Page 1: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

The BIM ToolkitStephen Hamil – March 2015 – v2.0

Page 2: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

BIM – Government Construction Strategy

Francis MaudeMinister for the Cabinet Office

Page 3: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

BIM – Government Construction Strategy

Page 4: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

BIM – Government Construction Strategy

Page 5: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Completing “Level-2” BIM Suite

Page 6: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

The Missing Pieces

Digital P

lan of Work

Classification

Page 7: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

The Project

2014 2015

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Scope Brief Phase 1 - Define Phase 2 - Deliver

Clients Brief Team Industry

Page 8: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

BIM Toolkit and Level-2 BIM

How will the BIM Toolkit benefit those working within the level-2 BIM process?

Standards are freely available at - http://shop.bsigroup.com/BIM

Page 9: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need

ProcurementPost-contract

award and mobilisation

Production

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Maintenanceand use

Page 10: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need

Page 11: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Page 12: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need

Client determines their plain language questions(determines the need)

Client produces their employer’s information requirements(Required information to meet the needs as )

Information requirements aligned to the project stages This is part of the tender documentation

Page 13: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

A collection of projects

Page 14: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Information at a project level

Page 15: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Information at a stage level

Page 16: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

At the start of the project the client

has not assembled their team

Page 17: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

At strategy/brief stage it is possible to

determine information needs

Page 18: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Template tasks can be modified,

removed and added to

Page 19: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Tasks and deliverables are assigned to roles

prior to the team being assembled

This information may be exported

Page 20: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need

Export to MS Excel for inclusion within the EIR document

(PDF)

…and export to IFC/COBie for digital

re-use

Page 21: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Procurement

Page 22: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Procurement

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Page 23: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Procurement

Bidders respond with their pre-contract BIM execution plan Proposed responsibility of bidders supply-chain is provided The client can compare these against their original information

requirements Selection can take place

Page 24: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

The proposed roles have been assigned

The proposed project team has

been added

Each item, at each stage has a party

responsible

The bidder

Page 25: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Procurement

Export to MS Excel for inclusion within the BEP document

(PDF)

…and export to IFC/COBie for digital

re-use

Page 26: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Post-contract award and mobilisation

Page 27: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Post-contract award and

mobilisation

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Page 28: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Production

Page 29: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Production

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Page 30: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Production

From design suppliers to construction suppliers:

The federated Project Information Model begins to grow dPOW defines the what, the when and who Information exchanges between supply-chain Information delivery to the client as agreed in EIR Documented classification and data structure allows for verification

Page 31: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Moving into the design phases the team is now

assembled and the information requirements

grow

Page 32: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Level of detail guidance can be defined for each

deliverable

Page 33: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Level of information guidance can be defined for each

deliverable

Page 34: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

A definitions library of 6,000 items across all construction disciplines will be provided

Page 35: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

At concept stage – the operations phase may be

considered

Page 36: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

At the technical design stage more geometric detail is

required

Page 37: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

The level of information grows through the bandings

too

Page 38: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

LOI-6 contains the standard COBie properties for transfer

to the asset management systems

Page 39: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

The definitions library covers infrastructure in addition to

buildings

Page 40: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

RICS have joined the core team and have provided

classification mappings to NRM1

Page 41: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

A number of new Uniclass classification tables will be

published

Page 42: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

At an early stage space requirements may be

specified

Page 43: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

New Uniclass – the Core Classification

Page 44: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

Advanced search technology is used to take the complexity

away from classification

Page 45: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Production

What has been asked for by the

project lead

What is provided by the project team

Page 46: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Deliverables

COBie XLSIFC 2x3

Documents

EIR

Data

ObjectsDocuments

ObjectsDocuments

Objects

DocumentsObjects

DocumentsObjects

DocumentsObjects

SpreadsheetBIM ToolXML

Validation Process Overview

Requirements

COBieLite

Validation

IFC Exchang

e

DPoWExchang

e

BEP

Data

DPoWExchang

e

Schema too rich

Schema too loose

Page 47: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Assessment and need – BIM Toolkit

A dPOW in IFC – every deliverable represented as a

coloured cube

Page 48: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Following hand-over then “In use”

Page 49: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

Operation

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Page 50: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

- ID- ParentSpace- Level- Manufacturer- Model- ExpectedLife- O+M-Manual

Page 51: The BIM Toolkit Stephen Hamil – March 2015 – v2.0.

More Information

BIMTaskGroup.org

theNBS.com/BIMToolkit

Social Media - #BIMToolkit