The Kleverud-Sørli and Sørli- Åkersvika projects Marketdialog 1. 19. oktober 2018
15

The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

Oct 28, 2019

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

The Kleverud-Sørli and Sørli-Åkersvika projects

Marketdialog 1. – 19. oktober 2018

Page 2: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

KLEVERUD-SØRLI AND SØRLI-ÅKERSVIKA

• Rules for the meeting/ marketdialog

‒ The agenda has to be equal for all supplier meeting to secure the same information level to all suppliers

• Agenda

‒ Presentation [x]

‒ Introduction to the projects

‒ Status/ Schedule

‒ Challenges

‒ Discussion

‒ Market/ Capacity 2019/ 20

‒ Priorities

‒ Contract strategy/ Enterprises

‒ Other relevant challenges and problems

2

Page 3: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

PORTEFOLIE AND MARKET

3

Page 4: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

PORTEFOLIE AND MARKET

Sterk satsing på samferdsel i det skandinaviske markedet

4

Page 5: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

More value for money

5

Page 6: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

6

• No injuries

• Cost effective

• Predictible

The Infrastructure Construction Division’s vision

Norways leading organisation for planning and execution of large infrastructure project

Page 7: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

Kleverud-Sørli

• 15,8 km double-track railway, designed for 250 km/h. Included in the project is the construction of the longest railway bridge in Norway, Tangenvika bridge (1070m), one rock tunnel the Hestnes tunnel 3,1 km and a new station at Tangen.

Sørli-Åkersvika

• 14 km double-track, designed for 250 km/h. A new station at Stange is included in the project, as well as Åkersvika Wetlands.

7

Kleverud-Sørli-Åkersvika

Page 8: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

THE KLEVERUD-SØRLI AND SØRLI-ÅKERSVIKA PROJECTS

8

2 StationsTunnel 3,10 km Bridge 1,07 km Open landscape 21,75 km

Approx. 30km double track:

Consists of:

Railroadtechnik

Page 9: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

KLEVERUD – SØRLI

• Approx.16 km double track from Kleverud to Sørli

• The Hestnestunnel 3,1 km long

• The Tangenvika bridge 1,07 km long from Espa to Tangenhalvøya

• A new Tangen Station

• Challenges:

➢Statsbudsjett 2020

➢Tangenvika jernbanebru

9

Page 10: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

SØRLI – ÅKERSVIKA

• Approx. 14 km doubletrack from Sørli to Åkersvika

• Zoning plan planned approved autumn 2019

• Re building of the Stange Station

• New railway will cross farmland, through densely populated areas, and cross protected wetlands

• Challenges:

➢Financing SB2021

➢Environment

‒ Farmland

‒ Enviromental protected area and Ramsarareas

‒ Extencive deposit management

‒ Ground condition

10

Page 11: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

Kleverud-Sørli:

• 2016: Local development plan approved

• 2018 (Q4): Approved contract strategy

• 2019 (Second half): Start prequalification of first main contract

• 2019: Start preparatory works

• 2020: Planned government funding

• 2020: First main contract award

• 2026: New infrastructure in operation

11

Sørli-Åkersvika:

• 2018 (Q4): Approved contract strategy

• End 2019: Local development plan approved

• 2019: Start preparatory works

• 2020 (Second half): Start prequalification of first main contract

• 2021: Planned government funding

• 2021: First main Contract award

• 2026: New infrastructure in operation

Planned Schedule

Page 12: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

PLAN AND BUDGET

• Cost frame 2018:

‒ Kleverud-Sørli Approx 5,9 Billion NOK

‒ Sørli-Åkersvika Approx 4,7 Billion NOK

• Expected financing:

‒ Kleverud-Sørli Statsbudsjett 2020

‒ Sørli-Åkersvika Statsbudsjett 2021

• New double track to Åkersvika in operation 2026.

12

Page 13: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

Bane NOR is dependent on our suppliers to realise our portfolio

13

Planned investments - Bane NOR

Bane NOR

Engineering

Railway technique

Construction

Typical project Bane NOR project cost split

0

2

4

6

8

10

12

14

16

18

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Bill

ion N

OK

Source: Bane NOR’s proposal of operationalisation of NTP (Innspill til Handlingsprogrammet) inclefficiency improvements

Page 14: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

Schedule for competition Kleverud – Sørli – Åkersvika (K-S-Å)

Q4Q3Q2Q1 Q4Q4Q3Q2Q1 Q4Q3Q2Q1 Q3Q2Q1

Evaluation

and

negotiationPreQ

UPG

2

2018 2019 2020 2021 2022

Q1 Q2 Q3 Q4

Contract

strategy

K-S-Å

UPG

2PreQ

Project exicutionPreparation

of offerKS2

Evaluation

and

negotiations

Zone plan & Detaled plan Sørli - Åkersvika S-Å Project exicution

K-S

SB2020

SB2021

KS2Preparation

of offer

Page 15: The Kleverud-Sørli and Sørli- Åkersvika projects · Statsbudsjett 2020 Tangenvika jernbanebru 9. SØRLI –ÅKERSVIKA •Approx. 14 km doubletrack from Sørli to Åkersvika •Zoning

CONTRACT STRUKTUR….?

Kleverud - Sørli 16 km (fra km92,5 til km108,5) Sørli – Åkersvika 14 km (fra km 108,5 til 122,5km)

Strekning / Fag

Dagsone kleverud Nærføring 1,00km

Tunnel Kleverud - Espa3,10 km

Espa dagsone0,2km

Tangenvika jernbanebru1,07km

Dagsone Furnesodden -Tangen stHøye skjær-inger 1,80km

Ny Tangen StStor fylling(inkl. overkjør-ingssløyfer)2,00km

Dagsone Tangen St - SørliMassebalanse6,00 km

Dagsone SørliNærføring0,5km

Dagsone Sørli -Stange stNærføring3,25km

Ny Stange St Nærføring1,50km

Dagsone Stange st - Ottestad3,50km

Ottestad st.Nærføring1,50km

Dagsone Ottestad -Åkersvika Parselldele4,00km

Hamar stmidlertidig tiltak

Forbredende arbeider

Prosjektering UNB II

Underbygning <MRD 1

Prosjektering JBT

JBT

Spor

Kl

EL

Tele

signal Thales Rammeavtale IV

15

Statsbudsjett 2020 Statsbudsjett 2021