml> 3 ARE
RETIRED?
Yes. Although our analysis to identify those resources is on-going as pmt of the IRP
evaluation process, the analysis conducted to date indicates that in addition to PVNGS
Unit 3 and additional capacity in SJGS Unit 4 the near-term resource additions that
would most economically replace the generation capacity of the retired units at SJGS are
solar photovoitaic generation and a gas-fired peaking facility. PNM ha<; not made its
final selection of these new resources and additional information important to resomce
selection will be obtained in future requests for proposals. Fu11hem1ore, the need for
replacement resources for which PNM would request approval m the future depends
tl.mdmnentally on whether the Commission approves PNM' s requested abandonment of
13
1
2
3
4
5
6 Q.
7
8 A.
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
SJGS Units 2 and 3 and CCNs for the inclusion of PVNGS Unit 3 as a jurisdictional
resource and additional capacity in SJGS Unit 4. PNM will request Commission
approval of the additional solar, gas-fired or other replacement resources in future
proceedings.
PLEA_~E COl\tlPARE THE COST OF EACH OF THE FOUR PORTFOLIOS
DESCRIBED ABOVE.
PNM Exhibit PJ0-3 provides a detailed comparison of the four pmtfolios I have
described above. In summary, the exhibit shows the net present value of revenue
requirements ("NPVRR") for each of the four portfolios. NPVRR is calculated by
discounting the annual revenue requirements for the cost of the new resource additions
and the system operation and maintenance costs for each portfolio over the 20-year
planning period using a discount rate equal to a weighted average cost of capital
("WACC") of 8.18%. The NPVRR methodology allows a comparison of the cost of
each portfolio on a comparable basis over the entire 20-year planning period, since the
revenue requirements of each pmtfolio will differ from year to year over the planning
period. The NPVRR of each of the four comparison portfolios is as follows:
1) Install SNCR on Units 1 and 4 and retire Units 2 and 3 consistent with the
Revised SIP and include PV3 in the portfolio for replacement capacity
(Revised SIP with PV Unit 3). This is the lea~t cost portfolio over the twenty year
planning horizon. The net present value over twenty years of the revenue
requirements associated with this pmtfolio is $780 million less than the portfolio in
which SCR is installed on all four SJGS tmits and the capacity in SJGS Unilo;; 2 and
14
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
DIRECT TESTIMONY OF PATRICK J, O'CONNELL
NMPRC CASE NO. 13-00 -UT
3 is retained. PNM Exhibit PJ0-4 provides a Load and Resomce Table illustration
of this portfolio.
2) Install SNCR on Units 1 and 4 and retire Units 2 and 3 consistent with the
Re\ised SIP and replace the capacity with gas-fired generation instead of PV
Unit 3 (Revised SIP with gas instead of PV Unit 3). The net present value over
twenty years of the revenue requirements associated with this portfolio is $56.8
million more than the NPVRR of Revised SIP with Palo Verde Unit 3 portfolio.
The higher cost is due to the need to rely more heavily on gas-fired generation when
PVNGS Unit 3 is not included in the portfolio.
3) Install SCR on all four generation units at SJGS consistent with the FIP. This
portfolio is the most expensive of the options and, as noted above, is $780 million
more expensive than the Revised SIP with Palo Verde Unit 3 portfolio. 'The higher
cost ret1ects the very near-tenn upfront capital cost of installing SCR at SJGS and
the ongoing cost of fuel and operation and maintenance expense for the SJGS
capacity that, under the Revised SIP portfolios, would be retired.
4) Retire all four unit-, at SJGS. This pmtfolio is $558 million more expensive over
twenty years than the Revised SIP with PV Unit 3 portfolio. In addition to replacing
the retired SJGS capacity with Palo Verde Unit 3 and renewables, this portfolio
requires the inclusion of a significantly greater amotmt of new natural gas generation
than the Revised SIP portfolio and, as I address below, is the riskiest of the four
portfolios due to volatile natural gas prices and a range of future cost'> associated
with anticipated environmental regulation.
15
Q.
