Top Banner
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Engineering Procedure Signals L1-CHE-PRO-035 Signalling Design Technical Review Procedure Version: 2 Issued: March 2017 Owner: Engineering Signals Approved and Authorised For Use By: Phil Ellingworth Chief Engineer
14

Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

Apr 15, 2018

Download

Documents

duongdang
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION

Engineering Procedure Signals

L1-CHE-PRO-035

Signalling Design Technical Review Procedure

Version: 2

Issued: March 2017

Owner: Engineering Signals

Approved and Authorised For Use By:

Phil Ellingworth

Chief Engineer

Page 2: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 14

Approval

Amendment Record

Approval Date Version Description 26/02/2017 1 Initial draft under MTM

08/03/2017 2 Document number amended from L1-NAM-PRO-001. Document reviewed and updated to reflect current procedures.

Page 3: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 14

Table of Contents 1 Purpose ........................................................................................................................... 4

2 Scope ............................................................................................................................... 4

3 Abbreviations and Acronyms ........................................................................................ 4

4 Definitions ....................................................................................................................... 5

5 References & Legislations ............................................................................................. 5

6 Related Documents ........................................................................................................ 5

7 Approach ......................................................................................................................... 5

8 Contractors Mandatory Requirements .......................................................................... 6

8.1 Equipment ......................................................................................................................... 6 8.2 Competency ...................................................................................................................... 6 8.3 Mentoring .......................................................................................................................... 7 8.4 Correlation ........................................................................................................................ 7 8.5 Standard Waivers ............................................................................................................. 7 8.6 Independent Verification ................................................................................................... 7

8.6.1 Verifier ............................................................................................................. 7 8.6.2 Verifier Certification ......................................................................................... 8

8.7 Design Report ................................................................................................................... 8 8.8 Application Logic Data Structure Manual (ALDS) ............................................................. 8 8.9 Calculations ...................................................................................................................... 8 8.10 Overlapping Design Agreement(s) (ODA) ........................................................................ 8

9 Roles and Responsibilities of Contractors ................................................................... 9

9.1 General ............................................................................................................................. 9 9.2 Draftsperson ..................................................................................................................... 9 9.3 Designer ............................................................................................................................ 9 9.4 Checker ............................................................................................................................. 9 9.5 Verifier ............................................................................................................................... 9 9.6 Approver ........................................................................................................................... 9 9.7 Certifier ........................................................................................................................... 10

10 Document Definitions ................................................................................................... 10

11 General Requirements of Contractors undertaking Design ...................................... 10

11.1 Standards, Instructions and Type Approvals .................................................................. 10 11.2 Drawing Version Control ................................................................................................. 10 11.3 CBI Application Logic Data Structure (ALDS) Manual.................................................... 10

12 Design Modifications .................................................................................................... 11

13 Isolation and re-instatement of Signalling Equipment ............................................... 11

13.1 Temporary Bridging Authority Forms .............................................................................. 11

14 Engineering Technical Review Process and Procedure ............................................ 11

15 Appendix 1 .................................................................................................................... 14

Page 4: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 14

1 Purpose The purpose of this document is to define the Signal Design and Technical Review requirements for MTM when performing an ARTO review of external designs.

The document shall also define the requirements and responsibilities of Contractors and the design documents they must produce in order for Metro Trains Melbourne (MTM) to undertake an ARTO Signalling Design and Technical review.

This document applies to all works on the MTM network affecting the signalling Infrastructure.

This procedure supersedes and replaces L1-NAM-PRO-001. Where other MTM processes and procedures refer to L1-NAM-PRO-001 this specification shall apply.

This procedure is not applicable when the design is undertaken in house by MTM. An ARTO review is not applicable for internal designs as MTM shall ensure their requirements are provided and met through the design process.

2 Scope It is imperative that all organisations have a clear understanding of MTM’s Design and Technical requirements and submit all the required documentation as listed in this procedure.

The requirements stated in this procedure apply to all signalling designs prepared by Contractors for use on the MTM network [either on behalf of MTM Projects, Infrastructure Delivery or other stakeholders such as the Public Transport Victoria (PTV), Level Crossing Rail Authority (LXRA), Melbourne Metro Rail Authority (MMRA)].

The design review must follow the Terms of Reference specified by MTM and shall provide assurance that all the requirements of the Accredited Rail Transport Operator’s (ARTO’s) Safety Management System, including operational and functional requirements and the appropriate standards, have been met.

This document should be read in conjunction with the latest MTM Design and Technical Review Procedure, document No. L1-NAM-PRO-002.

3 Abbreviations and Acronyms ARTO Accredited Rail Transport Operator

AS Australian Standards

CBI Computer Based Interlocking

CEI Chief Engineers Instruction

CMS Competency Management System

DMS Drawing Management System

DPN Design Practice Note

EDRG Engineering Design Review Group

MTM Metro Trains Melbourne Pty. Ltd.

