Top Banner
Target Value Design & Integrated Project Delivery Dr Glenn Ballard at Loughborough University 27 January 2010 1 Target Value Design and Integrated Project Delivery Glenn Ballard Loughborough 01/27/2010 Topics Review: SuHer Health hospital projects Target Value Design Integrated Project Delivery Update Progress on the SuHer Health hospital projects What’s been learned? A new challenge to be faced in complePng design Whole Life Target Value Design
25

Target Value Design for Integrated Project Delivery

Jan 04, 2017

Download

Documents

lamkhanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

1

Target  Value  Design  and  Integrated  Project  Delivery  

Glenn  Ballard  

Loughborough    01/27/2010  

Topics  

•  Review:  – SuHer  Health  hospital  projects  – Target  Value  Design  –  Integrated  Project  Delivery  

•  Update  – Progress  on  the  SuHer  Health  hospital  projects  – What’s  been  learned?  – A  new  challenge  to  be  faced  in  complePng  design  

•  Whole  Life  Target  Value  Design  

Page 2: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

2

2005 CURRENT Proposed Building Area: 1,298,500 BGSF 914,757 BGSF

Number of Stories (incl. below grade Parking and CUP):

21 18

Total No. of Beds: 620 555 Total No. of LDRs: 24 24 Total No. of ORs: 19 19 Total No. of ER Treatment Rms:

34 34

Loading Dock Location: Access off Post St. Access off Franklin St. Ambulance Location: Access off Franklin

St. Access off Post St.

Total No. of Parking Spaces: 620 555 2005 Design was $400 M over budget.

Current Design on budget moving towards surplus.

90%  of  the  program  in  70%  of  the  space.  

Page 3: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

3

Project  Phases  and  Target  CosPng  

The  ValidaGon  Study  

Establishing  a  Shared  Understanding,    

Basis  of  Design,  Budget  and  Schedule.  

The  Star)ng  Point  for  Target  Value  Design  

Page 4: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

4

Target  CosGng    

• Integrated  team  validates  facility  can  be  built  within  the  allowable  cost    • Sets  target  cost  at  or  below  allowable  cost  • Owner,  architect  and  contractors  work  within  market  constraints  

FEEDBACK LOOP

©  Glenn  Ballard,  2008  

SeJng  the  target  cost  and  project  schedule  

Target  set  14%  ‘below’  marketplace  

Nine-­‐project  marketplace  average  

Page 5: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

5

IPD  Target  Value  Design  Clusters  

M/E/P  

Cluster  Leaders  

Structure  

Landscape  

Material  Handling  

VerPcal  Transp.  

Site  Improvements  

Interior/  Finishes  

Building  Envelope  

Cluster  Targets  

Mechanical,  Electrical,  Structural,  Enclosure,  Interiors,  Gen.  CondiPons,  Equipment,  Furnishings,  Technology  

Page 6: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

6

Steel  Structure  

• ValidaPon  ~  22psf    • Current  Design  ~  20psf  • Industry  Standard  ~  30psf  

Viscous  Wall  Dampers  

Page 7: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

7

From  Construc,on  Industry  Ins,tute  research  by  Victor  Sanvido  

"Projects  are  built  by  people.    Research  into  successful  projects  has  shown  that  there  are  several  criPcal  keys  to  success.    A  knowledgeable,  trustworthy,  and  decisive  facility  owner/developer.  

 A  team  with  relevant  experience  and  chemistry  assembled  as  early  as  possible,  but  certainly  before  25%  of  the  project  design  is  complete.    

 The  contract  encourages  and  rewards  organizaPons  for  behaving  as  a  team."    

The  5  Big  Ideas  

Collaborate;  Really  Collaborate  

Networks  of  Commitment  

Tightly  Couple  Learning  w/  AcGon  

OpGmize  The  Whole  

Increase  Relatedness  

Page 8: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

8

Our  “Big  Room”  

Colloca)on  An  environment  

of  collabora)on,  trust,  and  innova)on      

Integrated  Project  Delivery  

•  3  party  contract  between  owner,  architect  and  construcPon  manager/general  contractor.  

