Top Banner
S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon Thursday, August 9, 2012 6 p.m. Jennings County High School
35

S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon

Feb 25, 2016

Download

Documents

frisco

S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon Thursday, August 9, 2012 6 p.m. Jennings County High School. Meeting Format Purpose of Meeting Informal Q & A in project display area with project engineers and INDOT project officials Information Packet. Welcome. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon

Thursday, August 9, 20126 p.m.

Jennings County High School

Page 2: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Welcome

Meeting Format Purpose of Meeting Informal Q & A in project display area with

project engineers and INDOT project officials Information Packet

Page 3: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project in North Vernon Introduction of INDOT Project Officials Design Consultant Team Recognition of Elected Public Officials

Page 4: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Project Stakeholders Indiana Department of Transportation Indiana Division Federal Highways Administration Jennings County City of North Vernon Local communities Elected Public Officials Community residents and citizens Commuters Schools Neighborhoods

Page 5: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Public Hearing Legal Notice of Public Hearing was published in

the North Vernon Plain Dealer and the North Vernon Sun on the following dates:

Tuesday, July 24, 2012 & Thursday, July 26, 2012 Tuesday, July 31, 2012 & Thursday, August 2, 2012

Copies of the legal notice were mailed to property owners and project stakeholders on the projectmailing list

Announcements were posted to the INDOT website and weekly public involvement list serve

Project mailing list will be updated following the public hearing, please sign in during the hearing

Project documents available for viewing at local repositories

Page 6: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Purposes of Hearing Introduce this project to the community Discuss purpose and need for project Present a preliminary proposal for

consideration Solicit input from the community Discuss public involvement for project Address questions & concerns

Page 7: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Project Development Process

We Are Herepublic

meeting June 2011

Page 8: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Environmental Document

Requirement of the National Environmental Policy Act (NEPA): Requires INDOT to analyze and evaluate the

impacts of a proposed project to the natural and socio-economic environments

Impacts are described in environmental document

Environmental document was released for public involvement last month and is anticipated to be approved later this summer

Page 9: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Environmental Document Development of document begins once purpose

of need for the project has been clearly identified Develop a number of possible alternatives

including a “Do Nothing” alternative as a baseline for comparison

Screen alternatives to identify a preferred alternative

Solicit public comment on environmental document and preliminary design plan

Solicit, address, and fully consider public comments as part of decision making process

Page 10: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Elements of the Environmental Documentation

Page 11: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 / South State Street Map

Page 12: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project Purpose and Need

S.R. 3 is currently a two lane facility Posted Speed Limit is 30 mph Traffic volumes:

2013 – 12,710 v.p.d. with 4% Trucks 2033 – 15,110 v.p.d.

Page 13: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project Purpose and Need Enhance safety within the project corridor

Property damage-only crashes are twice that of the statewide average for similar facility

Sight distance restricted along inside of curve Lack of defined entrance/exit points in curve area

Replace deteriorating pavement between David Drive and Chestnut Street Improve drainage control along project with curb and

gutter and storm sewer City of North Vernon to replace sanitary sewer main

Page 14: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project Alternatives No action / Do nothing alternative Jennings County EMS to Greensburg Street

Add two-way left turn lane (TWLTL) Extend sidewalk to Jennings County EMS Mill and overlay existing pavement New storm sewer system

Jennings County EMS to US 50 Includes above alternative Option to replace pavement from David Drive

to US 50

Page 15: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project Alternatives South of Mascatatuck County Park to US 50

Includes above alternatives Adds northbound passing blister at

county park entrance Extends sidewalk to Jennings County EMS

South of Mascatatuck County Park to US 50 Includes above alternatives Extends sidewalk to county park

Page 16: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project OverviewJennings County EMS to Meloy Street

Page 17: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project OverviewNorth of Meloy Street to Chestnut Street

Page 18: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Project Description Project limits – Jennings County EMS

to Chestnut Street Add a two way left turn lane (TWLTL) Resurface or replace pavement Include curb and gutter with storm sewer Sidewalk will be added,

replaced or left in place Sidewalk location will not be

any closer to most front doors State Street Historic District –

Jefferson St. to Chestnut St.

