As on 30.04.2011 Land Acqusition Civi works completed Structure, transformer, sub station eqpt.received Structure, sub station eqpt.erected Transf. erected& tested Original Target Date Actual/ Now Anticipated date 1 2 3 4 5 6 7 8 9 10 11 12 13 A 765/400kV Substations (a) Central Sector 1 Aug-08 a Gaya 765/400 3x1500 A 60% 60% 20% Yet to be started. Aug-12 Mar-12 Efforts being made to complete the sub station earlier. Threats from Maoist extremis is hampering progress b Sasaram 765/400 2x1500 U A * Aug-12 Aug-12 * To be accomodated in the existing HVDC station. Efforts being made to complete progressively from Dec'11 matching with associate line completion. c Fatehpur 765/400 2x1500 A 60% 60% 40% Yet to be started. Aug-12 Mar-12 Engg., civil works & erection under progress. d Lucknow 765/400 2x1500 A 70% 80% 50% Yet to be started. Aug-12 Mar-12 Engg., civil works & erection under progress. e Ranchi 765/400 2x1500 A 20% Aug-12 Aug-12 Engg. & supply under progress. Serious local problem being faced in land acquisation. Critical f 400 kV Balia Aug. to 765 kV 2x1500 A 70% 80% 50% Yet to be started. Aug-12 Mar-12 Engg., civil works & erection under progress. g 400 kV Agra Aug. to 765 kV 2x1500 A 40% 70% 30% Yet to be started. Aug-12 Aug-12 Engg., civil works & erection under progress. Completion affected due to delay in land acquisation. 2 Aug-08 a Fatehpur Extn. 765/400 2x315 A 70% 70% 40% Aug-12 Mar-12 Engg. ,civil works & erection in progress b Gaya Extn. 765/400 2x315 A 0% Aug-12 Mar-12 * Being constructed under DVC (main) project. Award placed in Aug'09. Date of Award Common Scheme for 765kV pooling Station and Network Associated with DVC & Maithon RB Project and import by NR & WR via ER STATUS OF CONSTRUCTION OF ONGOING SUB-STATIONS(220 KV and above) DURING 2011-12 Cummulative progress till date Commissioning Sl. No. Remarks Name of the Sub-Station Voltage ratio (kV/kV) Capacity MW/MVA Supplementary Transmission system Associated with DVC & Maithon Right Bank Project pspm(cea) Sub Stns 1 of 21
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
As on 30.04.2011
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
A 765/400kV Substations
(a) Central Sector
1 Aug-08
a Gaya 765/400 3x1500 A 60% 60% 20% Yet to be
started.
Aug-12 Mar-12 Efforts being made to complete the sub
station earlier. Threats from Maoist
extremis is hampering progress
b Sasaram 765/400 2x1500 U A * Aug-12 Aug-12 * To be accomodated in the existing
HVDC station. Efforts being made to
complete progressively from Dec'11
matching with associate line completion.
c Fatehpur 765/400 2x1500 A 60% 60% 40% Yet to be
started.
Aug-12 Mar-12 Engg., civil works & erection under
progress.
d Lucknow 765/400 2x1500 A 70% 80% 50% Yet to be
started.
Aug-12 Mar-12 Engg., civil works & erection under
progress.
e Ranchi 765/400 2x1500 A 20% Aug-12 Aug-12 Engg. & supply under progress.
Serious local problem being faced in
land acquisation. Critical
f 400 kV Balia Aug. to 765 kV 2x1500 A 70% 80% 50% Yet to be
started.
Aug-12 Mar-12 Engg., civil works & erection under
progress.
g 400 kV Agra Aug. to 765 kV 2x1500 A 40% 70% 30% Yet to be
started.
Aug-12 Aug-12 Engg., civil works & erection under
progress. Completion affected due to
delay in land acquisation.
2 Aug-08
a Fatehpur Extn. 765/400 2x315 A 70% 70% 40% Aug-12 Mar-12 Engg. ,civil works & erection in
progress
b Gaya Extn. 765/400 2x315 A 0% Aug-12 Mar-12 * Being constructed under DVC
(main) project. Award placed in
Aug'09.
Date of
Award
Common Scheme for 765kV pooling Station and
Network Associated with DVC & Maithon RB Project
and import by NR & WR via ER
STATUS OF CONSTRUCTION OF ONGOING SUB-STATIONS(220 KV and above) DURING 2011-12
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
Supplementary Transmission system Associated
with DVC & Maithon Right Bank Project
pspm(cea) Sub Stns 1 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
3 Mar-10
a Vindhyachal Pooling station 765/400 2x1500 Nov-12 Award placed in Feb'11..
Completion affected due to land
acquisation.
