Carley Daines & Partners 11 Bridgewater Road Walkden Manchester Project Job Ref. Section Sheet no./rev. 1 Calc. by F Date 18/01/2016 Chk'd by Date App'd by Date SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) SOAKAWAY DESIGN In accordance with CIRIA C697 SUDS Tedds calculation version 2.0.01 Design rainfall intensity Location of catchment area Manchester Impermeable area drained to the system A = 780.0 m 2 Return period Period = 30 yr Ratio 60 min to 2 day rainfall of 5 yr return period r = 0.390 5-year return period rainfall of 60 minutes duration M5_60min = 18.0 mm Increase of rainfall intensity due to global warming pclimate = 30 % Soakaway / infiltration trench details Soakaway type Rectangular Width of pit w = 4800 mm Length of pit l =4000 mm Percentage free volume Vfree = 96 % Soil infiltration rate f = 66.310 -6 m/s Base area Ab = w l = 19200000 mm 2 Perimeter P = 2 (w + l) = 17600 mm Coefficient b b = P f / (Ab Vfree) = 0.23 hr -1 Table equations Rainfall intensity i = M30 / D Coefficient a a = Ab / P - (A i / (P f)) Minimum depth required H = a (e (-bD) - 1) Duration, D (min) Growth factor Z1 M5 rainfalls (mm) Growth factor Z2 30 year rainfall, M30 (mm) Intensity, i (mm/hr) a (mm) Min depth req (mm) 5 0.37 8.7 1.47 12.8 153.04 -27325 514 10 0.52 12.2 1.51 18.3 109.94 -19323 720 15 0.63 14.7 1.52 22.5 89.91 -15604 864 30 0.80 18.7 1.54 28.8 57.62 -9608 1035 60 1.00 23.4 1.54 36.0 35.95 -5585 1138 120 1.21 28.3 1.52 43.0 21.52 -2905 1063 240 1.46 34.2 1.49 51.0 12.76 -1278 765 360 1.62 37.9 1.48 56.0 9.33 -641 478 600 1.82 42.6 1.45 61.9 6.19 -59 53 1440 2.28 53.4 1.41 75.2 3.13 509 0 Minimum depth of soakaway Hmax = 1138 mm Time for emptying soakaway to half volume ts50 = Vfree Ab / (f P) Ln((Hmax + Ab / P) / (Hmax / 2 + Ab / P)) = 1hr 17min 36s PASS - Soakaway discharge time less than or equal to 24 hours
9

SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

Feb 11, 2018

Download

Documents

phamdiep
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

Carley Daines & Partners

11 Bridgewater Road

Walkden

Manchester

Project

Job Ref.

Section

Sheet no./rev.

1

Calc. by

F

Date

18/01/2016

Chk'd by

Date

App'd by

Date

SOAKAWAY DESIGN (BRE DIGEST 365/SUDS)

SOAKAWAY DESIGN

In accordance with CIRIA C697 SUDS

Tedds calculation version 2.0.01

Design rainfall intensity

Location of catchment area Manchester

Impermeable area drained to the system A = 780.0 m2

Return period Period = 30 yr

Ratio 60 min to 2 day rainfall of 5 yr return period r = 0.390

5-year return period rainfall of 60 minutes duration M5_60min = 18.0 mm

Increase of rainfall intensity due to global warming pclimate = 30 %

Soakaway / infiltration trench details

Soakaway type Rectangular

Width of pit w = 4800 mm

Length of pit l =4000 mm

Percentage free volume Vfree = 96 %

Soil infiltration rate f = 66.310-6 m/s

Base area Ab = w l = 19200000 mm2

Perimeter P = 2 (w + l) = 17600 mm

Coefficient b b = P f / (Ab Vfree) = 0.23 hr-1

Table equations

Rainfall intensity i = M30 / D

Coefficient a a = Ab / P - (A i / (P f))

Minimum depth required H = a (e(-bD) - 1)

Duration, D (min)

Growth factor Z1

M5 rainfalls

(mm)

Growth factor Z2

30 year rainfall,

M30 (mm)

Intensity, i (mm/hr)

a (mm) Min depth req

(mm)

5 0.37 8.7 1.47 12.8 153.04 -27325 514

10 0.52 12.2 1.51 18.3 109.94 -19323 720

15 0.63 14.7 1.52 22.5 89.91 -15604 864

30 0.80 18.7 1.54 28.8 57.62 -9608 1035

60 1.00 23.4 1.54 36.0 35.95 -5585 1138

120 1.21 28.3 1.52 43.0 21.52 -2905 1063

240 1.46 34.2 1.49 51.0 12.76 -1278 765

360 1.62 37.9 1.48 56.0 9.33 -641 478

600 1.82 42.6 1.45 61.9 6.19 -59 53

1440 2.28 53.4 1.41 75.2 3.13 509 0

Minimum depth of soakaway Hmax = 1138 mm

Time for emptying soakaway to half volume ts50 = Vfree Ab / (f P) Ln((Hmax + Ab / P) / (Hmax / 2 + Ab / P)) = 1hr

17min 36s

PASS - Soakaway discharge time less than or equal to 24 hours

Page 2: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

Carley Daines & Partners

11 Bridgewater Road

Walkden

Manchester

Project

Job Ref.