Page 19: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 / South State Street (existing) Jennings County EMS to David Drive

Two 12 ft travel lanes 10 ft paved shoulders

David Drive to Chestnut Street Two 16 ft travel lanes No shoulders

Jennings County EMS to Chestnut Street 4 ft sidewalk along most of the project 6 ft to 20 ft grass buffer separates sidewalk

from edge of pavement along project

Page 20: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 / South State Street (proposed)

North of Smith Street to David Drive Resurface existing pavement Two 12 ft travel lanes 14 ft two-way left turn lane Curb and gutter

David Drive to Chestnut Street Replace existing pavement Two 12 ft travel lanes 11 ft two-way left turn lane Curb and gutter

Page 21: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 / South State Street (proposed)

Sidewalk Existing sidewalk to remain in place on both

sides of S.R. 3 from Jefferson Street to Chestnut Street

New/replaced sidewalk will be 6 feet wide and adjacent to curb and gutter

Sidewalk will be extended to Jennings County EMS

Page 22: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 / South State Street (proposed)

Miscellaneous Construction Items Steps and walks affected by road construction will be replaced 15 street approaches 47 drives Storm sewer outlets SE

of Meloy Street and SWof grocery store

$2.8 million estimatedconstruction cost

Page 23: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Maintenance of Traffic

No Detour Open to through traffic during construction Two major phases for construction

Page 24: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Maintenance of Traffic

Advance work construction activities: Construct storm sewer outlets Widen existing pavement along the east side

of the road Phase I major construction activities:

Construct west half of roadway: Pavement Curb and gutter Sidewalk Driveway and street approaches Storm sewers

Page 25: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Maintenance of Traffic

Phase II major construction activities: Construct east half of roadway

Pavement Curb and gutter Sidewalk Driveway and street approaches Storm sewer Sanitary sewer

Page 26: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

S.R. 3 Maintenance of Traffic

Post Phase II construction activities: Pavement surface course Signs Pavement markings

Page 27: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Real Estate Acquisition Process

Page 28: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Real Estate Acquisition Process

INDOT Representatives available to discuss procedures

How Land Is Purchased Explains the process of buying property

needed for highway improvements

Page 29: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Real Estate Acquisition Process “Uniform Act” of 1970:

All federal, state, and local governments must comply

Requires an offer for just compensation Acquisition Process:

Appraisals Review Appraisals Negotiations

Page 30: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Project Schedule Public Information Meeting (June 2011) Design / Environmental Documentation (2011-

2012) Public Hearing (August 2012) Project Letting (December 2012) Anticipated Construction to begin (Spring 2013) Anticipated project completion (Fall 2013)

Page 31: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

INDOT Would Like to Hear from You Talk with INDOT project team members Comment sheet in information packet E-mail or Mail comments to INDOT Sign-in sheet to be added to project

mailing list Visit INDOT website at: www.in.gov/indot All comments are very much appreciated

and will be given full consideration by project team

Page 32: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Stay Informed by Receiving Updates Sign-in at attendance table to be added to

project mailing list A meeting invitation was mailed to known

property owners within project area Announcement of this meeting was posted

to INDOT website. A media release was also issued

INDOT website at: www.in.gov/indot

Page 33: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Project Resource Location Seymour District Office, 185 Agrico Lane in

Seymour Responsible for transportation construction,

maintenance and project development activities in Eastern / Southeastern Indiana

[email protected] 1-877-305-7611

Kathy Eaton-McKalip, District Deputy Commissioner Glenda Seal, Customer Service Center Danny Pearcy, Project Manager

Page 34: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Public Involvement Team

Rickie Clark, INDOT Office of Public Involvement(317) 232-6601 [email protected]

Glenda Seal, INDOT Seymour District Customer Service Manager 877-305-7611 [email protected]

Danny Pearcy, Project Manager, INDOT Seymour District Office 877-305-7611 [email protected]

INDOT website at www.in.gov/indot/2366.htm

Page 35: S.R. 3 / South State Street  Added Auxiliary Lanes Project in North Vernon

Thank You

Please visit with INDOT project officials Project Open House:

Project maps, displays and INDOT project officials for informal Q & A

A special thank you to the Jennings County High School

Thank you for your attendance this evening