Republic of the Philipp DEPARTMENT OF AGRICULT Regional Field Office City of San Fernando, Pam STATEMENT OF WORK ACCOMPL As of _____________________ Name of Project : Supply of Labor and Materials for the Construction of One (1) Unit Working Shed Location : ROS - PARAISO, TARLAC CITY Subject : FINAL BILLING Contractor : C.J. CAYABYAB BAMBOO WORKS Item No. Description % Wt % Accomplishme Previous To Date 1 Roofing 20,950.00 69.83% - 69.83% 2 Painting 850.00 2.83% - 2.83% 3 Labor Cost 6,240.00 20.80% - 20.80% 4 tax 1,960.00 6.53% - 6.53% 5 - - - - - 6 - - - - - Total Project Cost 30,000.00 100.00% - 100.00% Prepared by: Recommending Approval: ENGR. CESARIO P. BALINGIT ORLINO A. MERCADO, Ph. Sr. Agriculturist Chief, Research Conforme: JOEL BRIAN C.J. CAYABYAB BAMBOO WORKS Contractor Contract Amount (Php)
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Construction of One (1) Unit Working Shed (6m x 4m) for Organic GardenLocation : ROS - PARAISO, TARLAC CITYSubject : FINAL BILLINGContractor : C.J. CAYABYAB BAMBOO WORKS
ENGR. CESARIO P. BALINGIT ORLINO A. MERCADO, Ph.D.Sr. Agriculturist Chief, Research
Conforme:
JOEL BRIANC.J. CAYABYAB BAMBOO WORKS
Contractor
Contract Amount (Php)
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : DESILTING OF SMALL FARM RESERVOIR(SFR) @ SCION GROVELocation : ROS - PARAISO, TARLAC CITYSubject : FINAL BILLINGContractor : Malta Construction & Supply
Item No. Description % Wt
I Mobilization 9,095.00 2.5% 2.5% 9,095.00II Clearing and Grubbing 2,568.00 0.71% 0.71% 2,568.00III Excavation / Desilting 279,485.71 77.05% 61.64% 223,576.22IV Compaction & Shaping of Dike 60,084.25 16.57% 8.28% 30,032.63V Hauling / Spreading 11,479.92 3.17% 1.58% 5,730.86
Total Project Cost 362,712.88 100.00% 74.71% 271,002.71
Conforme:
TOMAS P. MULDONG JR.MALTA Construction & Supply
Contractor
Contract Amount (Php)
% Accomplishment Previously Paid
Amount Prev. Paid (PhP)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Proposed Construction of Pavement and CanalizationLocation : ROS - Botolan, ZambalesSubject : FINAL BILLINGContractor : Bancal Construction and Supply
Previous To Date Coll. PreviousI Earthworks, Clearing and Excavation 2,140.00 3.15% 0 100.00% 100.00% 0II Backfill with 15% compaction 1,926.00 2.83% 0 100.00% 100.00% 0III Concrete and Masonry works 42,023.90 61.82% 0 100.00% 100.00% 0IV Reinforcement Bars 12,447.04 18.31% 0 100.00% 100.00% 0V Steel Works 9,436.87 13.88% 0 100.00% 100.00% 0
Total Project Cost 67,973.81 100.00% 0 100.00% 100.00%
Conforme:
JOEL M. BUTARANBANCAL Construction and Supply
Contractor
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Excavation/Concreting and Construction of Garage and Parking Area near Guest houseLocation : ROS - Botolan, Zambales
Subject : FINAL BILLINGContractor : Bancal Construction and Supply
Previous To Date Coll. PreviousI Earthworks 21,774.50 7.64% 0 100.00% 100.00% 0II Concrete Works 78,198.28 27.43% 0 100.00% 100.00% 0III Reinforcements 36,147.01 12.68% 0 100.00% 100.00% 0
IV Tinsmitry144,720.71 50.76%
0100.00% 100.00%
0
V Paintings 4,245.76 1.49% 0 100.00% 100.00% 0
Total Project Cost 285,086.25 100.00% 0.00% 100% 100% 0
Conforme:
TOMAS P. MULDONG JR.MALTA Construction & Supply
Contractor
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Concreting of Road from Admin building to farm house and Gravel roads from farm house to diversion dam to Vermi bed shedLocation : ROS - Magalang, Pampanga
