Top Banner
Status of ILC Activity in KEK H. Hayano, KE K APPI 03/10/2005
30

Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Jan 29, 2016

Download

Documents

Lorin Allison
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Status of ILC Activity in KEK

H. Hayano, KEK

APPI 03/10/2005

Page 2: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Official Time Schedule of ILC

2005.2 Decide the director and location of Central GDI2005. Establish Regional GDIs2005.8 Decide the design outline in Snowmass Workshop

(acc.gradient, 1 or 2 tunnel, dogbone/small DR, e+generation etc)

2005 end Complete CDR with rough cost/schedule2007 end Complete TDR, role of regions, start site selection2008 Decide the site, budget approval2009 Ground breaking2014 Commissioning starts

Page 3: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Asian Organization for ILC Research

● LC Office in JapanF. Takasaki, K. Yokoya, H. Hayano, N. Toge, S. Yamashita

● Working groups in Asian regionWG1 Overall design (K. Kubo)WG2 Main Linac (H. Hayano)WG3 Injectors (M. Kuriki)WG4 Beam Delivery System (T. Sanuki)WG5 HG Cavities (K. Saito)? Facility (A. Enomoto)? Site (R. Sugawara)

Page 4: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Critical Research Areas

● Establishment of the technology for acceleratinggradient 35MV/m

. Technologies for cost reduction

. Technologies for mass production

● Pursuit of possible higher accelerating gradient. Larger operational margin of gradient. Wider possibility of site selection

● Beam technology development using KEK-ATF. Unique storage ring to reach ILC emittance. Make full use of ATF capabilities

Page 5: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Guiding Principle Global Point of View

● Time line● Low cost design● Effective use of R&D budget by global coordination

Regional Point of View● Establish the leadership in leading areas● Promote industrial level

Time Scale● Snowmass issues (Aug.2005)● CDR issues (End of 2005)● TDR issues (End of 2007)

Page 6: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Development of 45MV/m High Gradient Cavity

● Single-cell test in Dec 2004 - Mar 2005● Individual vertical test of four 9-cell cavities by Sep.2005

. Just in time for CDR completion

. In existing facilities (AR east)

. If expected performance not obtained,⇒ change to slower plan for ILC 2nd stage

● Cryomodule test by end of 2006 ⇒ STF Phase 1● Industrial design by TDR

Page 7: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Superconducting RF Test Facility Comprehensive Test Facility dedicated to ILC SC-RF R&D

1. Superconducting Cavity; fabrication, surface treatment, installation, vertical test / horizontal test, system test with beam

2. Cryomodule; cavity installation, alignment, cryostat operation, heat cycle test, input coupler R&D, tuner mechanism R&D

3. Power source; modulator development, klystron development, WG components

4. He plant; High efficiency cryogenic system

5. Beam Instrumentation; ILC beam generation, BPM, HOM, Low-Level RF control

6. Cavity Surface Treatment Facility; BCP, CP, EP, HPR, clean room

Page 8: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Location of Test Facilities

ATF

L-band R&D Stand

STF

#4 building

KEK-BHe Plant Control Center

1) 60m x 30m building: Klystron Gallery (with extendable space) Cavity installation room magnet power supply room (with extendable space) Control room (with extendable space) Cooling water facility AC power yard external Tent House

2) 5m x 3.85m x 93.5m tunnel: Access hatch only 2m x 4.5m with elevator (with extendable space)

JPARC Proton Linac BuildingWill be empty in August 2005Then, STF construction.

Page 9: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Purpose of STF

● Establish industrial design of Linac unit (35MV/m and 45MV/m)

● Promote Asian/Japanese industrial level for ILC component production

● Form Asian base for international collaboration

● Enlist/educate new comers

Page 10: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Klystron Gallery

Page 11: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Tunnel underground

Page 12: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.
Page 13: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

STF Phase 1 (2005-2006)

● Cryomodule for 4 45MV/m cavities ● Cryomodule for 4 35MV/m cavities ● RF source and cryogenic system (mostly recycled) ● Electron beam and its diagnostics system ● Synthetic test of 35MV/m & 45MV/m cryomodules with beam

Other items in parallel ● Electro-polishing Facility . Can electro-polish cavities to be used overseas ● Cost reduction of cavity fabrication (Nb/Cu-clad, seamless)

Page 14: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

STF Test Accelerator-------- phase 1 ------------------------ (RF gun): (1.3GHz 1.5cell copper cavity 42MV/m, 3.2nC/bunch 3.2MW, 1ms klystron, 5Hz)