2
3
4
5 A.
6
7
8
9
10
11
12
13
14
15 16
17
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
N.MPRC CASE NO. 13-00 -UT
PLEASE CO.MP ARE THE "RISKINESS" OF THE FOUR PORTFOLIOS IN
TERl'fS OF SENSITIVITY TO DEl\tlAND ~'ill E~'ERGY VARIATIONS,
NATURAL GAS PRICE INCREASES A1"1> THE COST OF A.~TICIPATED
ENvlRONWfENT AL REGlJLATION.
It is impmtant to quantify the potential risk of cost increases a~sociated with each
portfolio because it is impossible to know the future with certainty, so pmdent plmming
involves choosing a course of action that leads to acceptable results tmder a wide range
of circumstances. Table PJ0-2 shows the cost risk measure for each of the four
portfolios. The cost risk measure is a statistical measure of the range of potential cost
variation over twenty years. When comparing portfolios, a higher cost risk measure
means that the portfolio is more susceptible to futme cost increases due to natural gas
price volatility, anticipated environmental regulations, variations in system demand and
energy requirements and other variables.
I)
2)
3)
4)
TablePJ0-2 Portfolio Cost Summary
Portfolio
Revised SIP with PV Unit 3
Revised SIP without PV Unit 3
FIP
Retire SJGS
16
Risk Measure ($M)
$194
$247
$225
$349
1
2
3
4
5
6 Q.
7 A.
8
9
10
11
12
13
14
15
16
17
18 Q.
19
20 A.
21
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
Note that the Revised SIP portfolio that includes Palo Verde Unit 3 is the least risky.
The portfolio that includes the complete retirement of all SJGS w1its is the most risky,
with the risk mea•mre that is 80% higher than the risk mea-;ure for the Revised SIP
pmtfolio with Palo Verde Unit 3.
\VHAT DRIVES THE MAGNITlJDE OF THE RISK MEASURE?
TI1ree variables have the most impact on the risk measurement calculation: the demand
and energy forecast, natural gas prices and estimates of a future cost associated with
carbon dioxide emissions. 111e magnitude of the risk mem;ure is primarily driven by the
estimated arnow1t'i of natural gas burned and carbon dioxide emitted over twenty years
by each of the portfolios in the comparison. In addition, variations in the demand m1d
energy foreca'lt have a more pronounced effect on the volatility of the total costs in
portfolios with the greatest exposure to natural gas and carbon dioxide emission price
char1ges. The Revised SIP portfolio that includes Palo Verde Unit 3 is the lea'lt risky
because there are no carbon dioxide emissions from Palo Verde Unit 3 and its inclusion
in the portfolio reduces the need to rely on carbon-emitting natural gaq generation.
\VHY DID YOU INCLUDE FUTURE COSTS OF CARBON DIOXIDE
EMISSIONS TO CALCuLATE THE PORTFOLIO COST ESTIMATES?
The IRP Rule requires utilities to assume a cost associated with carbon dioxide
emissions for purposes of resource plmming. In Case No. 06-00448-UT. the
Cormnission adopted standardized prices for carbon emissions to use for these plarming
assumptions. The standard monetary values adopted in 2006 are now out of date,
17
2
3
4
5
6
7
8
9
10
11 Q.
12 A.
13
14
15
16
17
18
19
20
21
22
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
because greenhouse gas regulation has not yet resulted in an additional cost associated
with greenhouse ga'> emissions at electric generation stations, but the process that will
result in greenhouse gas emission regulations at new and existing electtic generation
stations is underway. It is simply not reasonable to assume that there will not be
additional costs associated with greenhouse gas emissions during the twenty-year
planning period. As I describe later in my testimony, Pl\i'M has addressed the need to
include future greenhouse gas emission costs in resource planning by hiling PACE
Global to provide a projection of such costs based on current policy assumptions and a
nationwide model of electricity generation.
HOW DID PNM CALCULATE THE RISK MEASURE?