•  A  relaPonal  as  opposed  to  a  transacPonal  contract.  

•  Engages  downstream  players  in  upstream  processes  and  vice-­‐versa.  

•  Three  Musketeer  arrangements:  one  for  all,  all  for  one  –  Shared  risks  and  rewards  – Money  can  move  across  organizaPonal  boundaries  in  search  of  the  best  investments  for  the  project  

Page 9: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

9

Structure  

•  One  Agreement  signed  by  O-­‐A-­‐C  

•  “Joined”  by  jointly  selected  team  members    •  Provides  for  formaPon  of:  

–  Core  Group  –  Integrated  Project  Delivery  Team  –  Senior  Management  Group  

Integrated  Team  Concepts  

Owner  Stakeholder  

CM/GC’s  PM  Architect’s  PM  

Owner’s  Rep  

Core  Group  

Civil  

Structural  

Mechanical  

Electrical  

Plumbing  

Site  

Steel  

Mechanical  

Electrical  

Plumbing  

Framing  

Landscape  

Landscape  

Other  Other  

Integrated  Project  Delivery  Team  

Page 10: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

10

ExecuPve  Involvement  

Owner  Stakeholder  

CM/GC  PM  Architect  PM  

Owner’s  Rep  

Senior  Mgt.  

Senior  Mgt.   Senior  Mgt.  

Senior  Mgt.  

Core  Group/Senior  Mgt.  

SuHer  Health’s  IFOA  requires  

•  Last  Planner  •  Target  Value  Design  •  5S  Plan  

– Site  logisPcs  using  sort,  set  in  order,  shine,  standardize,  sustain  

•  Zero  RFI  Goal  – conversaPon  first,  pursue  reliable  promise  for  resoluPon  

– RFI  to  confirm  soluPon  (not  to  iniPate  inquiry)  

Page 11: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

11

SuHer  Health’s  IFOA  requires  

•  Built-­‐In  Quality  Plan  –  CII  study  suggests  that  up  to  10%  of  construcPon  cost  is  “rework”  

–  “InspecPons”  omen  fail  to  improve  quality  at  hand-­‐off  from  trade  to  trade  

–  Plan  seeks  to  directly  aHack  root  causes  of  quality  failures  –  P2SL  is  assisPng  in  developing  BiQ  for  establishing  standard  work,  tracking  &  improving                      

SuHer  Health’s  IFOA  requires  

•  Payments  within  10  days  

•  Problem  ResoluPon-­‐-­‐escalaPon  –  ParPes  negoPate  –  Core  Group    –  Senior  ExecuPves  –  Independent  Expert  –  MediaPon  

Page 12: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

12

The  Role  of  TVD  in  IPD  

TVD  is  a  process  for:  •  Defining  the  project  in  terms  of  value  to  owner  and  stakeholders.  

•  Seong  targets  for  what  is  to  be  delivered  (scope,  level  of  quality),  and  the  constraints  within  which  it  is  to  be  delivered  (cost,  Pme,  locaPon).      

•  Determining  the  feasibility  of  the  project:  can  what’s  wanted  be  delivered  within  constraints?  

•  Steering  design  and  construcPon  to  targets.  

Topics  

•  Review:  – SuHer  Health  hospital  projects  – Target  Value  Design  –  Integrated  Project  Delivery  

•  Update  – Progress  on  the  Su^er  Health  hospital  projects  – What’s  been  learned?  – A  new  challenge  to  be  faced  in  compleGng  design  

•  Whole  Life  Target  Value  Design  

Page 13: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

13

Target  Cost  &  Weekly  EsPmate  Updates  

Page 14: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

14

Choosing By Advantages Study of: Heating Hot Water SystemAlternative 1 Alternative 2

