The Atlanta BeltLine SE Study Groups: Eastside Trail Phase II Extension Updates July 20, 2017 @atlantabeltline @atlantabeltline @atlantabeltline View South of Kirkwood Ave
8

The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

May 08, 2018

Download

Documents

builien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

The Atlanta

BeltLine

SE Study Groups:

Eastside Trail Phase II

Extension Updates

July 20, 2017

@atlantabeltline

@atlantabeltline

@atlantabeltline

View South of Kirkwood Ave

Page 2: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Phase II Overview

• Kirkwood

Avenue to

Memorial

Drive

Page 3: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Scope of Work – General

• Installation of trail from Kirkwood Ave to Memorial Dr

• Lighting

• Cameras

• Bioswales

• Trees

• Planting

• Sod Shoulder

Page 4: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Scope of Work – Kirkwood

• Trail crossing at Kirkwood

• Rapid Flashing Beacons and granite work

• Other design options being evaluated

Page 5: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Scope of Work – Mauldin

• Installation of new pedestrian-scale bridge

• Installation of new sidewalks along Mauldin/Fulton Terrace

• Installation of ramp and stairs to the trail from Mauldin/Fulton Terrace

Page 6: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Scope of Work – Memorial

• Installation of

plaza at

Memorial

Drive

Page 7: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Possible Impacts

• Closure of Mauldin/ Fulton Terrace during bridge work

• Short lane closure for work at Kirkwood for crossing

• Hiking trail closure from Memorial to Kirkwood

• Memorial Drive sidewalk closure during plaza construction

Page 8: The Atlanta BeltLine - beltlineorg-wpengine.netdna-ssl.com · The Atlanta BeltLine ... • Bioswales • Trees • Planting • Sod Shoulder . Scope of Work – Kirkwood ... PowerPoint

Questions

@AtlantaBeltLine // [email protected]

Looking South to Kirkwood Ave (2013)