PNM calculated the risk measure using an analytic technique called Monte Carlo
simulation. Monte Carlo silnulation uses randomly selected values from probability
distributions as lisk valiables to determine how a change in estimated values of the
vmiables affects the total cost estimate. Performing the Monte Carlo simulation consists
of the following steps:
• Step 1: Determine the potential range of values for il1put valiables (including
load forecast, natural gas fuel prices, market p1ices for electricity, and C02
costs). Then define a probability distribution for each variable, i.e. the
likelihood that each value in the range may occur.
• Step 2: Determine the conelation among input valiables if m1y, i.e. the change
in one variable directly related to a change in m1other variable.
18
2
3
4
5
6
7
8
9
10
II
12
13
14 Q.
15 A.
I6
17
I8
19
20
21
22
23
DIRECT TESTIMONY O:F PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -LT
• Step 3: Generate 900 sets of random input conditions, one value from each
probability distribution while reflecting any correlation among the variables, for
each year of the study period. Each set is referred to as a "draw.''
• Step 4: Calculate the resomce pmtfolio's total system cost for each of the 900
draws using Strategist® to optimize portfolio dispatch.
• Step 5: Aggregate the result-; of the random draws from Step 4 and calculate the
average cost and cost variability.
Using the result of step three, steps four and five were applied to each pmtfolio, using
the same randomly generated conditions. For my testimony, the average cost calculated
through this process is used to report the net present value of revenue requirements over
twenty years and the cost variability, a calculated statistic called the 95th percentile risk,
is reported as the risk measme.
\VHAT DOES THE 95m PERC"ENTILE RISK REPRESENT?
The 95th percentile risk measure reflects a five percent likelihood that a given portfolio's
actual costs will be greater than the risk value. For instance, the Revised SIP with PV
Unit 3 portfolio risk mea.;;ure is $194 million dollars. This measure reflects a five percent
likelihood that pottfolio actual costs will be greater than $6,834 million dollars (S6,640
million plus $194 million) over the next 20 years and a 95% likelihood that portfolio
costs will be less than $6,834 million dollars over the next 20 years. So a larger 95th
percentile risk value means a portfolio's NPVRR is more likely to exceed the average
NPVRR than would be the case with a lower 95th percentile risk value.
19
1 Q.
2
3
4 A.
5
6
7
8
9
10
11
12
13
14
15
16
17 Q.
18
19 A.
20
21
22
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
WHAT ASSlJ1VWfiONS REGARDING RESOURCE AVAILABILITIES M'D
COSTS DID PNM MAKE TO PRODUCE THE PORTFOLIO
CO~IPARISONS?
The resource availability and cost assumptions PNM used in this analysis are provided
in PNM Exhibit PJ0-5. These assumptions are the same a"isumptions PNM is using to
develop the 2014-2033 IRP. The data was gathered from the best somces available to
PNM. For example, cost<; for renewable generation are based on the bids PNM received
in response to the request for proposals issued in late 2012 to develop PNM's 2014
Renewable Procurement Plan. Natural gas generation costs are based on <m Electric
Power Research Institute ("EPRI") Technical Assessment Guide ("'EPRI TAG'') cost
databm;e that is reviewed and updated annually for the electric industry. An important
set of a<;sumptions for the analysis includes future natural gas and carbon dioxide prices.
PNM hired PACE Global to develop these prices using their models of the national,
intercom1ected natmal gas and electric systems. I have included the docw11entation of
PACE's work in PNM Exhibit PJ0-5.
\VHY DID YOU USE A T\VENTY -YEAR PERIOD TO CALCULATE THE
PORTFOLIO COST ESTIMATES?
The IRP Rule, at Section 7(1), defines the planning period to be used as a twenty-year
period. New Mexico and the Commission require the development of a long term
resource plan through an IRP process. Also, resource planning requires a long-tenn
view to ensure the development of the most cost-effective pmtfolio.
20
1 Q.
2
3
4
5 A.
6
7
8
9
10
11
12
13
14
15
16 Q.
17
18
19 A.
20
21
22
23
DIRECT TESTIMONY OF PATRICK .J. O'CONNELL
Nl\1PRC CASE NO. 13-00 -UT
PLEASE ELABORATE ON YOUR EARLIER STATEMENT THAT THE
INCLUSION OF PALO 'VERDE uNIT 3 RESULTS IN A COST EFFECTIVE
PORTFOLIO EVEN AT A PRICE SIGNIFICA,l~TLY ffiGHER THAi~ THE
$2,500/KW PROPOSED BY PNM.
