TW@ESI 26TH MARCH 2017
TW@ESI26TH MARCH 2017
Hello to all , hope you all had a good weekend.
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
New employee – David Abela will be starting on Monday 27th
and replacing Steve Vassallo
Some Points Before Starting
We wish Romina happy holidays in London
Me and Tbr will be on a Tridium European Forum in London- I will be back to work on 30/3
A New employees - Francisco Rupérez Herrera and Miltiadis Charalampidis
(AKA Miltos) – awaiting you to join on the Linkedin group
Steve Vassallo has given in his resignation as a Junior
Developer- I will soon be announcing his last working
day
Clifton will soon be going on long leave from 6/7/2017 – 18/8/2017 both days included
Projects and Deadlines
16_025_DeLaRue_OFX
50% of the machines have been commissioned by CFH
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017
Q021_TF4- We have done progress here
16_007_LeMeridien
We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-
We have so far done 2 panels – we needed to achieve 5 by end of Feb 2017- so we are a little behind here- I am suggesting that a plan for when the next 3 panels may be done so as to plan resources
16_066_Sterling_DCS_Line2
We have started some preliminary engineering here.... We will now proceed to detailed engineering
16_040_Playmobil_Factory
We are well advanced design and engineering here on MCC1 and 2 and I have started placing major orders- next will be panel build for MCC1 and 2 in Parallel
Projects and Deadlines
16_023_GGY
We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
DDC and DAC panels are to be installed on site – then the electrical meters and the PIRs in terraces
15_023_FM panels
15_023 Q012 [D10 Endicare 230V] - Beginning april 2017
Q004_013_D5M ASRD 110 PPA is scheduled for 30th April – we also have another scheduled for 30th Sept
16_041_RSM_Security
We need to close off here – the sooner the better – we are very close here
16_058_Methode
Project handed over – well done to all!!
Projects and Deadlines
12_043_LSP
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here , which are to be put to bed once and for all!!
The snags are centred around the AC controls and the NUOO CCTV system
14_08_Siggiewi School-
We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others-
We also have to deliver the pool panel
15_038_new_HA_Ovt and 15_026_Apap
Residence
These two home automation projects are now urgent- we need to complete all installation
We also need to start working of the software development- they are urgent and we have to perform
Projects and Deadlines
SCM Support 13_012
I will be meeting the team to start up this SISA agreement shortly
13_070- SCM Lagoona Plant room
We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
12_025_SCM PH2
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
17_002 Flooring DAC
Installation survey and parts required
01 02 03 04
DesignFor the Past week we have been working on the following
RSM Asbuilt update, in order for CCI to close-off O&MFM Environmental As Built update for CFHMethode SMT – P&IDs Panel Drawings update, & CDs for O&M
Playmobil HF80 – Draughting for both MCC1 and 2 is completed – at CVA for checking on Monday we submit
Design
Sterling DCS Line2 – Start-up meeting, Start-up design – Points List 1st run
OTM – completed & submitted last panel of Q020 Netherlocks TF3_NVC_003OTM – continued docs updated of Q021 (started & completed 5DP02 update)
01 02 03 04
DesignAnd next week… we will work on
Sterling DCS Line2 – go through 1st Run of Points list with SSa, get I/O Racks & Safety Barriers’ details, in order to generate preliminary footprint of MCC3
Design
Sterling DCS Line2 – Start P&IDs.
Playmobil – Co-odinate hand-over of parts / Design brief to Lino
Meridien – evaluate Points list from CVA, to indicate what is required in order to generate new P&IDs
This is what the Installation team have been working on last week
RSM commissioning
OVT terminations and intruder panel installation
Installation
Works on CCA villa
Sliema Apartments – installation and terminations
Parliament faults
….. And this is what is planned for next week
Sliema Apartments – installation and terminations
Reading of meters at Life Sciences
Installation
SCM MGA lock and installation survey at Flooring technologies
Works at Hasco
Installation Planning
Installation
For the next 2 weeks the following is the schedule
https://calendar.google.com/calendar/embed?src=esimalta1%40gmail.com&ctz=Europe/Malta
Next week we will • FM Env D10_Endicare_230– This will be built by a sub
contractor• MCC1 • MCC2 by sub contractor
Panel Build
Panel Build
Week start 27.03.2017 Yearly Field devices checks, IR images & coordinated tests Mar-- E01-CC1, E02-CC1, EP1-CC1, E01-CC2, E01-CC3 Quarterly panel checks Mar -- H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1, T01-CC1, T02-CC1 E01-CC1, E02-CC1, EP1-CC1, F01-CC1, F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1 Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberQxxx_ShiftingOfFridgeD109080
Next week Siemens will be at Mater Dei to make an infrastructure technical audit- thanks to Silvio , Chris and John for organizing this.
Mater Dei Maintenance
Crane Currency BMS and ELV Proposals
Actavis Solvent area Process quote
De La Rue BMS
These are the quotes the business development
team have been working on
Business Development
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
I wish you all a good and productive
week