Page 5: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 14

PTV Public Transport Victoria

RAMS Reliability, Availability, Maintainability & Safety

RFI Request for Information

SAP Signalling Arrangement Plan

SER Signalling Equipment Room

TFM Trackside Functional Module

VRIOGS Victorian Rail Industry Operators Group Standards

4 Definitions Contractor

Shall

A person or company that undertakes a contract to provide materials or labour to perform a service or do a job for MTM. Is used as the descriptive word to express a requirement that is mandatory to achieve conformance to the standard.

Should Is used as the descriptive word to express a requirement that is recommended in order to achieve compliance to the standard. Should can also be used if a requirement is a design goal but not a mandatory requirement.

Standard

A requirement that is mandatory and shall be adhered to in order to achieve MTM’s objectives.

For the purpose of this document MTM Policies and Procedures, Design Practice Notes and Chief Engineers Instructions shall be deemed as a standard.

Design Check A check of the detailed design to ensure it conforms to the standards of the day and meets the requirements of the project.

5 References & Legislations Rail Safety Act 2006

6 Related Documents L1-NAM-PRO-002 - MTM Design and Technical Review Procedure

L2-SIG-PRO-007 - MTM Overlapping Design Agreement

7 Approach The Rail Safety Act 2006 is clear that rail safety is a shared responsibility and the Contractors Design Office is fully responsible for their design, checking and verification. The ARTO is responsible for ensuring the Contractor produces designs that are safe and comply with recognised quality assurance processes.

Page 6: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 14

The approach to be taken with a technical review is to consider the design based on MTM’s requirements, in particular the impact on both existing and future inspection, maintenance, safety and operational regimes. A ‘whole of life’ view shall be applied.

The MTM technical review is not a substitute for the design, checking and verification processes that form part of the production of signalling drawings. The MTM Review will, however, confirm that these have been satisfactorily performed by the Contractor.

The MTM Review will typically consider:

• Safety in design

• Maintainability

• Functional and Operational requirements

• Quality processes including design, check and verification

• Independence in the design process

• Competency of designers

• Compliance to standards, approvals and specifications

8 Contractors Mandatory Requirements The contractor shall ensure the following mandatory requirements are undertaken during the production of the signalling design prior to submitting to MTM for review. Evidence of such shall be supplied as part of the Design Review submission by the Contractor.

8.1 Equipment The designs shall utilise MTM type approved equipment only.

8.2 Competency All staff responsible for the design, checking, independent verification, installation and testing of signalling designs shall hold the relevant level(s) of competency as required by the MTM CMS to work independently.

All staff involved in the design, installation and testing of signalling designs that do not hold the relevant level(s) of competency for the tasks being undertaken shall be mentored by a person that holds the right level(s) of competency required by the MTM CMS for the task being mentored.

The mentor shall become the person responsible for that activity and shall be required to countersign all documentation associated with that activity.

Checkers under Mentorship shall hold a minimum competency of Level 2 in design and Level 1 in checking for the task(s) they are being mentored to check. Mentoring of independent verifiers shall not be permitted.

Page 7: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 14

8.3 Mentoring A contractor wishing to utilise mentors in the production, installation and/or testing of their signalling designs shall provide MTM with the following prior to any mentoring activities taking place;

1. A copy of their mentoring process for approval

2. A list of their staff and the activities that they wish them to be mentored in

8.4 Correlation Prior to any design alterations, all signalling source records required to be modified are to be correlated against the actual wiring and equipment on site to check their accuracy. Should differences be identified then the source records shall be updated and independently checked in order to ensure the base documentation used for the design reflects what is out on site. Once completed one paper copy of all amended source documentation shall be provided to MTM Engineering.

8.5 Standard Waivers A Standard Waiver shall be obtained where the requirements of standards cannot be met.

8.6 Independent Verification All safety critical designs are to be Independently Verified as detailed in VRIOGS 012.1, section 5.0. MTM considers Signalling Arrangement Plans, Control Tables, Bonding, Power and Cable Running Plans, Fringe/Interface, Level Crossing and SER/Location circuits, ALDS, Axle Counter and CBI Architecture and application logic data to be safety critical design.

MTM reserve the right to request Independent Verification of other items of design if deemed necessary.

8.6.1 Verifier Independence for safety critical design verification is essential and must be demonstrated by the Contractor.

Typically, independence requires the Verifier to be engaged from an external company and for the design to be verified at an office external to where the design has been created.

It may be acceptable to undertake verification within the same company but with the Verifier located in a separate office having had no involvement in the design production. This arrangement must be pre-approved by the MTM Head of Engineering – Signals.

The Contractor must be able to clearly demonstrate that there is no association between the person(s) undertaking the design and/or checking of the design to be verified.