PNM conducted a sensitivity analysis around the price of Palo Verde Unit 3 and fmmd
that the most cost effective Revised SIP portfolio includes Palo Verde Unit 3 up to a
price of $3,100/kW or $415.4 million. PNM has proposed including Palo Verde Unit 3
in rate ha'ie at a price of $2,500/kW or $335 million. To conduct the sensitivity analysis,
PNM included Palo Verde Unit 3 as a resource option in the Strategist modeling at a
range of prices. Only when the price for Palo Verde Unit 3 exceeds $3,100/kW, does
gas-fired capacity becomes a less expensive replacement for SJGS capacity than Palo
Verde Unit 3. So. while PNM ha<> detennined that $335 million is a fair price for
including Palo Verde Unit 3 in PNM's rate base, the value of Palo Verde Unit 3 to
PNM's customers exceeds this cost by $80.4 million.
HOW WILL THE J>ROPOSED RETIREMENT OF S.JGS tJr..1TS 2 AND 3 Al~D
THE OWNERSIDP EXCHAl~GE OF 78 M\V FROM UNIT 3 TO UNIT 4
M'FECT THE Al'VIOUNT OF CAPACITY THAT PNM OWNS AT S.JGS?
Table PJ0-3 provides the capacity currently held by PNM in each of the SJGS Lmits and
the capacity that would be held, a ... .;;suming Commission approval of PNM's requests in
this case, after the retirement of SJGS Units 2 and 3 and PNM's acquisition of an
additional 78 MW in Unit 4. The ownership transfer of 78 MW from Unit 3 to Unit 4 is
described by Mr. Olson.
21
1
2
3 Q.
4
5 A.
6
7
8
9
10
ll
12
13 Q.
14
15 A.
16
Unit 1
Unit2
Unit3
Unit4
Total
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
TablePJ0-3
Current ~1\Vs Change Result
170 0 170
170 -170 0
248 -248 0
195 +78 273
783 -340 443
DOES THE MOST COST-EFFECTIVE RESOlJRCE PORTFOLIO INCLUDE
THE 78 MW 0\VNERSHIP TRA.NSFER FROM SJGS UNIT 3 TO lJNIT 4?
Yes. This ownership transfer results in a more cost effective portfolio than would result
from a net retirement of more than 340 MW at SJGS. If the ownership transfer did not
occur and PNM's net retirement at SJGS were 418 MW, the most cost effective
pmtfolio would still be the Revised SIP portfolio with Palo Verde Unit 3, but the net
present value would increase by $79 million due to increased reliance on natural gas
generation, as referenced in PNM Exhibit PJ0-6. The risk measure would also increa.<;e
by $11 million.
DID PNM ASSUJME THAT A NATURAL GAS PEAKll~G PLANT IN THE
SJGS REPLACEIVIENT PORTFOLIOS \VOlJLD BE SITED AT SJGS?
Yes. All of the SJGS replacement portfolios include at least one heavy-frame gas
peaking plant as part of the most cost effective mix of replacement capacity. PNM
22
1
2
3
4
5
6
7
8
9
10
11
12
13 14 Q.
15 A.
16
17
18
19
20
21
22
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
assumed that the first such gas peaking plant in each portfolio would be sited at SJGS
due to the pe1mitting and economic advantages of using that site. PNM currently owns
sufficient land at the station to build and operate a natural gas peaking facility. Locating
the peaking facility at SJGS will significantly reduce the need to build transmission
interconnection facilities for the ne\v ga.;; plant because the gas plant will be able to use
existing trammission facilities that are currently serving SJGS Units 2 and 3. Siting new
generation at <m existing generation facility also simplifies permitting the new facility
since there is no change in land use associated with the new constmction. An estimate
of $10 million to pay for construction of a new gas supply line from existing, nearby ga'i
trnnsmission lines to SJGS is included in the plant constmction costs for the gas facility.
