Start up and Commissioning of Pipelines IiPM, Gurgaon 10 th July 2009 Presentation by D. S. Nanaware, Chief Project Manager, IOCL, Noida
Dec 22, 2015
Start up and Commissioning of Pipelines
IiPM, Gurgaon 10th July 2009
Presentation by
D. S. Nanaware,
Chief Project Manager, IOCL, Noida
10th July 2009 IiPM, Gurgaon 2
Methodology for Pre-commissioning of new pipelines
Objectives Task Forces Responsibility of Project/Construction
Group Responsibility of O& M Group Responsibility of Fire & Safety Group Documentation
Commissioning
Handing/Taking Over Case Study
Contents
10th July 2009 IiPM, Gurgaon 4
Preparation of pre-commissioning and commissioning plan
Safe commissioning of pipeline system
Safe and smooth operation of pipeline after commissioning
Proper handing over & taking over of pipeline system
Preparation of check list for all pending activities
Liquidation of check list points in a time bound manner
Objectives
10th July 2009 IiPM, Gurgaon 5
Task Forces
For efficient startup/commissioning specialized task-force can be formed including specialists from:
Projects/Construction Group
Operations & Maintenance Group
Fire & Safety Group
10th July 2009 IiPM, Gurgaon 6
Responsibility of Projects/Construction Group
The group will ensure:
Mechanical completion of pipeline system
Hydro-testing and pigging of entire pipeline
Inertization of pipeline
Ensuring readiness of pipeline system for commissioning
Handing over of pipeline system (including spares, tools, equipment etc) for operation
Handing over of relevant documents and certificates to O&M group
10th July 2009 IiPM, Gurgaon 7
Responsibility of O&M Group
The O&M group will ensure:
Verification and taking over of all contract, project and operation related documents before pre commissioning activities
All checks for ensuring system integrity and functionality
Verification of all statutory permissions
Verification of relevant inspection reports and certificates etc.
Verification of vender’s documents for material supply
10th July 2009 IiPM, Gurgaon 8
Responsibility of O&M Representative (contd..)
Verification of agreements and MOUs with product suppliers and consumers
Preparation of check list with target completion dates for all contracts works and material POs
Enlisting of all construction surplus materials, and equipment with all relevant inspection, test certificates and other documents
Ensure preparation of check list for balance jobs
Verification and taking over the project DFR, concept note and project approvals etc
10th July 2009 IiPM, Gurgaon 9
Responsibility of Fire & Safety Representative
Verification of Fire network and equipments as per relevant OISD standards
Check the adequacy of first aid fire fighting appliance as OISD Std. 117
Ensuring placement of fire fighting equipments/instruments as per OISD Std. 117
Check the compliance of safety audits, OISD audits and Pre-commissioning audits
Check the integrity of fire fighting system before start up and commissioning
10th July 2009 IiPM, Gurgaon 10
Documentation
The O&M Documentation In-charge shall take over and ensure proper distribution of documents related to:
A. Statutory clearances/Permissions
Factory License as per factory act 1948
State Pollution Control Board and Ministry of Environment & Forests (MoEF) clearances
State & Central Electricity Authority Permissions (wherever required)
Clearance for frequency in case of Radio set, Walky-Talky/VHF /UHF
Clearance from CCOE
10th July 2009 IiPM, Gurgaon 11
Documentation
A. Statutory clearances/Permissions (contd..)
Permissions/Agreements executed for Railways, Road (NH & SH), Canal, OFC and any other crossings
Authorization for hazardous waste rule (Management & handling - 1989)
B. Revenue and RoU related documents
Detailed RoU Survey Reports with Survey Numbers
Tree & Crop compensation details and documents
Land acquisition documents, ROU Cadastral Map
Field management books (FMBs)
List of disputes / pending complains with detail status
10th July 2009 IiPM, Gurgaon 12
Documentation
C. Construction Related Documents Mechanical Completion Certificate
Hydro testing acceptance certificates
Equipments Commissioning Certificate with commissioning history
Work order copies and Contracts
Construction QA/QC records, Procedures and inspection records
Radiography films and records
MOUs and agreements with product suppliers and consumers (Copies)
10th July 2009 IiPM, Gurgaon 13
Documentation
C. Construction Related Documents (contd..)
Agreements with contractors, venders, material / Equipment suppliers
All taxes and duties statements
SAT (Site acceptance Test) of all instruments including certificates and loop
testing certificates
Process Flow Diagram
As-build drawings such as plot plan, cable route drawing, earthing and P&ID etc.
10th July 2009 IiPM, Gurgaon 15
Commissioning is to bring the constructed / installed system to deliver the desired function.
Pipeline commissioning means introducing crude/ product/Gas in the pipeline from originating station, filling the entire length and then start delivering to the planned receipt system.