Central Plant Heating Hot Water System

Distributed Heating Hot Water

Factor: Square feet of Mechanical Space Required

Criteria: Attribute 3200 square feet5100 sq ft required/17

roomsAdvantage 1300 Sq Ft. 2

Factor: Access for MaintenanceCriteria: Attribute Outside secure perimeter Inside secure perimeter

Advantage Outside rather than in 4

Factor: Quantity of Boilers & StandbyCriteria: Attribute 3 duty plus 1 standby 20 duty +7 Standby

Advantage Less total boilers 5

Factor: Ability to do Boiler Stack Heat Recovery

Criteria: Attribute10% increase in boiler

efficeincy Not requiredAdvantage Reduction X therms 8

Factor: Pumping Energy

Criteria: AttributeMore required due to long distribution runs

Less required due to shorter piping runs

Advantage 500,000 KwH per year 10

Factor: Construction Schedule

Criteria: AttributeLonger due to site

distributionShorter - no site distribution

requiredAdvantage 2 weeks 1

Total Importance 19 11Capital Cos t

Page 15: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

15

Quality & Safety

VSM Trade Flow

???

Bid/Scope Allocation

Job-Site Environment

Construct’n Engineering

Estimate

Owner’s Reqrmnts.

AHJ

F.R.S.

Design Standards

VSM Design Info. Flow

BIM Standards

Budget

Work Packaging

Construction Standards

Materials & Suppliers Sequencing/

Scheduling

Quality Assurance

Supply-Chain Database

Lean Site Logistics

Strategic Sourcing

ConstrucPon  Process  Improvement  Value  Stream  Mapping  

3. Production Planning

•  Electrical:  Light  Fixture  Install  •  Ductwork:  Complete  Duct  Install  Process  •  Fire  ProtecPon:  Sprinkler  Install  •  Plumbing:  Toilet  Install  

Current State Future State

Page 16: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

16

BEFORE   AFTER  

Page 17: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

17

Eliminate  Waste  

ConPnuous  

Improvement  and  Learning  

Respect  Challenge  and  Grow  Them  

Long-­‐Term  Thinking  

Problem  

Solving  

People  and  Partners  

Process  

Philosophy  

The  Challenge:  Crea,ng  a  Lean  Culture  in  a  Project  Environment  

Page 18: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

18

What  has  been  learned?  •  Building  the  culture  is  criPcal.  One  key  is  to  change  supervisory  

behavior.  Another  is  to  redefine  everyone’s  role.  Both  are  works  in  progress,  but  cultural  shim  in  aotudes  and  behaviors  has  definitely  been  made.  

•  Design  can  always  be  improved,  but  must  be  steered  to  the  delivery  of  value  within  project  constraints.  In  other  words,  you  must  know  when  to  stop;  the  last  responsible  moment.  Structuring  design  work  could  have  been  done  beHer.  Now  experiencing  refinements  in  design  that  seem  trivial  from  the  perspecPve  of  design  intent  but  maHer  a  great  deal  to  those  who  will  use  the  design  for  purchasing,  fabricaPon,  installaPon,  inspecPon,  and  commissioning.      

•  The  expected  cost  keeps  falling.  Process  design  may  offer  as  much  or  more  potenPal  for  savings  than  product  design.  

•  Choosing  by  Advantages  is  a  powerful  method  for  achieving  consensus  among  stakeholders  with  different  values.  

•  It  really  is  vital  to  design  facility  use  before  designing  the  facility.    

Page 19: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

19

Lean  in  Healthcare  OperaPons  

Thedacare  and  Virginia  Mason  first  applied  lean  to  healthcare  delivery,  then  later  to  the  design  and  construcPon  of  healthcare  faciliPes.  

The  opposite  has  happened  at  SuHer  Health.  The  result:  a  challenge  for  Cathedral  Hill  as  they  prepare  for  construcPon—how  to  handle  the  inevitable  demand  for  changes  in  building  design  to  facilitate  a  lean  approach  to  faciliPes  management  and  healthcare  delivery?  