IV. RELATIONSHIP TO 2014-2033 IRP
HOW IS PNlVI COORDINATL"iG TIDS FILL"iG \VITH PNM'S 2014-2033 IRP?
PNM's 20141RP is scheduled to be filed with the Commission by July 2014. Consistent
with the IRP Rule, the lRP will present an analysis of portfolio alternatives over the next
twenty-year period, identify the most cost-effective portfolio, and include a four-year
Action Plan. I anticipate that the key near-term elements of that Action Plan will
include:
• Pursue abandonment of SJGS Units 2 <md 3 by the end of 2017;
• Pursue approval for a CCN for 78 MW of capacity in SJGS Unit 4 by J mmary 1,
2015;
23
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19 Q.
20
21
22 A.
23
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
• Pursue approval for a CCN to include PVNGS Unit 3 as a jurisdictional
generating resmrrce;
• Identify new natmal gas resources required to replace capacity being retired at
SJGS and file a CCN to have such resources in place by early 20 18; and
• Identify 40 MW of new solar resomces to be comtructed as replacement
generating capacity for the retired SJGS capacity and seek NMPRC approval to
constmct and operate such facilities by 2016.
Consistent with the IRP Rule, PNM began the IRP Public Advisory Process in July
2013. A number of meetings with the public and the Public Advisory Group have been
conducted. TI1e analysis presented in my testimony has been discussed in the public
advisory process. PNM anticipates that during the next few months, through the IRP
process, the remaining resomces necessary for replacement of the retired generation
capacity in SJGS Units 2 and 3 \Vill be specifically identified and addressed in the fom
year Action Plan, and an over-all, long-term resource plan for meeting forecasted
customer loads over the next twenty years will be described. Of course, this longer-tem1
plan will again be revisited by PNM in its next (2017) IRP process.
FROl\1 AN IRP PERSPECTIVE, 'WHY SHOID.D THE ~'MPRC APPROVE
PNl\l'S REQUEST FOR A CCN TO TRAI\JSJi"'ER 78 J\IW OF CAPACITY
FROM SJGS UNIT 3 TO SJGS UNIT 4?
All pmtfolios that include the additional capacity in SJGS Unit 4 are lower in cost and
less risky than portfolios that do not. Including an additional 78 MW of capacity in Unit
24
2
3 Q.
4
5
6 A.
7
8
9
10
ll
12
13
14
15
16
17
18 Q.
19 A.
20
21
22
23
DIRECT TESTil\tONY OF PATRICK .J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
4 is cost-etlective. It is an existing resource and is not subject to siting and constmction
uncertainties as may exist for new resomces.
FROM At'J IRP PERSPECTIVE, WHY SHOlJLD THE Nl\IPRC APPROVE
PNM'S REQUEST "FOR A CCN TO L~CLUDE PVNGS l!N1T 3 A.'i A
.JURISDICTIONAL RESOURCE?
Next to the addition of 78 MW of SJGS Unit 4 capacity in the resource portfolio,
PVNGS Unit 3 is the most cost-effective resource option for replacement of the
abandoned base-load capacity in SJGS Units 2 and 3. All portfolios that include
PVNGS Unit 3 are lower in cost and less risky than portfolios that do not. All such
portfolios showed lower levels of C02 emissions and cost risks than portfolios that did
not include PVNGS Unit 3. It is an existing resource and PNM controls sufficient
transmission capacity to bring the generation to the Four Comers area and into PNM's
load centers. Granting PNM's application for a CCN for PVNGS Unit 3 reduces the
amount of new generation capacity that PNM must obtain and results in significant
savings to customers over the twenty-yem· planning period.
V. CONCLUSIONS
DO YOU HAVE AlW CONCLl.HliNG OBSERVATIONS?
Y cs. Complying with the requirements of the Regional Haze Rule by retiring Unit'> 2
and 3 at SJGS and, installing SNCR on Units 1 and 4, pursuant to the Revised SIP, and
replacing the retired capacity with Palo Verde Unit 3, 40 MW of solar generation, a
natural ga.'> peaking facility located at SJGS m1d an additional 78 MW of capacity in
SJGS Unit 4 is in PNM's customers' best interests because it is the most cost-effective
25
DIRECT TESTIMONY OF PATRICK J. O'CONNELL
NMPRC CASE NO. 13-00 -UT
1 approach available to PNM and provides significant enviromnental benefits.
