TW@ESI 1 st January 2017 Hope all of you had a good time off and Happy New Year to all! The following is a record of what was done during the last working week/s and a forecast of the first week in 2017.....
13

TW@ESI 1st January 2017

Feb 15, 2017

Download

Business

Simón Abela
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TW@ESI 1st January 2017

TW@ESI1st January 2017

Hope all of you had a good time off and Happy New Year to all!

The following is a record of what was done during the last working week/s and a forecast of the first week in 2017.....

Page 2: TW@ESI 1st January 2017

A General Note before we start-•Welcome back to all those who where overseas in Poland and wish the Fenechs a good continuing vacation down under in Aussie Land- well done to Nicky who finished the Sydney Hobart race aboard Breakthrough •Welcome to the group Donaghan- Jerico is still pending to accept the invitation to join the group•On Wednesday 3rd Jan 2017, a part time student , Patrick Brejza will be joining the TRIDIUM/HSDK software development section.

Page 3: TW@ESI 1st January 2017

Projects and deadlines• 16_007_LeMeridien_BMS_upgrade- We have started working on

phase 1 panels – phase 1 which has to be completed by Feb 2017- next steps are– We need to order the JACES and Field devices – Prepare the Software for the phase one panels– Once materials are here, design sketches are available and software is

available we will do change over.Early next year we should do the change over for the roof panels with the

programmed logic and some basic graphics only• 14_069- Q019 AS410 – We are proceeding with works here in

conjunction with Gruppo Sett in Italy• 16_025_DeLaRue_OFX- Design is ready, materials have been

ordered and training by overseas specialists will be on 16/1/17• 14_069- Q021_TF4- Panel is on site and installed- still issues to be

resolved with regards to the FOC terminations

Page 4: TW@ESI 1st January 2017

Projects and deadlines• 16_041_RSM_Zebbug_Security-. We need to complete all works by End

of January 2017- All materials have been ordered and we need to start thinking of Panel building, programming , Testing and commissioning

• 16_051_Baxter_AHU_Controls- Many thanks to all who pushed and pulled to complete what we could complete. All IO devices have been installed and tested, we could not test the closed loop due to problems on the air balancing activities by others- In our first week in we must complete what we can to put this project to sleep and complete

• 16_058_Methode- Another fast tack project Jace Based AHU control system here – we will kick it off in this week – Target is to finish it by end of February 2017- we have started ordering the long lead items here – the plan is to start Panel design ASAP and start panel build on 3 or 4th week of Jan 2017.

• 15_023_FM panels- We have a new 2 panels for FM environmental (D5M-110) ... The delivery date is not know – design is completed

Page 5: TW@ESI 1st January 2017

Projects and deadlines• 16_015_RSM- this lighting control project is to be completed in the first weeks

when we get back in we need to really keep a good eye on what is happening on site by the main contractor- we must ensure the wiring and terminations are done properly- as soon as the main contractor collects the field devices we must ensure he tests the DALI loops and then we can commission and program

• 15_011- Sliema apartments – We have done some terminations and panel build is completed too.

• 16_023_GGY- we have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

• 14_083_Intercontinental – We have commissioned the system with snags - we will return to site when snags are done by others- we also have to deliver the pool panel

• 15_038_new_HA_Ovt and 15_026_Apap Residence are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation

• 12_027- Parliament –We are finalizing the documentation and eventually need to integrate ProWatch.

Page 6: TW@ESI 1st January 2017

Projects and deadlines• 13_031_CCA- still issues with values on ILPS and we also have to execute

some new works at CCA (new cameras, pagers)• 12_043_Life Sciences – we have nearly completed all items here- some

small snags are pending to close off• 13_075_Bosch_ProWatch_Genetec_Interface - The Bosch HSDK interface

is well advanced and we have documented and we should shortly be expecting to go overseas to commission

• 13_070- SCM Lagoona Plant room We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

• 12_025- The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• 14_081_Siggiewi School- there are some snags pending here due to louvres

Page 7: TW@ESI 1st January 2017

DesignLast week• Meridien – Briefed DSH & Shridar on Panel Sketches, on site (MCPM2 &

MCPM1)• Methode SMT – released MF Parts for quote (still chasing quote)• OTM – completed SAS-000980• FM Env – Draughted new Panel Design for D5M-110 submitted to client• Sliema Graham Apartments – As Built update of DDC PanelsNext Week:• Methode SMT – release long-lead items from MF (after receipt of

quote)• Methode SMT – Points List, P&IDs, Panel Design• De la Rue – from Client drawing, convert to our Panel Drawing standard• RSM Security – Draught Intruder Panels & DAC Panels after receipt of

sketches from CCI, SAI

Page 8: TW@ESI 1st January 2017

InstallationThis past week: • Continue with works at Mosta workshop• Continue with works at Baxter• Water meter readings at Lifesciences• Fix camera and other works at CCA villaNext week:• Works at Sliema apartments• Works at Life sciences• Continue with works at Mosta workshop

Page 9: TW@ESI 1st January 2017

Panel Build

Well done to the efforts done to catch up – we are still in slight delay

• We need to fit in Le Meridien panel change overs on site• RSM security panels (DAC/Intruder)• 16_058_Methode- 3rd or 4th week of Jan 2017

Page 10: TW@ESI 1st January 2017

Mater DeiWeek 48

Yearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1

Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1,

D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1

Weekly update of antivirus on all BMS stations

ReactiveHandling of reactive work orders

Others• Participating in weekly fire drills• Tackling software work orders • New Angiography Project• Training of new team member• Integration of Samoc into Master

Page 11: TW@ESI 1st January 2017

Sales and Business DevelopmentWe are working on quotes for a Sterling

Chemicals Line 2 PLC system, S5 PLC upgrade for Kordin Grain terminals , lighting control systems in Qatar.

Page 12: TW@ESI 1st January 2017

Birthday wishes go to

Romina Buttigieg- 5th JanJohn Galea- 7th Jan

Page 13: TW@ESI 1st January 2017

Team ESI

• I would like you take the opportunity and spend 15-30 minutes reflecting on 2016 and listing what went good for you on your job and what went bad... List your achievements and disappointments and set your major objectives for 2017!! Anyone wishing to share this exercise .. Please do so!!