SMHa/CGD/TT c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s addition + renovations
Jan 17, 2016
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s addition + renovations
phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
integrated project delivery team
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
Media Center / Phase 2
Spaces Number of Spaces Sq. Footage Total Sq. Footage
Reading Room 1 1,747 1,747
Office/workroom 1 180 180
Conference Room 1 150 150
Conference Room 1 225 225
Storage Room 1 165 165
Public Toilets 2 40 40
Total NSF 2,547
Total Gross SF in area to be renovated 2,547
the program / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
the program / phase 2
Auditorium / Phase 2
Spaces Number of Spaces Sq. Footage Total Sq. Footage
Seating Area 1 4,400 4,400
Stage 1 1,250 1,250
Media Production/Green Room 1 300 300
Dressing Rooms 2 300 600
Prop Construction 1 750 750
Storage 1 600 600
Total NSF 7,900
Total Gross SF in area to be renovated 9,330
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
opportunities/challenges
Cross High School exhibits obvious pride in their school building & facilities. The newly renovated Media Center will provide a welcoming center of learning for the students and the community of Cross. The expanded Auditorium will allow for presentations to the entire school population and provide a needed multi-purpose space for the school, to be used for large group meetings, wrestling practice, and even community gatherings.
Auditorium• Provide dressing rooms and back-of-house spaces for productions, along with current AV equipment• Provide seating for the entire student population, along with faculty• Provide floor space for wrestling practice or other multi-purpose uses• Fire sprinkler protection will be added to ensure the space is protected for large group gatherings
Media Center• Provide exterior entry and access for after-hours use by students and the surrounding community, and can be locked off from the remainder of the school to provide security for the classrooms• Entry canopy at exterior will reinforce the school’s image and provide a location for the Berkeley County Libraries Bookmobile to park & serve the Cross community• Provide current technology and research options for students
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
phasing
Media CenterPhase 2
AuditoriumPhase 2
Locker RoomsPhase 1
GymPhase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
demolition / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
new work / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
existing conditions / future media center
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
existing conditions / media center
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
media center / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
existing conditions / auditorium
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
auditorium / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
gym / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
• Student Safety
• Emergency Egress
• Additional Staff on Site
• Radio Contact with School Personnel
• CHS Staff Participation at Weekly Project Meetings
• Control and Badging of all Project Personnel
• Site Specific Orientation for Subcontractors
safety
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
• Solicitation for Phase 2
– Advertisements in Local and State Periodicals
– SCBO
– AGC
– TTC Database (Over 400 invitations)
– CDI Database
• Tri-County Market
bid solicitation
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
subcontractor outreach
Phase 2
• 25% Local and Minority
Subcontractors
– Scheduling, Concrete HVAC,
Electrical, Masonry,
Demolition, Casework, Tile,
Fire Protection
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
Phase 2
• Pricing Estimates
– January 10, 2014
– February 9, 2014
• Design Development OSF Review May 28, 2014
• Detailed Design Submittal June 19, 2014
• Detailed Design Estimate July 17, 2014
• Implementation Documents Submittal August 8, 2014
• GMP Estimate August 28, 2014
• Bids Received September 4, 2014
• Board Approval September 23, 2014
• First Day of Work October 6, 2014
• Complete Media Center February, 2015
• Complete Auditorium July, 2015
tentative schedule / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
GMP / phase 2
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s questions?
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s appendix
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
locker rooms / phase 1
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
Athletics / Phase 1
Spaces Number of Spaces Sq. Footage Total Sq. Footage
Coaches Offices 2 180 360
Training Room 1 250 250
Locker Rooms 2 900 1,800
Visitor Locker Rooms 2 350 700
Uniform Storage 1 135 135
Laundry/Equipment 1 135 135Storage
Total NSF 3, 110
Total Gross SF 4, 080
the program
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
Phase 1
• Start of Preconstruction December 2013
• Pricing Estimates
– January 10, 2014
– February 9, 2014
– May 20, 2014
• Local Contractor Outreach Session May 5, 2014
• Bids Received May 8, 2014
• Board Approval May 27, 2014
• Last Day for Students June 2, 2014
• First Day of Work June 3, 2014
• Demolition Complete June 21, 2014
• HVAC, Elect, Plumbing Complete August 10, 2014
• Turn Over Locker Rooms for StudentsSeptember 2, 2014
• Punch List Completion October 17, 2014
schedule / phase 1
SMHa/CGD/TT
c r o s s h i g h s c h o o l b e r k e l e y c o u n t y s c h o o l s
GMP / phase 1