Top Banner
TW@ESI 4 th December 2016 Hope all of you had a good weekend The following is a record of what was done during the past week and a forecast of the next week.....
14

TW@ESI update 4th December 2016

Feb 15, 2017

Download

Business

Simón Abela
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TW@ESI update 4th December 2016

TW@ESI4th December 2016

Hope all of you had a good weekend

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI update 4th December 2016

A General Note before we start-•Our Christmas party has been planned for Monday 12th December 2016- evening – please pencil this date and keep it free•Tomorrow Monday 5th December will be the date all who are joining the fun of Secret Santa will open our presents •For new employees Jerico, Kristiyan and Stoyan- can CVA/SSA/JGA ask them to join LinkedIn, ask to connect with me and I will include them in our group- speaking of new members in our Linkedin•We have got confirmation from Siemens that we have been certified for all modules (NET, S7, WinCC) for which Silvio attended a workshop for re certification lately- Well done Silvio! •We have a new employee starting with the MDH team tomorrow 5/12- Donaghan Zerafa- he will be replacing Simon Florian as a Day technician•Last week myself and John travelled to Qatar finding further opportunities in this region – there is a lot of work there and we feel that step by step we may have opportunities there

Page 3: TW@ESI update 4th December 2016

Projects and deadlines• 16_007_LeMeridien_BMS_upgrade- We have started working on phase

1 panels – phase 1 which has to be completed by Feb 2017- next steps are– We need to order the JACES and Field devices – Prepare the Software for the phase one panels- we need to form a plan here

as we are falling back!!– Once materials are here, design sketches are available and software is

available we will do change over.• 12_043_Life Sciences – we need to call for an inspection of snags to

close everything down- we need to complete the tenant building module- this is now a very urgent and hot project

• 13_075_Bosch_ProWatch_Genetec_Interface - The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

• 12_027- Parliament –We have done progress in closing off and we now need to finalise the documentation and finally integrate ProWatch

Page 4: TW@ESI update 4th December 2016

Projects and deadlines• 14_069- Q019 AS410 – Material from Siemens has been received, RFIs

are started to be answered by the client• 14_069- Q021_TF4- panel build, panel installation, Patch panel

installation, FOC termination and testing• 12_025- The last issues on the DAC for SCM PH2- IT IS NOW A

PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• 14_081_Siggiewi School- there are some snags pending here which have to be seen to.

• 16_025_DeLaRue_OFX- We have kicked off and now need to start working on typical design (whihc should be completed before our shut down) - training by overseas specialists will be on 16/1/17

• 13_031_CCA- still issues with values on ILPS and we also have to execute some new works at CCA (new cameras, pagers)

Page 5: TW@ESI update 4th December 2016

Projects and deadlines• 15_011- Sliema apartments – We have done some terminations and will shortly start

the panel build• 16_023_GGY- we have some snags pending as well as the integration to the Acs- we

also have to transfer the old GGY system to the new platform• 14_083_Intercontinental – We have commissioned the system with snags - we will

return to site when snags are done by others• 16_015_RSM- this lighting control project is to be completed in December 2016 we

need to really keep a good eye on what is happening on site by the main contractor- we must ensure the wiring and terminations are done properly- as soon as the main contractor collects the field devices we must ensure he tests the DALI loops and then we can commission and program

• 15_038_new_HA_Ovt and 15_026_Apap Residence are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation

• 13_070- SCM Lagoona Plant room We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

Page 6: TW@ESI update 4th December 2016

Projects and deadlines• 16_041_RSM_Zebbug_Security- CCI and SAI will

be going through the scope during week of 18th Nov so as to allow me to start ordering- A kick off will be held during week of 5th Dec

• 16_051_Baxter_AHU_Controls- An extremely fast track project which was started off last week (Commissioning date is in the week after Christmas) – next steps are– Panel design and construction– Programming of Control description– Carry out installation and commission the system

Page 7: TW@ESI update 4th December 2016

DesignLast week• FM Environmental As built feedback• Mosta Workshop Plan drawing for Enemalta application• Sliema Graham Apartments – Addition of new PIR leg at Penthouse

terrace• Baxter AHU: released Panel design for panel building• Meridien – completed Phase 1 Panel sketches, released to CVA & CCi to

check, before DSH implementation on siteNext Week:• Small updates on FM Environmental As built feedback• RSM Panels As Built feedback from CCi• Various updates from CCi, SAi, etc• Start-up of De la Rue sketching• Julian will be on leave from 6th Dec – he will be back on 15th Dec –

Happy Holidays

Page 8: TW@ESI update 4th December 2016

InstallationThis past week: • Lifesciences installed batteries on Jaces and checked some water

meters• Aurobindo Insulated chiller TT sensors• Baxter: Passed power cable and some BMS cables• OTM panel modifications labelling and updates of panel drawings• Continued with works on Mosta workshopNext week:• OTM panel modifications labelling and updates of panel drawings• Install new cameras and network switch at CCA villa• Install PIR’s at Graham• Continue with works at Mosta workshop

Page 9: TW@ESI update 4th December 2016

Panel Build

Well done to the efforts done to catch up – we are still in slight delay

• Project 14_069 - OTM Additions panel is complete – Hallelujah! Testing will be in the next week

• Project 15_023 - FM Env Control Panels is done too!• Project 16_015 - RSM DALI panels are completed too • Project 16_051 – Baxter AHU This has bee started and will be

completed by the 9th Dec• Project 15_011 - Graham Sliema Apts Blk Is next in line

Page 10: TW@ESI update 4th December 2016

Mater DeiWeek 48

Yearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1

Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1,

D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1

Weekly update of antivirus on all BMS stations

ReactiveHandling of reactive work orders

Others• Participating in weekly fire drills• Tackling software work orders • New Angiography Project• Training of new team member• Integration of Samoc into Master

Page 11: TW@ESI update 4th December 2016

Sales and Business DevelopmentWe are working on quotes for a catering

establishment, small AHU control system for Methode, S5 PLC upgrade for Kordin Grain terminals lighting control systems in Qatar and trying to secure a large BMS project in malta.

Page 12: TW@ESI update 4th December 2016

Birthday wishes go to

Sridhar Venkatesh December 6Brian Farrugia December 8

Page 13: TW@ESI update 4th December 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 14: TW@ESI update 4th December 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable