Top Banner
THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process
38

THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Dec 16, 2015

Download

Documents

Riley Silman
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

THE EIA PROCESS AND

BASELINE MONITORING

CGCL Data Collection Process

Page 2: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

April 2013 CGCL Applies for environmental clearance to

construct and operate a Methanol/DME facility

Project Screening by

EMA

Scoping By the EMA

Final TOR July 19

EIA Required

Review: Definition of EIA

Page 3: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Review: Definition of EIA3

Environmental Impact Assessment is : A formal process for identifying:

The likely effects of activities or projects on the Environment and on human health and welfare.

Environment is broadly interpreted as physical, biological, and social.

In EIA, the term “impacts” is used instead of “effects of activities.”

Page 4: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Terms of Reference

The TOR’s provided is used to guide the preparation and format of the EIA Report;

It identifies the environmental aspects which required monitoring;

The information which is needed to effectively assess the project impacts and inform the decision-making process;

It makes provisions for public involvement in the process;

Indentifies project alternatives which should be examined;

It stipulates format of studies to be carried out (e.g.

methodologies and approach, time & space boundaries);

It identifies the requirements for mitigation and monitoring.

Page 5: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

What is an impact?5

The impact of an activity is a change from the baseline situation caused by the activity. The baseline situation is the existing environmental condition in the absence of activity.

The baseline situation is a key concept in EIA. To measure an impact, you must know what the baseline situation is.

Page 6: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Assessing Impacts

When collecting baseline data, the data must provide information which allows the EIA specialist to assess:- long term and short term impacts direct and indirect impacts cumulative impacts beneficial impacts and adverse impacts

Page 7: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Impact Categories

Examples of direct impacts include: increased noise and dust decreased air quality, decreased water quality, increased solid waste, increased employment (3000 jobs at peak

construction), increased training and education, increased infrastructure development.

Page 8: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Impact Categories

Indirect impacts include: increased traffic, increased commercial activity increased employment small business development

Cumulative impacts include: Are those which provide incremental

contributions to existing conditions produced by existing industries and socio cultural activities

Page 9: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

The Baseline Situation9

•In characterizing the baseline situation, many environmental components are of interest.

•The components of interest are those that are likely to be affected by your activity—or upon which your activity depends for its success

Water Quantity of Pollutants, quality.

Soils Erosion, soil type, crop productivity

Flora Composition and density of natural vegetation, productivity, key species

Fauna Population size, habitat health, sensitive, rare or commercially valuable species

Noise Sound pressure levels

Air Quality, Quantity of Pollutants

Page 10: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

4 Components of the Baseline Environment

The Physical and Chemical Environment The Biological Environment The Human (Social Environment) The Human (Economic Environment)

Page 11: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Sampling Method

Sampling design involved the collection of historical data from published sources and EIA documents and well as the conduct of field surveys.

Historical data will be used to establish past trends observed.

Real time data collected through sampling will be used to determine the current environmental status as well as validated the historical data sets.

Focus was placed on collecting data necessary for determining the impact of CGCL’s proposed operations.

Page 12: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Defined Study Area

The immediate study area includes all of the land, air and sea space within a five kilometre radius of the proposed plant site

The wider study area was defined as

areas directly, or indirectly affected by proposed CGCL activities and encompasses all of that area within a 10km radius of the project site.

Page 13: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Ambient Air and Climate

Climate –local climate, rainfall, temperature variation, humidity

Ambient Air Quality – Levels of combustion gases present (NOx, SOx, CO2, Volatile organic compounds). Level of dust particulates present (TSP, PM10, PM2.5)

Light intensity Ambient Noise Levels (SPL) taking into

consideration community activities, traffic and existing industrial activities

Page 14: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Geology, Sediment and Soil

Geology and topography. Information was gathered to describe; Existing topography Presence of geological features such as

faults, rivers, aquifers. Seismic studies Soil type /rock type

Current sediment quality within the Vessigny River and Coast of La Brea (Heavy metals, Hydrocarbon compounds)

Page 15: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Hydrology

Vessigny River characteristics: seasonal flow rate, flooding, discharge rate.

Water quality (i.e. pH, temperature, DO, BOD, Heavy-metal content, hydrocarbon content, nutrient content, bacteriological characteristics)

Characteristics of aquifer present: usage, areas of recharge, capacity

Page 16: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Coastal processes

Wave and current characteristics.

Sea bed characteristics (bathymetry)

Marine-water quality (e.g.. pH, temperature, DO, salinity, Heavy-metal content, hydrocarbon content, nutrient content)

Page 17: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Biological Environment

Description of the Flora and fauna present within the immediate impact zone.

Vegetation and Fauna found on UIE Main site

Living organisms found within the Vessigny River

Living organisms found in Brighton Harbour, within the impact zone of the proposed seawater intake, process water outfall and shipping lanes. (i.e. benthic, free-swimming and planktonic organisms)

Page 18: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Biological Environment

Emphasis will be placed on examining and describing:

The presence of any sensitive habitats (e.g. mangrove systems, nursery areas, spawning grounds).

Sensitive, rare, endangered or commercially important species found within the study area and impact zones.

Page 19: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Social Environment

The Social Impact Assessment (SIA) involves analysing, monitoring and managing the social consequences of development. - International Association for Impact Assessment

Data is current being collected to describe the social and cultural environment within the defined study areas.

Sources of data collected include; CSO census data, information from village councils and community-based organizations and primary field surveys.

                                                     

Page 20: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Data Collected Thus Far

Page 21: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Flora found on the Main Site UIE

Flora on Site

Page 22: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Sedges and grasses

Page 23: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Fauna found on the Main Site UIE

Terrestrial Fauna Onsite

Page 24: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Terrestrial Fauna Onsite

Cnemidophorus lemniscatus

Page 25: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

White-Headed Marsh-Tyrant

Arundinicola leucocephala

Page 26: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Blue-black Grassquit

Volatinia jacarina

Page 27: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Shiny Cowbird

Molothrus bonariensis

Page 28: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

River Sample Stations

Station 3 Mouth of River

Station 1Down Stream of project site

Station 2Down Stream of the SMR

Station 4Vessigny Beach

Page 29: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.
Page 30: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Fresh Water Fishes

Hoplias malambaricus

Page 31: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Two-Spotted Sardine /Doree

Astyanax bimaculatus

Page 32: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Brackish Water Fish

Cavalli Caranx hipposCatfish Ariidae (lpil)

Page 33: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Brackish Water Fish

Coscorob Aquidens pulcher

Mullet Mugil sp.

Page 34: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Crustaceans

Honey Shrimp Xiphopenaeus kroyeri

Cirrique Callinectes sp.

Page 35: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Air and Noise Sample Stations

Sobo Village Rec. Ground

La Brea round -about

NESC

UIE Main Site

Page 36: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Marine Stations Sampled

5m

10m

15m

N

Brighton Port

Page 37: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Next Phase In EIA ProcessBaseline data Collection

Project Alternatives

Impact Assessment

Mitigation and Monitoring Plans

Social Field Survey

Social Impact Assessment

Modelling studies

EIS preparation

Page 38: THE EIA PROCESS AND BASELINE MONITORING CGCL Data Collection Process.

Thank You for your Attention