AGC meeting January 2012 AGC meeting January 2012 California Department of California Department of Transportation Transportation Presentation Topics Caltrans Who we are Construction Contract Work Past, Present, Future Proposed State Budget Priority Initiatives Underway Mark Leja Chief, Division of Construction
14
Embed
Transportation Projects Outlook 2012 - Mark Leja, Caltrans
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
AGC meeting January 2012AGC meeting January 2012 California Department of California Department of
TransportationTransportation
Presentation TopicsCaltrans
Who we are
Construction Contract Work Past, Present, Future
Proposed State BudgetPriority Initiatives Underway
Mark LejaChief, Division of Construction
Caltrans-Who we areCaltrans-Who we are
• 20,000 Employees
• 12 District Offices
• $13 Billion Annual Budget• 15,213 miles of Highways (50,560 lane-miles)• 12,600 Bridges
Historical Construction WorkHistorical Construction Work
Historical Construction WorkHistorical Construction Work(Peak $ Last Five Fiscal Years)
2006/7 576 Projects $9.9 Bill
2007/8 601 Projects $11.0 Bill
2008/9 652 Projects $9.6 Bill
2009/10 725 Projects $9.9 Bill
20010/11 814 Projects $11.0 Bill
Today 620 Projects $9.7 Bill
Ongoing Construction projectsOngoing Construction projects(by size of project)(by size of project)
620 projects, valued at $9.7 billion• 16 (2%) above $100 million • 117 (19%) between $10 and $100 million• 291 (47%) between $1 and $10 million• 196 (32%) less than $1 million
Tentative Advertising – Next 12 monthsTentative Advertising – Next 12 months(by size of project)(by size of project)
310 projects, valued at $3.7 Billion• 8 (3%) above $100 million • 64 (21%) between $10 and $100 million• 156 (55%) between $1 and $10 million• 82 (23%) less than $1 million
Proposed State BudgetProposed State Budget(The Big picture)(The Big picture)
$9.2 billion general fund deficientGovernor proposes:
• $4.2 billion in cuts• Temporary taxes (voter approved)
10
Proposed State BudgetProposed State Budget(Key Transportation elements)(Key Transportation elements)
Single Transportation Agency• CT, DMV, CHP, Pilot Commission and HSR
Continuous appropriation of HUTA fundsCaltrans budget $11.2 billion
• 16% less than last year• will adjust in May revision
Program wide review of Caltrans
11
Priority Construction Initiatives Priority Construction Initiatives UnderwayUnderway
Partnering- keep the momentum going2010 Standard SpecificationsReducing support costs- be more efficientImplementing the new Stormwater PermitsDesign Build pilot program
12
Questions?Questions?
Thank YouThank You!!
California Department of California Department of TransportationTransportation