Section

Sheet no./rev.

2

Calc. by

F

Date

18/01/2016

Chk'd by

Date

App'd by

Date

Page 3: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

DB

B

BD

2

LAP100m activity zone

Soft l

ands

cape

buffe

r to gr

eenb

elt

Railway track, Liverpool/Manchester line

29.

25.

22.

CB

BC

CBCC

B

BC

B

Apts.

A

C

35.36.

30.

31.

28. 32.27.

26.

24.

23.

21.18. 20.

19.

9-17.

8.7.

6.

5.4.

3.

2.

1.

A

B

BB

BB

33.

34.BC

Page 4: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

Carley Daines & Partners

11 Bridgewater Road

Walkden

Manchester

Project

RHINEWOOD HOTEL, GLAZEBROOK

Job Ref.

15-B-10668

Section

LARGE SOAKAWAY

Sheet no./rev.

1

Calc. by

CRC

Date

22/03/2016

Chk'd by

Date

App'd by

Date

INTRODUCTION

The large soakaway drains 15 units at 50m2 plus 750m2 of highway

Total drained area – 1500m2

SOAKAWAY DESIGN (BRE DIGEST 365/SUDS)

SOAKAWAY DESIGN

In accordance with CIRIA C697 SUDS

Tedds calculation version 2.0.01

Design rainfall intensity

Location of catchment area Manchester Imp area drained to soakaway A = 1500.0 m2

Return period Period = 30 yr Ratio r r = 0.360

5-yr rtn period rainfall 60 min M5_60min = 18.0 mm Increase for global warming pclimate = 30 %

Soakaway / infiltration trench details

Soakaway type Rectangular Width of pit w = 8000 mm

Length of pit l =4800 mm Percentage free volume Vfree = 96 %

Soil infiltration rate f = 66.310-6 m/s

Base area Ab = 38400000 mm2 Perimeter P = 25600 mm

Coefficient b b = 0.17 hr-1

Table equations

Rainfall intensity i = M30 / D

Coefficient a a = Ab / P - (A i / (P f)) Minimum depth required H = a (e(-bD) - 1)

Duration, D (min)

Growth factor Z1

M5 rainfalls

(mm)

Growth factor Z2

30 year rainfall,

M30 (mm)

Intensity, i (mm/hr)

a (mm) Min depth req

(mm)

5 0.36 8.4 1.47 12.4 148.60 -34981 480

10 0.51 11.9 1.50 18.0 107.71 -24941 680

15 0.62 14.5 1.52 22.1 88.39 -20198 820

30 0.79 18.5 1.54 28.4 56.87 -12462 991

60 1.00 23.4 1.54 36.0 35.95 -7327 1119

120 1.22 28.5 1.52 43.4 21.68 -3823 1079

240 1.48 34.6 1.49 51.7 12.92 -1671 810

360 1.67 39.1 1.47 57.5 9.58 -852 537

600 1.90 44.5 1.45 64.3 6.43 -78 63

1440 2.42 56.6 1.40 79.3 3.30 689 0

Minimum depth of soakaway Hmax = 1119 mm Time to empty half soakaway ts50 = 1hr 27min

PASS - Soakaway discharge time less than or equal to 24 hours

Page 5: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester
Page 6: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

EARTH ENVIRONMENTAL & GEOTECHNICAL

Ashbourne House, 334 Wellington Road North Stockport, Cheshire, SK4 5DA

Tel: 0161 2824518 Email: [email protected] Web: www.earthenvironmental.co.uk

SOAKAWAY

Site: Rhinewood Hotel, Warrington

Number: SA1

Date: 06th January 2016

Engineer: Peter Lynch

Dimensions: 1.8 X 2.5m

Total Depth: 2.0m

Job No.: A1197-16

Coordinates: SJ 69717 92487

Schematic Profile:

Log:

TOPSOIL Brown SAND Reddish brown SAND

GL – 0.50m: Black slightly silty SAND with rootlets (TOPSOIL). 0.50 – 1.10m: Brown slightly silty slightly gravelly fine to coarse SAND. Gravel is medium to coarse and subangular of mudstone. 1.10m – 2.00m: Reddish brown slightly silty fine to medium SAND. Groundwater not encountered. Trial Pit complete at 2.00m bgl. Trial pit stable at final depth.