Page 8: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 14

8.6.2 Verifier Certification The Verifier shall provide a verification report that includes certification from the Verifier that the (safety critical) design verified complies with the projects functional and operational requirements, is maintainable and conforms to the required standards (unless supported by a standard waiver). The Verifier shall also confirm that the design is safe to use for train operations on the MTM network.

8.7 Design Report The Contractor shall provide a comprehensive Signalling Design Report which includes certification that:

• the design complies with the projects functional and operational requirements;

• the design is maintainable:

• the design conforms to the required standards unless supported by a standard waiver.

The design report shall also contain any comment logs prepared by the checker and verifier during their checks. These logs shall detail the comments raised along with the designer’s response/actions and all logs shall be closed out to the satisfaction of the person(s) who raised them or their appointed delegate.

8.8 Application Logic Data Structure Manual (ALDS) An Application Logic Data Structure manual shall be produced and submitted for review prior to undertaking preparation of any data.

8.9 Calculations Calculations shall be provided to support the production of the signalling design.

8.10 Overlapping Design Agreement(s) (ODA) Where a drawing or drawings are required for a design and the drawing is already under the control of another design team then an ODA shall be produced in accordance with MTM document L2-SIG-PRO-007.

Failure to undertake and provide these mandatory requirements shall result in MTM rejecting the design until such time as they have been undertaken and provided.

Page 9: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 14

9 Roles and Responsibilities of Contractors

9.1 General The contractors design office is fully responsible for their design, checking, verification and approval of their design.

The contractor shall validate the design through a rigorous testing procedure in accordance with the requirements of AS 4292.4 using independent and appropriately qualified, experienced and competent staff. The Contractor shall ensure that Signalling design and its installation are functionally in accordance with the approved scope and design specification(s). Tests shall then be carried out to validate that the installed system operates in accordance with the required signalling principles and safe working rules and regulations.

The contractor shall submit the Testing and Commissioning Plan to MTM for review and all comments shall be closed out in accordance with MTM’s Works Readiness Procedure (L1-NPD-PRO-002) unless agreed otherwise by the Office of the Chief Engineer.

9.2 Draftsperson The Draftsperson is the person who has drafted or has performed CAD work of the signalling drawing. The Draftsperson shall be identified by the initial of their first name and full last name (e.g. J CITIZEN) appearing in the drawing’s Title Block under “Drawn By” field.

9.3 Designer The Designer is the person who has designed the signalling drawing and shall be identified by the initial of their first name and full last name (e.g. B KING) appearing in the drawing’s Title Block under “Designed By” field. It is acceptable that the same person acts as draftsperson and designer.

9.4 Checker The Checker is the person who performs as the design office internal checker of the signalling drawing and shall be identified by the initials of their first name and full last name (e.g. M SMITH) appearing in the drawing’s Title Block under “Checked By” field.

9.5 Verifier The Verifier is the person who Independently verifies the signalling design and shall be identified by the initial of their first name and full last name (e.g. J BLOGGS) appearing in the drawing’s Title Block under “Ind Review” field.

9.6 Approver The Approver is the person who, within the production organisation, takes responsibility that the drawings have been appropriately checked & verified and who takes responsibility that the drawing has been through an engineering quality assurance process for its accuracy and safety in design. The Approver of the signalling drawing shall be identified by the initial of their first name and full last name (e.g. D JONES) appearing in the drawing’s Title Block under “Approved” field.

Page 10: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 14

9.7 Certifier The Drawing Certifier is the person who, within the production organisation, takes responsibility that the drawings have been installed to as-built status.

10 Document Definitions The commencement of any technical review shall require the provision of the fundamental documents that identify the parameters by which the design is to be undertaken.

These include but are not limited to the following;

a) Final Operating Requirements

b) Signalling Functional Specification

c) Scope and Technical Requirements Specification

d) Design Management Plan

e) Drawing Management Plan

f) Master Drawing Register

g) Design Interface Management Plan

11 General Requirements of Contractors undertaking Design

11.1 Standards, Instructions and Type Approvals In order to maintain its status as an ARTO, MTM has to meet the requirements of its Safety Management System. This requires MTM to ensure that its Contractors conform to the relevant Standards.

11.2 Drawing Version Control The PTV Infrastructure Drafting Standards specify the version control requirements for drawings that are booked into the State drawing repository (Drawing Management System i.e. DMS) at the as-built stage.

The Design Contractor shall ensure their as built drawings comply with these requirements. Please refer to PTV Infrastructure Drafting Standards for current requirements.

The Contractor is responsible for maintaining its own document control system throughout the design lifecycle.

11.3 CBI Application Logic Data Structure (ALDS) Manual This document shall be produced by the design office and submitted for MTM review, with all comments closed, prior to any data preparation work being undertaken on the project.

The ALDS shall be produced, checked and independently verified in the same manner as all other designs submitted to MTM for review.

