Underground System Design TADP 547 Operation & Maintenance Practice Presentation 6.3 Instructor: Frank Frentzas
Underground System Design
TADP 547
Operation & Maintenance
Practice
Presentation 6.3
Instructor: Frank Frentzas
Operation & Maintenance Practice
With proper operation and maintenance procedures under-
ground cable systems will provide long term and trouble free
service when properly maintained.
Without proper maintenance cables can still operate well for
many years. However, when problems or failures occur the
repair costs will likely to be high with repair durations running
from days to months.
The reliability of any underground cable system is a direct
function of the operation and maintenance programs being
performed.
Utilities generally develop maintenance procedures specific to
their system operation and workload.
Operation & Maintenance Practice (cont.)
System operators should have procedures available that cover
operational requirements of underground cable systems.
Operators should be aware of the key factors that can effect
cable operation and cable life.
– Thermal loading/ampacity
– Pressure requirements
– Circuit reclosure schemes
Key Factors
Thermal loading:
System operators should be aware of and follow both normal and
emergency conductor temperatures - based on ampacity rating.
Pressure requirements:
Pressures are critical for cable operation. Cables should be operated
within the specified cable pressure range to avoid break-down/failure
of the insulation. Cables operating outside the normal pressure range
should be de-energized.
Circuit Reclose Scheme:
When underground cable circuits trip on a fault a reclose operation
should be prevented - since you will likely be closing back into the
fault. When overhead lines are a part of the cable circuit, a reclose
should only be allowed when the distance relay indicates the fault
was on the overhead line portion.
Standard Practice Practice
It is vitally important that maintenance procedures incorporate
both safe work practices and environmental requirements and
regulations.
Since no two maintenance programs are alike, we will cover
general maintenance procedures for HPFF, HPGF, LPFF and
XLPE cable systems.
We will start by covering maintenance procedures for Pipe
Type cable systems.
HPFF & HPGF Procedures
A life expectancy of fifty plus years is not unusual
for Pipe Type cable systems. With such longevity
replacement parts from original manufacturers can
be problematic or non-existent. The resulting
difficulties for regular system repairs provide a
powerful incentive for ensuring effective preventive
maintenance programs are in place.
Line Route Patrols
Focused inspections to verify no unauthorized
excavation or construction has taken place along
the cable route.
Prevent third party damage to pipe coating which
may lead to future pipe leaks.
Verify no ground shifting, sinking or wash-outs
have taken place along cable route.
Frequency of patrols is typically weekly.
Manhole Inspections
Underground manhole inspections verify the
condition of the HV cable systems they
contained.
Interior visual inspection of structural integrity
of manhole interior walls, floors, and ceilings.
Verification that pipe coating shows is not
damaged and there is no evidence of coating
disbanding from the pipe surface.
Verification that all connections are properly
coated and no signs of corrosion are present.
Manhole Inspections (cont.)
Verifies there are no dielectric fluid leaks from
the joints, piping, or valves.
Grounding conductors are securely connected.
All cathodic connections properly connected
and insulated, and bond leads are not in contact
with any structures that would compromise the
cathodic protection system.
Frequency of inspections can vary from 2 - 5
years.
Termination Inspections
Verify there are no dielectric fluid leaks from
terminations, piping, or valves.
Grounding conductors are securely connected to
the structure.
All cathodic connections are properly connected.
Check and re-torque base and top plate bolts.
Insulator checked for cracked or damage sheds,
and for contamination.
Frequency of inspections can vary from 1 - 5 years.
Fluid Samples
Fluid samples can provide baseline condition of the
line, and are periodically checked every 1 to 5 years
for changes in gas levels.
Fluid samples drawn from joints and terminations to
examine the condition of the cable insulation.
Dielectric fluid samples are taken from the bottom
of the joint and termination using a glass jar. The
test checks for moisture, dielectric strength, power
factor, and color.
