SUMMER TRAINING PRESENTATION IN THERMAL POWER PLANT AT JINDAL STEEL & POWER LTD. (C.G.) PRESENT BY: AMIT BANSAL BE- ELECTRICAL 101204012
Nov 16, 2014
SUMMER TRAINING PRESENTATION
IN THERMAL POWER PLANT
ATJINDAL STEEL & POWER
LTD. (C.G.)PRESENT BY:
AMIT BANSALBE- ELECTRICAL
101204012
JSPL is an steel and energy company Founded in 1969 by late O.P. Jindal Third largest producer of steel in India 11th fastest growing company in India Its turnover is around US$ 3.56 billion Chairman- Mr. Naveen Jindal
COMPANY PROFILE
Situated in Dongamahua, a village in Raigarh district of Chattisgarh
It is a captive power plant with capacity 4*135 MW
Coal used is low grade coal Coal supply is from Dongamahua
captive coal mines Two transmission lines one line is going
to JPL, Tamnar and other line is going to JSPL, Raigarh
Power is transmitted at 220 kv
POWER PLANT OVERVIEW
Turbines are steam driven Fuel used is coal Turbine is mechanically coupled with
generator (135 MW) Works on Rankine cycle
THERMAL POWER PLANT
RANKINE CYCLE
WORKING OF THERMAL POWER PLANT
provides the facility of switching, control and protection of electric power
Power is transferred at 220 kv Total 16 bays Switchyard equipments are grounded by two
earthing connections
220 KV SWITCHYARD
Automatically operated switch Protect electrical circuits from overload or
short circuit Detect fault condition and interrupt the
flow SF6 has high insulating property & high
electronegativity i.e. has high affinity to absorb electron
Operated at ON load condition
SF6 CIRCUIT BREAKER
Manually operated mechanical switch which isolates a part of circuit from system as and when required
operated at off load condition Must be open after circuit breaker is open
and must be close before circuit breaker is closed
ISOLATOR
Static machine used for step up or step down current/voltage.
In DCPP there are 4 different ratings of transformer are used
Generating Transformer Substation Transformer Unit auxiliary Transformer Mines substation Transformer
POWER TRANSFORMER
Critical link between power station and the transmission network
Rating is 180 MVA Step up 13.6 KV to 220 KV Windings in GT are star-delta connected Total 4 GT’s
GENERATING TRANSFORMER
Rating is 40 MVA Used when either the unit or plant shut
down takes place So to start the plant or unit they take the
power from JPL Windings are star-star connected Step down transformer Total 3 ST’s
SUBSTATION TRANSFORMER
Rating 25 MVA Used to run the auxiliaries of the plant Once with the help of ST’s unit is started
then after disconnecting ST generated power is utilized with the help of UAT
Directly connected to the generator output Windings are delta-star connected Step down 13.6 KV to 6.9 KV Total 4 UAT’s
UNIT AUXILLARY TRANSFORMER
Coal supply in DCPP is from their captive mines
So, to supply power to mines MST’s are used
Rating is 50 MVA Total 2 MST’s
MINES STATION TRANSFORMER
In DCPP oil immersed transformers are used Mineral oil is used Provides insulation to the winding and act
as coolant Protects windings from direct contact with
oxygen
TRANSFORMER OIL
transformer goes under thermal & electrical stresses
Gases are produced due to decomposition of transformer insulating oil
Affect the insulation of winding When fault is major, production of
decomposed gases are more & collected in buchholz relay
But when gases are not significantly high they get dissolved in oil
TESTING OF TRANSFORMER OIL
Amount of gases are analyzed by DGA kit
General gases found are hydrogen, ethane, methane, ethylene, acetylene, carbon monoxide, carbon dioxide, nitrogen and oxygen
DISSOVED GAS ANALYSIS TEST
GAS APPROVED LIMIT(ppm) H2 100
CO2 2500 C2H2 2 CO 350
C2H4 50 C2H6 65 CH4 120
DGA KIT EQUIPMENT IN WHICH OIL IS KEPT
Dielectric strength of oil is known as breakdown voltage of transformer oil
Measured by observing at what voltage sparking occurs b/w two electrodes separated by 2.5 mm gap
Low value of BDV indicates that presence of moisture
Minimum value of BDV at which transformer oil can safely be used is 50kv
BREAKDOWN VOLTAGE TEST
BDV KIT
measure insulation resistance in MΩ Test should be run between each winding
and ground and between each pair of winding
Low value indicates that transformer is the problem
Polarization index, P.I.=R10/R1 P.I. must be greater than 2
INSULATION RESISTANCE TEST (MEGGER TEST)
Polarization index Condition of winding
Measures to be taken
<1 Hazardous Dry winding
1-1.5 Bad Dry winding
1.5-2 Doubtful Drying is recommended
2-3 Adequate
3-4 Good
>4 Excellent
MEGGER KIT
When load is increased, insulating oil of the transformer gets heated up, expands and expels in conservator tank and subsequently pushes out the dry air through silica gel breather When oil cools down, air from atmosphere is drawn into the transformer. During this to prevent moisture from entering silica gel is used. When silica gel breather absorb moisture it turns from blue to pink
TRANSFORMER BREATHES!!!
SILICA GEL BREATHER
Due to flowing of current oil gets heated Rating of transformer depends upon
allowable temp. rise limit So to prevent transformer oil from excessive
heating, radiators are used It increases the surface area of oil Can further be accelerated by using cooling
fans
RADIATOR
Oil temp. indicator60-65 – alarm – fan on90-95 – transformer trip
SINGLE LINE DIAGRAM OF
DCPP