Subject : FINAL BILLINGContractor : P.V.B. Construction and Trading
ANDREW B. VILLACORTA, DVM, CESO IVRegional Executive Director
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of JULY 5, 2013
% Weight Accomplishment Amount Collectible (Php)To Date Coll. Previous To Date Coll.22.52% 22.52% 0 2,500.00 2,500.0077.48% 77.48% 0 8,600.00 8,600.00
100.00% 100.00% 0.00 11,100.00 11,100.00
Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Approved By:
ANDREW B. VILLACORTA, DVM, CESO IVRegional Executive Director
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Repair of Admin Building Damaged Conference Room Roofing Location : ROS - Botolan, ZambalesSubject : FINAL BILLINGContractor : Bancal Construction and Supply
Previous To Date Coll. Previous1 Distmantling of Roofing and Ceiling Board 3,210.00 7.53% 0 100.00% 100.00% 02 Roofing and Ceiling Board 39,439.13 92.47% 0 100.00% 100.00% 0
Total Project Cost 42,649.13 100.00% 0 100.00% 100.00%
Conforme:
JOEL M. BUTARANBANCAL Construction and Supply
Contractor
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Provision of Perimeter fence for GoathouseLocation : ROS - Botolan, ZambalesSubject : FINAL BILLINGContractor : Bancal Construction and Supply
Total Project Cost 102,495.73 100.00% 0.00% 100% 100% 0
Conforme:
TOMAS P. MULDONG JR.MALTA Construction & Supply
Contractor
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHED
Name of Project : PROPOSED EXTENSION OF TIRE PATH GOING TO GATE 3Location : ROS - PARAISO, TARLACSubject : FINAL BILLINGContractor : B.G. GIRON CONSTRUCTION AND SUPPLY
ANDREW B. VILLACORTA, DVM, CESO IVRegional Executive Director
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Improvement of One unit Guardhouse and two units guard postsLocation : ROS - Magalang, PampangaSubject : FINAL BILLINGContractor : R&M Vilaa Garcia Builders Co.
Previous To Date Coll. PreviousGuardhouse 3,210.00 7.53% 0 100.00% 100.00% 0
1 Clearing 39,439.13 92.47% 0 100.00% 100.00% 0
Total Project Cost 42,649.13 100.00% 0 100.00% 100.00%
Conforme:
JOEL M. BUTARANBANCAL Construction and Supply
Contractor
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Provision of Perimeter fence for GoathouseLocation : ROS - Botolan, ZambalesSubject : FINAL BILLINGContractor : Bancal Construction and Supply
Total Project Cost 102,495.73 100.00% 0.00% 100% 100% 0
Conforme:
TOMAS P. MULDONG JR.MALTA Construction & Supply
Contractor
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHED
Name of Project : PROPOSED EXTENSION OF TIRE PATH GOING TO GATE 3Location : ROS - PARAISO, TARLACSubject : FINAL BILLINGContractor : B.G. GIRON CONSTRUCTION AND SUPPLY
Total Project Cost 1,526,111.98 100.00% 0 100.00% 100.00%
Conforme:
B.G. GIRON CONSTRUCTION AND SUPPLYContractor
As of NOVEMBER 15, 2012
Contract Amount (Php)
NELSON T. NUCUMTechnical Staff / ENG'G SECT.
ENGR. SABINO V. MACARAIGBuilding & Structure Coordinator
ENGR. CESARIO P. BALINGITAgri Infra Dev't Coordinator
Checked By:Prepared By: Recommending Approval:
ENGR. ABRAHAM C. MOLINAChief - RAED
Republic of the PhilippinesDEPARTMENT OF AGRICULTURE
Regional Field Office IIICity of San Fernando, Pampanga
STATEMENT OF WORK ACCOMPLISHEDAs of _____________________________
Name of Project : Supply of Labor and Materials for the Improvement of One unit Guardhouse and two units guard postsLocation : ROS - Magalang, Pampanga
Subject : FINAL BILLINGContractor : R&M Villa Garcia Builders Co.