4 Dec-10
a Jabalpur Pooling station 765/400 2x1500 Dec-13 Tendering under progress.
Northern Region
5 Jul-09
a Jhatikara 765/400 4x1500 A 40% 60% 10% Jan-12 Award placed in Sep'09. Engg. civil
works & erection in progress.
b Meerut (Aug.) 765/400 2x1500 A 30% 40% Jan-12 Engg. & civil works under progress.
c Moga (Aug.) 765/400 2x1500 A 40% 20% Jan-12 Award placed in Nov'09. Engg. & civil
works under progress.
6
a Bhiwani 765/400 2x1500 Part land
acquired
May-12 Award placed in Dec'09. Engg. in
progress. Delay in commencement of
works due to now availability of S/S
land. Now part land handed over &
work being started. Completion
expected by Mar'13.
7 Aug-10
a Bareilly (with 125 MVAR
Reactor)
765/400 2x1500 U A Apr-13 Award under progress.
Western Region
8 Jul-09
a Wardha 765/400 3x1500 A 88% 30% 15% Oct-12 Oct-12 Engg., supply & civil works under
progress.
765KV System for Central Part of Northern Grid -
PART-III
765KV System for Central Part of Northern Grid -
PART-II
Trans. System associated with Mundra Ultra Mega
Power Project
Transmission System for Phase-I
Generation Projects in ORISSA - Part - B.
Transmission System of Vindhyachal-IV and Rihand -
III (1000MW each) Gen. Proj.
Northern Regional System Strengthening
Scheme - XXI
pspm(cea) Sub Stns 2 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
9 Oct-08
a Satna 765/400 2x1000 A 90% 81% 4% Dec-12 Jun-13 Engg., supply & civil works under
progress.
a Indore 765/400 2x1500 A Dec-12 Dec-12 Award placed in Aug'10.
b Bina 765/400 2x1000 A 40% 80% 28% Dec-12 Dec-12 Engg., supply & civil works under
progress.
c Gwalior 765/400 2x1500 A Dec-12 Dec-12 Award placed in Aug'10.
10 Feb-09
a WR Pooling Station near Sipat 765/400 2x1500 A 72% 28% 13% Feb-12 Feb-12 Engg., civil works & erection in
progress.
11 Feb-09
a WR Pooling Station near Sipat
(3rd ICT)
765/400 1x1500 A 10% Feb-12 Feb-12 Engg. & supply under progress.
12
a Raigarh Pooling Station 765/400 4x1500 Aug-13
b Raipur Pooling Station 765/400 1x1500 Aug-13
Eastern Region
13 Sep-10
a Jharsuguda Pooling Station 765/400 2x1500 U A Mar-13 Award placed in Mar'11.
* Land acquisation critical.
b Angul Pooling Station 765/400 4x1500 U A Mar-13 Award placed in Mar'11.
* Land acquisation critical.
(b) State Sector
UTTAR PRADESH (UPPCL) :
Trans. System associated with Sasan Ultra Mega
Power Project
Establishment of Pooling Station at
Raigarh (Korba) and Raipur for IPP Gen.
Proj. in Chhatisgsrh
Part-B- Regional System Strengthening in WR for
Sasan
Western Region System Strengthening-XI
Part-A- Tr. System of Sasan(4000) UMPP
Transmission System for Phase-I
Generation Projects in ORISSA - Part - A.
Western Region System Strengthening-X
pspm(cea) Sub Stns 3 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
1 Unnao 765/400 2x1000 Mar-11 May-11 LOI issued on 23.01.2010.Work
awarded to M/s Crompton Greaves.
Soil testing completed.Foundation
work of Towers in Progress.
2 Anpara C 765/400 2x600 +
1000
Mar-11 May-11 Work awarded to Ms Areva. Soil
testing completed .Pile testing for soil
stablisation in ash dump yard area is
in progress.
3 Mainpuri 765/400 2x1000 May-12 May-12 Proposed under PPP mode
B 400/220kV Substations
(a) Central Sector
1
a Misa (2nd ICT) 400/220 315 A Feb-13 Feb-13 Awarded. Engg. in progres.
2 Feb-09
a Biswanath Chariyali Pooling
Station
400/132 2x200 U A Aug-13 Aug-13 Packages under tendering.
Completion affected due to delayed in
award (ant. in Mar'14)
b Aug. of 400KV Agra S/Stn. 400/220 4x105 A Aug-13 Aug-13 Completion matching with Gen.
NORTHERN REGION
3 Sep-07
a Part-I, GIS Pooling Station near
Chamera-II HEP
400/220 630 ACompleted Completed 95%
Yet to be
received
Mar-10 Aug-11 Testing & commissioning under
progress.