The purpose of this document is to clearly define all the rules and steps required to produce Interlocking data utilising standard data structures.

Page 11: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 14

The data structures shall be clearly explained in detail in order for the reader to have a clear understanding of how the structures work and provide the functionality requirements of MTM as defined by the Victorian Rail Industry Operators Group Standards (VRIOGS) and/or any relevant MTM specific requirements (ie DPNs, RFIs, Chief Engineer’s Instructions etc.).

The ALDS shall include a typical signalling layout that the structures are based around in order to help the reader understand the structures application.

12 Design Modifications Once a design has been Issued For Construction (IFC) modifications to that design shall be approached in either of two ways, these being;

a) If construction has not commenced then the IFC design shall be modified, checked and verified, issued to MTM for review and once all comments closed issued as an up revised IFC design.

b) If construction has commenced then the design shall be modified, checked and verified, issued to MTM for review and, once all comments are closed, issued as a design modification on a design modification sheet.

Design modifications shall be produced in the same manner as any other design alteration and shall assume that any previous design alterations have been completed.

Design modifications shall be uniquely numbered and recorded in a design modification register.

13 Isolation and re-instatement of Signalling Equipment Project works requiring any signalling equipment isolated, false fed or removed shall require an isolation/re-instatement design package produced, checked, verified by the contractor and issued to MTM EDRG for review.

13.1 Temporary Bridging Authority Forms Temporary Bridging Authority forms are for the exclusive use of Infrastructure Maintenance.

14 Engineering Technical Review Process and Procedure a) Design contractors submissions for review shall be complete and include all supporting

documentation referenced at Section 10 above. The Design Report and all Standard Waivers and ODAs must also be submitted;

b) The following design documents shall be submitted to MTM EDRG for review;

i. Design Management Plan ii. Drawing Management Plan iii. Design Interface Management Plan iv. CBI Application Data Logic Structure Manual v. Signalling Arrangement Plan

Page 12: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 14

vi. Table of Routes vii. Aspect Sequence Chart viii. Control Tables ix. Track Circuit, Bonding and Signalling Apparatus Plan x. Axle Counter System Overview Plan xi. Axle Counter Communication Overview Plan xii. Cable Running Plan xiii. CBI Architecture Plan xiv. Power Calculations xv. Power Distribution Plan xvi. Power Location Detailed Design xvii. Power Location Equipment Room Detailed Design xviii. Trackside Functional Module (TFM) / Object Controller Input/Output bit

allocations xix. Location Case Detailed Design xx. Signal Equipment Room (SER) Detailed Design xxi. Signalling Diagram (Litho) xxii. Train Control System Diagram xxiii. Communication Architecture Plan xxiv. Communication Design

c) These design packages shall be submitted to the Engineering Design Review Group EDRG Document Controller via the MTM Project Manager or their appointed delegate;

d) The MTM EDRG Document Controller shall record the receipt of the package and forward to the Signalling Design and Review Manager to be allocated a reviewer;

e) The Signalling Design and Review Manager shall appoint suitable persons to undertake the MTM Engineering Technical Review following RAMS principle for all stages of a projects signalling design;

f) The reviewer shall ensure that all the mandatory requirements stated in section 8 above have been undertaken prior to starting the review of the design documentation. The review shall be terminated and the package rejected if it is identified that these mandatory requirements have not been satisfied;

g) Once satisfied that the mandatory requirements have been fulfilled, the reviewer shall commence a review of the design details submitted;

h) The reviewer shall satisfy themselves through a partial or full review, using their knowledge and experience, that the design complies with project requirements, current legislation, standards, manufacturers specifications and other applicable MTM requirements (such as DPNs and Instructions).

i) The Reviewer shall raise a Comment Log to record:

• Errors identified

• Non conformances

• Further information required

Page 13: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 14

• Clarifications required

j) The Comment Log shall be passed to the EDRG Document Controller who shall forward to the Project Manager or appointed delegate. The Document Controller will record that the review is complete;

k) If, during the review, the reviewer raises ten (10) category 3 comments or a combination of thirty (30) category 2 and 3 comments the review shall be terminated and the package shall be rejected.

l) A design package shall not be permitted to proceed to the next phase of the project until such time as all comments have been addressed to the satisfaction of the reviewer or their appointed delegate.

Page 14: Signalling Design Technical Review Procedure · ARTO Accredited Rail Transport Operator AS Australian Standards . CBI Computer Based Interlocking . CEI Chief Engineers Instruction

SIGNALLING DESIGN TECHNICAL REVIEW PROCEDURE

L1-CHE-PRO-035 Version: 2 Effective from: 8th March 2017

Approving Manager: Chief Engineer Approval Date: 08/03/2017 Next Review Date: 08/03/2020 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 14

15 Appendix 1

MTM Review Process