2 Accordingly, the N:MPRC should approve PNM's Application in this case.
3
4 Q. DOES TillS CONCLUDE YOL'R DIRECT TESTiwiONY?
5 A. Yes.
GCG# 517366
26
PNM EXHIBIT PJ0-1
Consisting of 1 page
PNM EXHIBIT PJ0-1 Page 1 of 1
PATRICK J. O'CONNELL: EDUCATIONAL AND PROFESSIONAL SUMl\1ARY
Name: Patrick J. O'Connell, PE
Address: Public Service Company of New Mexico Main Offices Albuquerque, New Mexico 87158-1105
Position: Director, Planning and Resources
Education: B.S., Civil Engineering, with distinction and magna cum laude in General Honors University of New Mexico, Albuquerque, New Mexico 1990
Employment: Public Service Company of New Mexico, Albuquerque, New Mexico: Director, Planning and Resources, July 2012 - present Project Manager, PNM Generation, 2009- 2012 Project Manager, Integrated Resource Planning, 2007 - 2009 Senior Gas Supply Planner, PNM Gas Services, 1999 - 2007
Public Service Company of New Mexico, Santa Fe, New Mexico Project Engineer, PNM \Vater Services, 1996- 1999
URS Greiner, Albuquerque, New Mexico: Design Engineer, 1994 - 1996
GMA Inc., Albuquerque, New Mexico: Staff Engineer, 1993-1993
Licensure: New Mexico Professional Engineer, License No. 12876
Testimony: New Mexico Environmental Improvement Board, Case No. EIB 10-04(R): In the Matter of Proposed Regulation, 20.2.350 NMAC- Greenhouse Gas Cap and Trade Provisions
New Mexico Public Regulation Commission Case No. 12-00317-UT: PNM's 2013 Energy Efficiency Plan Case No. 13-00004-UT: PNM's Delta Plant CCN Application Case No. 13-00175-UT: PNM's La Luz Energy Center CCN Application Case No. 13-00183-UT: PNM Renewable Energy Plan for 2014
PNM EXHIBIT PJ0-2
Consisting of 1 page
PNM Exhibit PJ0-2
PUBLIC SERVICE COMPANY OF NEW MEXICO Current Load and Resource Projections for Summer Peak- 201.4/RP
Not".L • PNM ass...,rnes a C<.iP<K.Ity credtt fm n.~new.lb!~ <thr.:ult.es ba:;ed on type of technology and contribution at the peak hour * Dt.'rrilr~d i{e-;ptJmf:' & ~;i~Jr R~:"sources grosst>o up tor ·r cansmiS:>!On losses .. PNM d:i5l.imc:, a 100'1,,. (dp~Clty uedit for P:mpent'{ Battery ~mo • Ci.l'~i¥.•t''y' C£>ti!t tor geotherrna! resm;rce '5 ba.:.ed ,;pon developer estimates • ~uture r;:~our:;e~ are wrrent!y b('tr~g ~ele-Ci.<:>d thr-;:.h;th RFP's for renewabies, natural ga~, and lo<ld management, consJstent With the act1on p!.ar. 1n ?N\.~\ ~C L 1 1 ~P, tJit<d lviy lS, :c:1: t'NM ,:Dilt1nuaHy evaluates its need for resources as. circumsunce.s change,
PNM EXHIBIT PJ0-3
Consisting of 1 page
Ltne
[1]
[2]
13) [4]
[5]
[6]
[7]
[8]
19]
1101 [11]
[12]
]13]
[14]
{15]
{16]
117]
118]
119]
[20)
121]
[22]
[23]
[24]
125] [26)
In] [28j
[29]
(.lO]
[ ll)
(32)
[33)
[34
135)
[36)
(37)
[38]
[39]
(40]
(41]
[42]
[43
[44]
Summary of Regional Haze Compliant Portfolios
Scenario Description Revised SIP with PV3 Gas Pflcing PACE Reference Case C02 Pncrng PACE Reference Case ($11 in 2020) Energy f.ffrnency furecdst 2014 IRP Forecast PV DG forecast 2014 IRP Forecast Demand Response Fort?Cdst _ 2014 IRP Forecast Resource Alt<?rndtrve Dot abase EPRI TAG/PNM Estimates Renewable Procurements 2014 REPP + Projections Palo Verrie 3 Available $2,500/kW -NOx Control at San Juan SNCR's on 1 & 4 San Juan O&M Harvest Savings Units 2 & 3 San Juan Stranded Asset Costs $20,764,674 SJ Retirements Units 2 & 3 (Dec 2017) 2014
I Revised SIP w/o PV3 FIP ("4 SCR") FIP ("4-Unit Shutdown at SJ") i
PACE Reference Case PACE Reference Case PACE Reference Case PACE Reference Case ($11 in 2020) PACE Reference Case ($11 in 2020) PACE Reference Case ($11m 2020) I