Dissolved Gas Analysis (DGA)
Dissolved Gas Analysis (DGA) used to determine the
paper insulation condition. The technology was
extensively used on power transformers and adopted by
the cable industry.
DGA samples are taken using a glass syringe with a small
end tube to draw fluid from the top of joints and
terminations.
All samples must be sealed and protected from moisture
and heat until they reach the laboratory for analysis.
Samples are analyzed for several gasses using a gas
chromatograph to measure the concentration of each gas.
Dissolved Gas Analysis (DGA)
The concentration of each gas gives an indication of the
insulation condition.
High concentration of Acetylene indicates arcing is taking
place and that the joint or termination should be inspected as
soon as possible.
High levels of Carbon Monoxide and Dioxide indicate
decomposition of cellulose components (impregnated paper),
possibly due to overheating.
IEEE 1406 specifies acceptable and concern levels for gas
and moisture content.
Pressurization Plants
Pressurization plants maintain line pressure and
are essential to cable system reliability.
Pumping plants are typically inspected once a
month, and more frequently for older plants with
weekly chart recorders which require the chart to
be changed.
Unit should be visually inspected for fluid leaks and
damage to any mechanical components.
The annunciator alarm panel should be checked for
proper operation.
Pressurization Plants (cont.)
Pressure gauges, switches, timers, and regulating
valves should be checked and calibrated annually
for proper operation.
If the HPFF circuit is equipped with a forced cooling
unit it should be checked and calibrated once a
year.
Nitrogen cabinets on HPGF system should be
checked annually for proper calibration and proper
alarm operation.
Corrosion Inspection
Most pipe systems fail from the outside, meaning
the pipe fails before the cable system. A corrosion
protection system should therefore be inspected
annually for proper operation.
Pipe coating defects, also refer to as holidays,
should be identified and repaired to avoid corrosion
leaks. Pipe defects are identified by performing a
coating resistance test and an above ground
survey.
The frequency of these tests is anywhere from 3 - 10
years, depending on the pipe history and location.
Low Pressure Fluid Filled Systems
Low Pressure Fluid Filled systems are similar to pipe type
systems in frequency and procedures for line patrols, manhole
inspections, and fluid samples.
Manhole inspections involve an inspection of cable supports
and link boxes used for sheath bonding system, and the fluid
reservoir for proper level and pressure.
Pressure alarms must be inspected and tested every (1 to 3
years) for proper operation
A cable sheath test must be performed every 3 - 5 years to
verify the cable jacket integrity.
In some cases, sheath current readings are also measured
every 3 - 5 years.
XLPE Cable Systems
XLPE systems require less maintenance than other
cable systems since no hydraulic pressure equip-
ment is used.
However, XLPE systems require the same main-
tenance as other cable systems when it comes to
line route patrols, manhole inspections, sheath
tests, and sheath current measurements.
Line inspections can prevent contractors from
digging into the cable or damaging the jacket/
sheath, which can lead to localized hot spots and a
cable failure.
XLPE Cable Systems (cont.)
Manhole inspections are similar to other cable systems in that
they verify structure condition and, most importantly, inspect
the cable system.
Check racking system for any movement, and the grounding
and bonding system.
Manhole inspections typically performed on a 3 - 5 year
frequency.
Sheath tests should be performed every 3 - 5 year to identify
jacket or sheath damage, and the condition of bonding
connections - including link boxes and surge arrestors.
XLPE Cable Systems (cont.)
Sheath currents can be measured on a 3 - 5 year
cycle to verify the bonding system is operating as
designed.
In some cases, real-time optical fibers embedded
temperature measurements can be taken to provide
actual cable operating temperatures.
On-line partial discharge (PD) tests are now being
performed to detect cable and accessories defects.
Most utilities perform a PD test during the initial
installation and just prior to warranty expiration.
Typical Manhole Inspection Form
Actual Sheath Test Form: Note Damage on C Phase
Summary
Providing cable systems are operated per design
and a comprehensive maintenance program is
performed the systems will operate trouble free
for many years.