In case of crude pipeline, there may be intermediate storage stations for operational requirement but ultimate supply is to be made to a refinery
In case of product pipeline/Gas pipeline, there may be several intermediate delivery stations before terminal/dispatch station.
Objective of Commissioning
10th July 2009 IiPM, Gurgaon 16
Preparation of commissioning manual
A document describing the procedure to be followed for commissioning is to be prepared by experienced persons
The purpose of making the document is to set forth the objectives of commissioning of pipeline system and to establish guidelines for safe commissioning in order to achieve the required goals.
Pre-commissioning check list
A check list is prepared, which covers the technical, safety as well as statutory requirement before the pipeline and associated facilities is declared ready for commissioning.
Pre-commissioning
10th July 2009 IiPM, Gurgaon 17
Constituting a pre-commissioning team: A committee of experienced engineers is constituted to
audit the construction as per pre-commissioning check list and report to the management regarding readiness of the system or any shortcomings to be complied before commissioning.
Procurement of consumable/tools/pigs etc: As mentioned in the Commissioning Manual, required
consumables, tools, pigs, spares and safety equipments are to be made available prior to commissioning.
Availability of product/ crude: As per line fill calculation, the availability of crude oil or the
product, as the case may be, is to be ensured at originating / pumping station in coordination with Refinery and Marketing.
Pre-commissioning (contd..)
10th July 2009 IiPM, Gurgaon 18
Pipeline sections are generally commissioned in phased
manner / in totality based on the situation and
preparedness.
After hydro-testing and caliper pigging it is expected that
the sections are in a fairly clean condition.
Commissioning
10th July 2009 IiPM, Gurgaon 19
Constituting a commissioning team:
A committee of experienced engineers is constituted to perform the objective of commissioning.
Scrutiny of audited pre-commissioning check list:The committee to ensure the compliance of any shortcomings reported in the pre-commissioning check list.
Identification and deployment of manpower
at new stations
Deployment of security personnel at stations
Arrangement of water and disposal plan
Commissioning action plan
10th July 2009 IiPM, Gurgaon 20
Pressurization of pipeline section with compressed air up to 3-5 Kg/sq cm.
Injection of about 500 to 1000 KL water into the section from launching barrel end
Launching of cleaning (bi-di) pig after introduction of water in the line
Maintaining 5-10 kg/sq.Cm back pressure at other end by venting the air
Introducing about 1000 to 3000 KL of water behind the cleaning pig
Launching batching (bi-di) pig
Commissioning steps
10th July 2009 IiPM, Gurgaon 21
Introducing HSD / Crude in the line and maintaining 5 to 10 Kg/sq.cm back pressure at other end.
Draining dirty water to storm water drain / pre-fixed drain outlet at the receiving end
Receiving cleaning pig
Again draining dirty water to storm water drain
Receiving batching pig
Lining up marketing HSD receipt tank /Refinery or Pipeline crude receipt tank
Flow to be diverted to HSD / Crude receipt tank as soon as oil traces are observed. Temporary facility for water draining to be dismantled & permanent blinding put
Commissioning steps (contd..)
10th July 2009 IiPM, Gurgaon 22
Since, before pumping water, line is filled with air at a pre-determined pressure, so monitoring and air draining facility is kept ready at receiving end to maintain back pressure of air at 5 to 10 Kg/sq.cm
Pumping into an empty line will cause excessive flow rate & current in the motors resulting in frequent tripping. May result in increase of interface length.
As the pig reaches at receiving end, it is taken out. The muck & dirt quantity is collected and after analysis it is disposed off.
Handing over the system to operating group
Commissioning steps (contd..)
10th July 2009 IiPM, Gurgaon 23
Specific check points/procedure for
Gas Pipelines
LPG Pipelines
ATF Pipelines
Commissioning steps (contd..)