Pace Global's Marketlink scenarios are a set of four internally-consistent states of the world developed against a backdrop of changing policy frameworks over time
'It The prevalence of certain geopolitical, environmental, and macroeconomic conditions can lead policy makers to focus near-term on one of several competing aspects of energy policy:
--- Costs
Environmental Protection
~- Energy Security
Safety
'It As the geopolitical, environmental, and economic conditions change, energy policy is likely to shift away from the predominant near-term focus into other competing objectives
--· Market and regulatory response feedbacks over time
Each scenario is developed by carefully evaluating the relationships and correlations between energy policy and the fundamentals of fuel and power markets
The scenarios are intended to push the envelope of potential outcomes; in other words, they are plausible, but low probability
Page 3 BPS I Pace Global
Focus on low cost energy; weak environmental regulation; few coal retirements; few renewables
Strong environmental policy results in high C02
price, many coal retirements, and significant renewable expansion; power sector demand and fracking ban results in high gas pnces
Page4
Near term shock to oil and gas prices results in push for diverse domestic supply; opposition to exports, low gas prices longer term
Nuclear phase out with continued pressure on coal capacity; flat demand growth; pressure on gas pnces
BPS I Pace Global
• Pace Global and PNM identified natural gas price and carbon price as the two major drivers of portfolio performance
• The "Clean" and "Cheap" Marketlink themes drive gas and carbon prices in opposite directions, based on the underlying economic and regulatory drivers. These themes were used to define the selection of scenarios for use in the analysis.
• Three scenarios were deployed:
·.~~~~;i~s:;0,~"tf~'i;t~v l~.eferenoe,
'~-~~:,< \"
Page 5 BPS I Pace Global
Conditions
Environmental Regulations
Natural Gas Prices (HH and Permian)
Gas Market Factors
C02 Prices
PRB Coal Price
National Coal Retirements
Regional Power Sector Load Growth
Power Sector Expansion
Page6
};>MATS remains on track for 2016 implementation
?NYMEX Forwards to 2015
>Modest growth in Permian gas production, declining San Juan production
>No C02 regime
YPRB 880010.80 in the range of $12-14/ton plus transport
>Announced (up to 25 GW)
};>Base load growth (1.5%)
J;>Continued replacement of coal fired generation with gas. Moderate expansion of solar and wind
Mid Term 2016-2025
J;>Possibility of additional regulations, e.g. revised CSAPR
J;>Gas prices move towards range of $5-6/MMBtu
>Growth, then plateau, of Gulf Coast LNG and Mexican pipeline exports
};>Modest C02 regime starts in 2020 ( -$1 0/tonne)
Y PRB 880010.80 in the range of $15/ton plus transport
I t.!._ I I I I I t.!._ I I I I I t.!._ I I I I c: ro >- ::;, a... > c: ro >- ::;, a... > c: ro >- ::;, a... > ro~ ro--, a.> oro~ ro--, a.> oro~ ro--, a.> o --, ~ wz--, ~ wz--, ~ wz
--- Reference Low Gas & Carbon Scenario High Gas & Carbon Scenario
*Note that the San Onofre Nuclear Generation Station (SONGS) in California is retired across all cases
Page 22
-------f-----~~----
X
BPS I Pace Global
*Note that Navajo and Intermountain are additional plants for retirement beyond the Reference Case. *Note that the San Onofre Nuclear Generation Station (SONGS) in California is retired across all cases.