Pictures:

SA1 Spoil

Page 7: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

EARTH ENVIRONMENTAL & GEOTECHNICAL

Ashbourne House, 334 Wellington Road North Stockport, Cheshire, SK4 5DA

Tel: 0161 2824518 Email: [email protected] Web: www.earthenvironmental.co.uk

SOAKAWAY

Site: Rhinewood Hotel, Warrington

Number: SA2

Date: 06th January 2016

Engineer: Peter Lynch

Dimensions: 1.8 X 2.5m

Total Depth: 2.0m

Job No.: A1197-16

Coordinates: SJ 69774 92536

Schematic Profile:

Log:

TOPSOIL Brown SAND

GL – 0.50m: Black slightly silty SAND with rootlets (TOPSOIL). 0.50 – 2.00m: Brown slightly silty slightly gravelly fine to coarse SAND. Gravel is medium to coarse and subangular of mudstone. Groundwater not encountered. Trial Pit complete at 2.00m bgl. Trial pit stable at final depth.

Pictures:

SA2 Spoil

Page 8: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

Earth Environmental& Geotechnical Ltd

Tel / Fax: 0161 2824518 Job No: A1197Web: www.earthenvironmental.co.uk Site: Rhinewood hotelEmail: [email protected] Client: R P Tyson Construction Ltd

Location Reference: SA1

Date 06/01/2016 Time Depth of

Geology in test section Sand Units Elapsed water below top of casing

Depth to Base of Hole 2 m (secs) (m)

Hole width 1.8 m 0 1.000

Hole length 2.5 m 1 1.010

Depth to water at start of test below ground level 1 m 2 1.010

Depth to water at end of test below ground level 1.10 m 3 1.010

Depth to 75% full 1.25 m 4 1.020

Depth to 50% full 1.50 m 5 1.020

Depth to 25% full 1.75 m 6 1.020

Height to 50% depth 0.500 m3 7 1.030

Effective Storage Volume Vp75-25 2.25 m3 8 1.030

Time for water level to fall between Vp75 -25 1215 s 9 1.030

Internal surface area of hole up to 50% depth including base 8.80 m2 10 1.030

Soil Infiltration Rate, f 2.10E-04 m/s 15 1.040

30 1.040

60 1.050

120 1.060

180 1.060

240 1.100

SOAKAWAY TEST

(To: BRE 365 1991)

1.000

1.020

1.040

1.060

1.080

1.100

1.120

0 50 100 150 200 250 300

De

pth

Be

low

Gro

un

d L

eve

l (m

)

Elapsed Time (secs)

Page 9: SOAKAWAY DESIGN (BRE DIGEST 365/SUDS) - …myplanning.warrington.gov.uk/Planning/StreamDocPage/obj.pdf?DocNo… · Carley Daines & Partners 11 Bridgewater Road Walkden Manchester

Earth Environmental& Geotechnical Ltd

Tel / Fax: 0161 2824518 Job No: A1197Web: www.earthenvironmental.co.uk Site: Rhinewood HotelEmail: [email protected] Client: R P Tyson Construction

Location Reference: SA2

Date 06/01/2016 Time Depth of

Geology in test section Sand Units Elapsed water below top of casing

Depth to Base of Hole 2 m (secs) (m)

Hole width 1.8 m 0 1.20

Hole length 2.5 m 1 1.20

Depth to water at start of test below ground level 1.2 m 2 1.20

Depth to water at end of test below ground level 1.26 m 3 1.20

Depth to 75% full 1.40 m 4 1.21

Depth to 50% full 1.60 m 5 1.21

Depth to 25% full 1.80 m 6 1.21

Height to 50% depth 0.400 m3 7 1.21

Effective Storage Volume Vp75-25 1.80 m3 8 1.21

Time for water level to fall between Vp75 -25 3420 s 9 1.21

Internal surface area of hole up to 50% depth including base 7.94 m2 10 1.21

Soil Infiltration Rate, f 6.63E-05 m/s 15 1.21

30 1.22

60 1.23

120 1.26

180 1.26

240 1.27

SOAKAWAY TEST

(To: BRE 365 1991)

1.10

1.12

1.14

1.16

1.18

1.20

1.22

1.24

1.26

1.28

0 50 100 150 200 250 300

De

pth

Be

low

Gro

un

d L

eve

l (m

)

Elapsed Time (secs)