4 Feb-09
a Extn. Patiala (1x500) 400/220 500 A40% 80% 30%
Aug-11 Aug-11 Award placed in July'09. Engg. & civil
works under progress.
b Extn. Malerkotla (1x500) 400/220 500 Commissioned 3/11
5 Dec-09Northern Region System Strengthening-XXIII
Eastablishment of 400/220 kV GIS Pooling Station
near Chamera-II HEP
Part-A : North East - Northern/ Western
Interconnector -I
Northern Region System Strengthening-XIV
North East - NR/WR Inter - connector (Subansiri &
Kameng)
pspm(cea) Sub Stns 4 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
a Extn. Bahadurgarh 400/220 1x500 A 30% 30% Dec-11 Award placed in Mar'10.Engg. & civil
works under progress.
b Extn. Lucknow 400/220 1x500 A 40% 60% 20% Dec-11 Award placed in Mar'10. Engg. & civil
works under progress.
6 Feb-09
a Neemrana 400/220 2x315 A 10% 40% Nov-11 Feb-12 Engg. & civil works under progress.
Completion affectted due to delay in
land acquisation.
b Kotputli 400/220 2x315 U A Nov-11 Feb-12 Engg. in progress. Completion
delayed due to land acquisation (ant.
in Dec'12).
7 Feb-09
a Dehradun 400/220 2x315 U A Nov-11 Feb-13 Engg. in progress. Completion
delayed due to land acquisation (ant.
in Mar'13).
8 Feb-09
a Bagpat (GIS) 400/220 2x500 Feb-12 Mar-13 Engg. in progress. Completion
delayed due to land acquisation (ant.
in Mar'13).
9 Feb-09
a Manesar (GIS) 400/220 2x500 A 2% 10% Nov-11 Mar-12 Engg. & civil works under progress.
Completion matching with line.
10 Dec-09
a Sikar 400/220 2x315 A 40% 40% 10% Aug-12 Award placed in Mar'10. Civil works
under progress.
b Panchkula 400/220 2x315 30% 30% Aug-12 Award placed in Mar'10. Engg. in
progress. Civil works under progress.
11 Mar-10
a Sohawal 400/220 2x315 A 20% Nov-12 Award placed in Aug'10
Northern Region System Strengthening Scheme -
XV
Northern Region System Strengthening
Scheme - XVIII
System Strengthening in Northern Region
for SASAN & MUNDRA (UMPP)
Northern Region System Strengthening
Scheme - XIX
Northern Region Transmission
Strengthening Scheme
Northern Region System Strengthening Scheme -
XIII
pspm(cea) Sub Stns 5 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
b Shahajanpur 400/220 2x315 A 20% Nov-12 Award placed in Aug'10
c Saharanpur 400/220 2x315 U A Nov-12 Award placed in Nov'10
d Jind 400/220 2x315 U A Mar-13 Tendering under progress.
Land acquiation delayed . Section -6
awaited. State Govt. asking for
repeating Section-4 as one year
lapsed after Sec-4.
e Jaipur (South) 400/220 2x500 A 5% 20% Nov-12 Engg. & civil works under progress.
f Bhiwadi Extn. 400/220 1x315 A 10% Mar-13 Award placed in Nov'10
12 Jul-10
a Wanpoh 400/220 2x315 A Jul-13 Award placed in July'10. Engg. in
progress. Land hand-over in Dec'10.
13 Aug-10
a Hamirpur GIS (with 80 MVAR B.
Reactor)
400/220 2x315 U A Mar-13 Award placed in Nov'10. Engg. in
progress. Land acqusition to be
expedited.
14 Dec-10
a Samba (with 80 MVAR B.
Reactor)
400/220 2x315 U A Aug-13 Award under progress.
15 Nov-09
a Bhiwani 765/400 2x315 Part land
acquired
May-12 Award placed in Dec'09. Engg. in
progress. Delay in commencement of
works due to now availability of S/S
land. Now part land handed over &
work being started. Completion
expected by Mar'13.
WESTERN REGION
Northern Regional System Strengthening
Scheme - XXII
765KV System for Central Part of Northern Grid -
PART-III
Northern Regional System Strengthening
Scheme - XVI
Northern Regional System Strengthening
Scheme - XX
pspm(cea) Sub Stns 6 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
16 Dec-07
a Navi Mumbai (GIS) 400/220 630 A 95% 95% 50% Sep-10 Mar-13 Engg., supply, civil works & erection
under progress. Sub station to be
completed matching with commissioning
associated line.
17 Feb-08
a Wardha Extn. 400/220 315 A A A 85% Nov-10 Dec-11 Supply & erection under progress.
b Pune Extn. 400/220 315 A A A 98% Nov-10 Dec-11 Supply & erection under progress.
c Raipur Extn. 400/220 315 A Complected Complected 90% 80% Nov-10 Jun-11 Erection under progress.