Page 23 l\U reserved. BPS I Pace Global
PNM EXHIBIT PJ0-6
Consisting of 1 page
PNM Exhibit P.J0-6
SJGS Unit 4 Additional Capacity Portfolio Comparison
Scenario Description Revised SIP with PV3 Revised SIP with PV3 no 78 MW to SJ4
line ~~~-------------------f--------~~~~----~----------1---------~~~~--~-----------1 [11 Gas Pricing PACE Reference Case PACE Reference Case
[9] NOx Control at San Juan SNCR's on 1 & 4 SNCR's on 1 & 4
(10 } San Jwan O&M Harvest Savings Units 2 & 3 Units 2 & 3
(11 } San Juan Investment Recovery $16,401,523 $20,601,519
(12 I SJ Retirements Units 2 & 3 (Dec 2017) Umts 2 & 3 (Dec 2017)
[13 I 2014 (14 i 2015 Red Mesa {102 MW) Red Mesa (102 MW)
[15 I [16 I 2016
2015 Solar {23 MW) 2015 Solar (23 MW) b::-:-::-------------t------A:--e.:.r:cod'Ce""ri"'va"'t'-iv"'e:C(4:-'0~M:C.:W'-:c.)---------~-----;A-"er"'o":d'-er'-'iv"'a0:tlv-"e0:.:(C'40-:7M':LW:-c):-----l
[17 I Solar (40 MW) Solar (40 MW)
[18 I 2017 [19 I 2018
----+-----·-:----:=-::::-:-c-:c:--------- ·-----------------Large GT (177 MW) Large GT (177 MW)
[32 I 2027 2nd Aeroderivative {40 MW) Large GT (143 MW)
[33 J 2028 [34 I 2029 Aeroderivative (40 MW)
[35 J 2030 [36 1 2031 Small GT (85 MW)
[37 I 2032 [38 i 2033 =::-------------!-------------- -----~---,A;-e-rod-;-e--,-nv::-:at--,-ive:-;(-:-:;40:-:-M:::Wcc-)----
[39]
20-Year lOLH
1401 Average NPV
(41} Difference to Revised SIP with PV3
Average NPV [41)
95th Percentile Risk
51.20 37.74
$6,640,253,862 $6,719,185,750
$78,931,888
$194,357,382 $205 615,262
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION
IN THE MATTER OF THE APPLICATION l OF PUBLIC SERVICE COMPANY OF NEW ) MEXICO FOR APPROVAL TO ABANDON ) SAN JUAN GENERATING STATION UNITS ) 2 AND 3, ISSUANCE OF CERTU'ICATES ) OF PUBLIC CONVENIENCE AND ) NECESSITY FOR REPLACEMENT POWER ) RESOURCES, ISSUANCE OF ACCOUNTING ) ORDERS AND DETERMINATION OF ) RELATED RA TEMAKING PRINCIPLES AND) TREATMENT, )
PUBLIC SERVICE COMPANY OF NEW MEXICO,
Applicant
) ) ) ) )
AFFIDAVIT
STATE OF NEW MEXICO ) ) ss
COUNTY OF BERNALILLO )
Case No. 13-00 ___ -UT
PATRICK J. O'CONNELL, Director, Planning and Resources, Public Service
Company of New Mexico, upon being duly sworn according to law, under oath, deposes and
states: I have read the foregoing Direct Testimony and Exhibits of Patrick J. O'Connell and it
is true and accurate based on my own personal knowledge and belief.
SIGNED this 17th day of December, 2013.
(---"-,
\[il;'Lt'f __ -f' ?. {(1\vt.~(( ____ _ PATRICK J. O'CONNELL
SUBSCRIBED AND SWORN to before me this 1 ih day of December, 2013.