DC gun : DC 200kV CsTe photocathode for quick start + UV(262nm) Laser (337ns spacing, 2820bunches)

Test Cryomodule : 4x 9cell TESLA SC cavity (5m cryomodule), 35MV/m        4x 9cell LL SC cavity (5m cryomodule), 45MV/m     4x 350kW + 4x 450kW = 3.2MW, 1.5ms klystron, 5Hz

Beam analyzer: energy analyzer, emittance, BPM

-------- phase 2 ------------------------Accelerating Unit : 3 set of 17m full-size (12 cavities) cryomodule 2x 10MW, 1.5ms klystron, 5Hz

Page 15: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

STF Infra-structureEP: build new EP(Electro chemical Polishing) facility

HPR : move High Pressure Rinse from L-band test stand

Clean room : build new clean room for cavity assemble

Vertical Test Stand : build new stand, deep enough for superstructure cavity

Coupler Test Stand : 5MW, 1.5ms klystron, 5Hz (switch use between Test Cryomodule )

He Plant : 600W at 4K plant moving from AR-East building (adding new 2K system )

Page 16: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Conceptual design of cryomodule

35MV/m TESLA design cavities

45MV/m Low-loss cavities

Weld connection

Valve Box STF Phase 1Why two module and connection? ->5m carry hatch, ->Establish weld connection in tunnel.

Become to 8 cavities in one cryostatLike TTF cryomodule

Page 17: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

DESY

Page 18: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Preliminary design of cryomodule   whole assembly

35MV/m TESLA design cavities 45MV/m Low-loss cavities

Single cryostat operation (option)

Page 19: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

Cryomodule Cryostat Design

KEK cryomodule cross-section Design is underway

Page 20: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

STF Modulator, klystron plan1. Buy 5MW Thales Klystron, Build Pulse trans, Modify PNC Modulator putting bouncer circuit in it.

2. Build one more modulator (ILC spec.) for cavity driving (in 2006). start investigation of technology for bouncer modulator/IGBT modulator.

For driving cavities & Input coupler Test stand, later for RF-gun.

Additional PT+Bouncer circuit allows to use TH2104C.

PNC modulator TH2104C

Page 21: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

STF Phase 1 Beam Line Plan

Page 22: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.
Page 23: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

STF Phase 2 (2007-2009)

● 3 Cryomodules each containing 12 caviries (35 or 45MV/m)

● Reinforcement of RF and cryogenic systems

● Synthetic test with a beam

Many uncertainties for Phase 2 ● GDI will be functional by the time of detail design of Phase 2 ● Collaboration/competition with TTF2/SMTF ● A few full-spec RF unit needed for TDR somewhere in the world

● STF Phase 2 is desired for Asian industrial level

Page 24: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

ILC CryomoduleILC Cryomodule

1m dia. Cryostat(17m length),12 of 9-cell SC Cavities

Page 25: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

ILC Multi-Beam Klystron

Page 26: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

ATF● Beam dynamics study (Fast ion instability, wiggler, etc)● Development of diagnostics devices (Laser wire, cavity BPM etc.)● Improvements of extracted beam (coupling, stabilization)● Development and test of fast extraction kicker

Extension of ATF Extraction Line : ATF2 (A) Small beam size (A1) Obtain σy ∼35nm (A2) Maintain for long time (B) Stabilization of beam center (B1) Down to < 2nm by nanoBPM (cavity BPM) (B2) Bunch-to-bunch feedback of ILC-type beam (∼300ns interval)

Page 27: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

ATF

ATF emittance goal was set toX emit=2.5E-6( at 0 intensity)Y emit=2.5E-8( at 0 intensity) 1% from X

Mission: generation&confirmation of LC low emittance e- beam

Page 28: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

ATF2 : final focus beam line

Line 1 or Line 2 (depend on movement plan of existing facility)

ATF DR

Page 29: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

International Collaboration on ATF2

● Design study going on by international collaboration . Mini-workshops: Dec.11 at KEK, Jan. 5 at SLAC . Completion of optics design in ∼ March

● Budget . Total 2.8 Oku Yen (floor, beamline, diagnostics) . Desirable to share the expenses among Asia, North America, Europe

● Present plan . Floor construction in summer 2006 . Start operation in Jan. 2007

Page 30: Status of ILC Activity in KEK H. Hayano, KEK APPI 03/10/2005.

END