18 Apr-08
a Shujalpur 400/220 630 A 95% 95% 78% Jan-11 Oct-11 Engg.,Supply ,civil works & erection in
progress
19 Oct-08
a Bachchau 400/220 630 A Complected Complected 75% 50% Oct-12 May-11 Efforts being made to prepone the
S/Stn. matching with Gen. proj.
b Navsari GIS 400/220 630 A 15% 80% 10% 80% Oct-12 Mar-12 Award placed in July'09. Engg. & civil
works under progress.
c Aurangabad 400/220 630 U A Oct-12 Oct-12 Tendering under progress.
SOUTHERN REGION
20 Kaiga 3 & 4 Trans. System Mar-05
a Kozhikode S/Stn. (2x315) 400/220 630 A Completed Completed Completed 95% Dec-07 Mar-13 Civil work & erection under progress.
Completion matching with line.
21 Kundankulam - APP
Transmission System (Balance
portion)
Mar-05
a Muvattapuzha ( 2nd Trf.) 400/220 315 A Completed Completed Completed 80% Nov-08 Mar-12 * Completion matching with line.
22 Mar-09
a Chulliar (Palakkad) 400/220 2x315 A 30% 70% 10% Jul-11 Feb-12 civil works under progress.
Transmission System Associated with Mundra Ultra
Mega Power Project
System Strenghthening -XI of SR
WESTERN REGION Strengthening Scheme-VI
WESTERN REGION Strengthening Scheme-IX
Western Region System Strengthening-V
pspm(cea) Sub Stns 7 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
23 Dec-09
a Bidadi (GIS) 400/220 2x500 A 70% 80% 10% Mar-12 Award placed in Dec'09.
Engg.,supply, civil works & erection
under progress.
24 Feb-10
a Yelahanka (GIS) 400/220 2x500 A 40% 20% Jun-12 Supply & Civil works under progress.
EASTERN REGION
25 May-10
a Kishanganj 400/220 2x315 U A Jan-13 Award placed in Jun'10. Engg. in
progress.* Land acquisation critical.
26 Jul-10
a Daltonganj 400/220 2x315 U A Nov-12 Tendering under progress.
Completion likely to be delayed (ant.
in Mar13). Land yet to be acquired.
b Bolangir 400/220 2x315 A Nov-12 Award placed in July'10.
c Kenonjhar 400/220 2x315 A Nov-12 Award placed in July'10.
d Chaibasa 400/220 2x315 U A Nov-12 Tendering under progress.
Completion likely to be delayed (ant.
in Mar13). Land yet to be acquired.
e Uttara 400/220 2x315 U A Nov-12 Tendering under progress.
Completion likely to be delayed (ant.
in Mar13). Land yet to be acquired.
f Lakhisarai 400/132 2x200 U A Nov-12 Award placed in Feb'11.Engg. In
progress.
g Banka 400/132 2x200 A Nov-12 Award placed in Feb'11.Engg. In
progress.
System Strengthening - XII of SR
Transmission System for Transfer of
Power from Generation Project in SIKKIM
to NR/WR Part - A.
System Strengthening - X of SR GRID
Eastern Region Strengthening Scheme -
III
pspm(cea) Sub Stns 8 of 21
Land
Acqusition
Civi works
completed
Structure,
transformer,
sub station
eqpt.received
Structure,
sub station
eqpt.erected
Transf.
erected&
tested
Original
Target
Date
Actual/ Now
Anticipated
date
1 2 3 4 5 6 7 8 9 10 11 12 13
Date of
Award
Cummulative progress till date CommissioningSl.
No.
RemarksName of the Sub-Station Voltage
ratio
(kV/kV)
Capacity
MW/MVA
27 Mar-11
a Rangpo (GIS) 400/220/
132KV
16x105
3x100
U A Nov-13 Tendering under progress.
28 Feb-10
a Silchar (New) 400/220 2x200 A 40% Mar-12 Work under progress.
(b) STATE SECTOR (SS)
NORTHERN REGION (NR) :
1 Harsh Vihar GIS 400/220 Dec-11
2 Loni S/S (2x315) 400/220 630 Dec-10 Sep-11 (i) Contract awarded on 31.3.2010 with
18 months completion period .Soil testing
done. (ii) Out of 80 hec.,60
hec.land has been accquired.
(iii) Boundary wall construction obstructed
by villagers
System Strengthening
1 Nawada 400/220 2x315 Mar-11 Jun-11
2 Nuhiawali 400/220 3x315 Jun-11 Aug-11 Purchase order placed to M/s GET