TW@ESI 4 th December 2016 Hope all of you had a good weekend The following is a record of what was done during the past week and a forecast of the next week.....
TW@ESI4th December 2016
Hope all of you had a good weekend
The following is a record of what was done during the past week and a forecast of the next week.....
A General Note before we start-•Our Christmas party has been planned for Monday 12th December 2016- evening – please pencil this date and keep it free•Tomorrow Monday 5th December will be the date all who are joining the fun of Secret Santa will open our presents •For new employees Jerico, Kristiyan and Stoyan- can CVA/SSA/JGA ask them to join LinkedIn, ask to connect with me and I will include them in our group- speaking of new members in our Linkedin•We have got confirmation from Siemens that we have been certified for all modules (NET, S7, WinCC) for which Silvio attended a workshop for re certification lately- Well done Silvio! •We have a new employee starting with the MDH team tomorrow 5/12- Donaghan Zerafa- he will be replacing Simon Florian as a Day technician•Last week myself and John travelled to Qatar finding further opportunities in this region – there is a lot of work there and we feel that step by step we may have opportunities there
Projects and deadlines• 16_007_LeMeridien_BMS_upgrade- We have started working on phase
1 panels – phase 1 which has to be completed by Feb 2017- next steps are– We need to order the JACES and Field devices – Prepare the Software for the phase one panels- we need to form a plan here
as we are falling back!!– Once materials are here, design sketches are available and software is
available we will do change over.• 12_043_Life Sciences – we need to call for an inspection of snags to
close everything down- we need to complete the tenant building module- this is now a very urgent and hot project
• 13_075_Bosch_ProWatch_Genetec_Interface - The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
• 12_027- Parliament –We have done progress in closing off and we now need to finalise the documentation and finally integrate ProWatch
Projects and deadlines• 14_069- Q019 AS410 – Material from Siemens has been received, RFIs
are started to be answered by the client• 14_069- Q021_TF4- panel build, panel installation, Patch panel
installation, FOC termination and testing• 12_025- The last issues on the DAC for SCM PH2- IT IS NOW A
PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
• 14_081_Siggiewi School- there are some snags pending here which have to be seen to.
• 16_025_DeLaRue_OFX- We have kicked off and now need to start working on typical design (whihc should be completed before our shut down) - training by overseas specialists will be on 16/1/17
• 13_031_CCA- still issues with values on ILPS and we also have to execute some new works at CCA (new cameras, pagers)
Projects and deadlines• 15_011- Sliema apartments – We have done some terminations and will shortly start
the panel build• 16_023_GGY- we have some snags pending as well as the integration to the Acs- we
also have to transfer the old GGY system to the new platform• 14_083_Intercontinental – We have commissioned the system with snags - we will
return to site when snags are done by others• 16_015_RSM- this lighting control project is to be completed in December 2016 we
need to really keep a good eye on what is happening on site by the main contractor- we must ensure the wiring and terminations are done properly- as soon as the main contractor collects the field devices we must ensure he tests the DALI loops and then we can commission and program
• 15_038_new_HA_Ovt and 15_026_Apap Residence are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation
• 13_070- SCM Lagoona Plant room We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue
Projects and deadlines• 16_041_RSM_Zebbug_Security- CCI and SAI will
be going through the scope during week of 18th Nov so as to allow me to start ordering- A kick off will be held during week of 5th Dec
• 16_051_Baxter_AHU_Controls- An extremely fast track project which was started off last week (Commissioning date is in the week after Christmas) – next steps are– Panel design and construction– Programming of Control description– Carry out installation and commission the system
DesignLast week• FM Environmental As built feedback• Mosta Workshop Plan drawing for Enemalta application• Sliema Graham Apartments – Addition of new PIR leg at Penthouse
terrace• Baxter AHU: released Panel design for panel building• Meridien – completed Phase 1 Panel sketches, released to CVA & CCi to
check, before DSH implementation on siteNext Week:• Small updates on FM Environmental As built feedback• RSM Panels As Built feedback from CCi• Various updates from CCi, SAi, etc• Start-up of De la Rue sketching• Julian will be on leave from 6th Dec – he will be back on 15th Dec –
Happy Holidays
InstallationThis past week: • Lifesciences installed batteries on Jaces and checked some water
meters• Aurobindo Insulated chiller TT sensors• Baxter: Passed power cable and some BMS cables• OTM panel modifications labelling and updates of panel drawings• Continued with works on Mosta workshopNext week:• OTM panel modifications labelling and updates of panel drawings• Install new cameras and network switch at CCA villa• Install PIR’s at Graham• Continue with works at Mosta workshop
Panel Build
Well done to the efforts done to catch up – we are still in slight delay
• Project 14_069 - OTM Additions panel is complete – Hallelujah! Testing will be in the next week
• Project 15_023 - FM Env Control Panels is done too!• Project 16_015 - RSM DALI panels are completed too • Project 16_051 – Baxter AHU This has bee started and will be
completed by the 9th Dec• Project 15_011 - Graham Sliema Apts Blk Is next in line
Mater DeiWeek 48
Yearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1
Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1,
D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1
Weekly update of antivirus on all BMS stations
ReactiveHandling of reactive work orders
Others• Participating in weekly fire drills• Tackling software work orders • New Angiography Project• Training of new team member• Integration of Samoc into Master
Sales and Business DevelopmentWe are working on quotes for a catering
establishment, small AHU control system for Methode, S5 PLC upgrade for Kordin Grain terminals lighting control systems in Qatar and trying to secure a large BMS project in malta.
Birthday wishes go to
Sridhar Venkatesh December 6Brian Farrugia December 8
Team ESI• I urge you all to follow this blog and keep up to date with
what is happening at ESI • I await all your feedback on all the ESI discussions –
without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group
• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
Team ESI
• Lets all work to get the work done on time, on budget and to the required quality
• We need to communicate, pull the rope in the same direction to make our projects a success and profitable