10th July 2009 IiPM, Gurgaon 24
HANDING / TAKING OVER FORMAT
NAME OF PROJECT : ______________________
LOCATION : ______________________
PROJECT IDENTIFICATION : ______________________
PROJECT COST : ______________________
PMC : ______________________
CONTRACTOR : ______________________
DATE OF COMMISSIONING : ______________________
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 25
I. DETAILS OF FACILITIES TO BE HANDED OVER
1. _____ INCH DIA. P/L FROM _______ TO ______ (ALONGWITH OFC)
HAVING DESIGNED CAPACITY OF ______ MMT/MMSCMD AT PRESSURE
_________KG/CM
2. ORIGINAL/DISPATCH TERMINAL/ STATION AT : ______________________
3. RECEIVING TERMINAL AT : ______________________
4. SV/IP STATIONS ALONG PIPELINE AT : ______________________
5. ANY OTHER FACILITIES (IF APPLICABLE) : ______________________
6. HDD (IF ANY) DETAIL : _____________________
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 26
II. IMPORTANT PARAMETERS AND DATES
1. MECHANICAL COMPLETION DATE OF MAIN LINE WORKS: __________
2. PIGGING (FOAM, GAUGE, CLEANING PIG & EGP) : __________
3. HYDRO — TEST & DESIGN PRESSURE OF MAIN LINE : __________
4. MECHANICAL COMPLETION DATE OF RECEIVING :
__________
& ORIGINATING TERMINALS
5. INSTRUMENTATION COMPLETION DATE : __________
OF TERMINAL STATION
6. COMMUNICATION SYSTEM COMPLETION DATE : __________
7. SCADA AND TELEMETRY COMMISSIONING DATE : __________
8. DATE FOR PRODUCT/GAS CHARGING IN THE SYSTEM : __________
9. FINAL DATE OF COMMISSIONING : __________
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 27
III. STATUS OF SYSTEMS / FACILITIES TO BE RECORDED BEFORE TAKING OVER
(A) Pipeline & CP
1. Status of ROU, CP test points and Markers OK/ Not OK
2. Checking of mainline & by—pass line valves & Actuator OK / Not OK
3. Physical Status of SV/IP, receiving & Pump stations OK / Not OK
4. Performance test of SVs/IP station Done / Not Done
5. Checking of casing shorting at crossings. Done / Not Done
6. Status of Temporary CP Removed./ Not
Rmd
7. Status of captive power system Comm / Not
comm.
with battery bank (wherever applicable)
8. if pipeline is not charged, is it dried & filled with inert gas Yes / No
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 28
(B) COMMUNICATION & SCADA
1. Status of communication system Comm / Not comm.
2. OFC Checking Done/Not Done
3. Status of SCADA and telemetry system Comm / Not
comm.
(If applicable)
4. Communication between the RTU OK/ Not OK
at maintenance bases
5. Communication between the flow OK/ Not OK
computers to RTU/SCADA for Master Control Centre
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 29
(C) INSTRUMENTATION & METERING
1. Status of metering systems (If applicable) Yes/NO
2. Checking of Instrumentation Panel (If Applicable) Comm/Not
comm.
3. Status of Chromatographs (If applicable) Done / Not
Done
4. Status of Instruments at SVs/RRs/IPs comm/Not
comm.
5. Remote operation of Valves at SVs & Terminals. OK/NOTOK
6. Status of UPS Comm. /Not
comm.
(D) ELECTRICAL SYSTEM
1. Checking of Electrical Panel & battery backup (If Applicable) Comm/Not comm
2. Electricity at terminals/distribution stations from S.E. Board OK/NOTOK
3. Earthings system Comm/Not comm.
3. Lighting Comm/Not comm.
4. Lightening Protection System OK/NOTOK
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 30
(E) FIRE & SAFETY
1. Status of Fire fighting Systems OK / Not OK
2. Status of fire detection system at SVs/RRs/lPs & Terminals Comm/Not comm.
3. Status of on line extinguishing system at SVs/RRs/lPs Comm./Not comm.
4. Safety audit by Fire & Safety personal from O&M Done/ Not Done
(F) GENERAL
1. Status Control Buildings Construction Comp./Not Comp.
2. Status of basic amenities for security guards at the Done / Not Done
permanent establishment
(Security rest room, water, lighting arrangement)
3. Preparation of final checklist before taking over Done / Not Done
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 31
(G) DOCUMENTATION
1. Listing & handing over of all procedures, reports, Done / Not Done
certificates, vender manuals, drawings and
related documents which are to be handed
over as per Contractual obligation with the venders
2. Listing & handing over of “As builds”, Alignment Done / Not
Done
sheet, hydro test report, Pigging report,
pipeline route map, pipe book, crossing
details (Hard copy & soft copy)
3. Revenue records & records for permanent land acquisition Done! Not
Done
4. Certificates related to Metering system Done I Not
Done
(H) SPARES
1. Commissioning spares Handed over/not handed over
2. Two years spares Handed over/not handed over
Handing/Taking Over
10th July 2009 IiPM, Gurgaon 32
Case Study: Commissioning of SSPL
Name of Pipeline : Sidhpur- Sanganer Pipeline
Length : 517 km
Pipe Size & Thickness: 18’ OD x 0.250” WT
Pipe Grade : API 5L-X65
Capacity : 3.4 MMTPA (5.7 Max)
MAOP : 92 Kg/cm2
Line fill : 79840 Kl Sidhpur - Kot : 28500 Kl
Kot - Baghsuri : 30500 Kl
Baghsuri - Sanganer : 20840 Kl