Topics  

•  Review:  – SuHer  Health  hospital  projects  – Target  Value  Design  –  Integrated  Project  Delivery  

•  Update  – Progress  on  the  SuHer  Health  hospital  projects  – What’s  been  learned?  – A  new  challenge  to  be  faced  in  complePng  design  

•  Whole  Life  Target  Value  Design  

Page 20: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

20

If  It  Were  To  Be  Budgeted  TradiPonally  

Page 21: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

21

Overview  of  Target  Value  Design    •  Values  are  developed  from  purposes  and  design  criteria  from  

values  •  Design  begins  with  how  the  facility  will  be  used  before  

designing  the  facility  •  Key  members  of  the  project  team  are  engaged  to  help  

validate  and  improve  project  business  plans  •  Clients  tell  the  project  team  what  they  are  able  and  willing  

to  spend  to  get  what  they  want-­‐their  allowable  cost  •  Targets  are  set  as  stretch  goals  to  spur  innovaGon  •  Design  is  steered  toward  targets  using  a  set  based  approach  

in  which  alternaGves  are  evaluated  against  values  and  decisions  are  made  at  the  last  responsible  moment  

Two  outcomes  of  TVD  that  look  to  be  repeatable  (at  least  within  the  healthcare  and  educaPon  

sectors)  

1.  Projects  are  completed  below  market  cost—so  far  as  much  as  19%  below.  

2.  Expected  cost  falls  as  design  develops.  

Page 22: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

22

For  those  who  only  buy  and  do  not  produce  (design  or  make),  cost  is  driven  by  market  pricing.      

Target   Value   Design   treats   cost   as   an   outcome   of   producPon  system  design,  operaPon  and  improvement.    

Why?  

Why?  

•  ProacPve  value  engineering;  e.g.,  viscous  wall  dampers  

•  Scope  control  – Scope  grounded  in  business  purpose  – Steering  design  to  targets    

•  Scope  refinement  –  involvement  of  specialists  in  designing  improves  buildability  and  reduces  conPngency  

Page 23: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

23

Whole  Life  Target  Value  Design  

Why  Change  a  Winning  Game?  •  To  enable  beHer  investment  of  cost  savings—to  deliver  greater  value  to  owner  and  stakeholders.  

RelaPve  Costs  

Page 24: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

24

What  Changes?  

•  Give  the  design  team  a  tool  to  calculate  the  impact  of  design  alternaPves  on  facility  whole  life  costs  and  benefits.  

•  Keep  the  budget  alive  during  design,  recalculaPng  the  allowable  and  target  cost  based  on  the  anPcipated  impact  of  design  alternaPves  on  whole  life  costs  and  benefits.    

Challenges  1.  Persuade  clients  to  develop  an  operaPons  cost  model  

and  use  it  to  calculate  their  return  on  investment,  and  hence  what  they  are  willing  to  invest  to  get  that  return.  

2.  Persuade  clients  to  give  the  operaPons  cost  model  to  the  design  team.  

3.  Learn  how  to  link  the  product  and  operaPons  models  so  changes  in  the  former  are  reflected  in  the  laHer.  

4.  Persuade  financiers  to  allow  a  floaPng  budget  during  design.  

5.  Learn  how  to  design  to  a  moving  target.  

Page 25: Target Value Design for Integrated Project Delivery

Target  Value  Design  &  Integrated  Project  Delivery  Dr  Glenn  Ballard  at  Loughborough  University  27  January  2010  

25

What  limits  customer  value?  

•  The  extent  to  which  design  and  construcPon  enables  realizaPon  of  purpose.  Forecast  the  impact  of  design  alterna,ves  on  whole  life  costs  and  benefits.  

•  Ability  to  fund  the  investment  required  in  design  and  construcPon.  Adjust  allowable  and  target  costs  to  forecast  benefits.    

•  The  extent  to  which  the  facility’s  potenPal  is  realized  in  use.  Consider  a  project  complete  only  when  the  facility  is  opera,ng  to  target  performance.  

Comments?  QuesGons?