Page 1: Shawnee County Willard Bridge Presentation July 23, 2015

July 23, 2015

Page 2: Shawnee County Willard Bridge Presentation July 23, 2015

Weekly Inspection Update Design Update Permitting Update R-O-W Update Utility Relocation Update Funding Update Schedule Review Other Items

Page 3: Shawnee County Willard Bridge Presentation July 23, 2015

Six-month intensive inspection was completed week of July 6, 2015

Condition remains primarily unchanged

• Current weight limits still satisfactory • Incorporating “saddle” component into bridge replacement plans for

enhanced floor beam support o Provides extra level of support for floor beam o Extends life of floor beam to last through construction o Will be first requirement of bridge contractor

Page 4: Shawnee County Willard Bridge Presentation July 23, 2015

93% Complete

Estimated Completion date: August

Page 5: Shawnee County Willard Bridge Presentation July 23, 2015

Permitting Acquisition Remains on Schedule UPRR

◦ Proposed plans (Unit 1) sent to UPRR

UPRR continuing review process

Environmental ◦ NEPA (National Environmental Pollution Act) Document

KDOT has led the NEPA process since the project field check was completed in 2010

Project considered for a “Categorical Exclusion”

KDOT will be re-confirming clearances due to time that has passed since original consideration

◦ Previously obtained 7 environmental clearances

Others

◦ Corps of Engineers 404 Permit ◦ KDWR – Action Plan ◦ KDHE Notice of Intent ◦ KDOT Environmental Services Action Permit

Page 6: Shawnee County Willard Bridge Presentation July 23, 2015

NE Quadrant (1 property owner) ◦ R-O-W documents have been finalized; ◦ Negotiations with property owner have been held ◦ Tentative agreement has been reached regarding price ◦ Concerns regarding KDWP Boat Access

NW Quadrant (1 property owner) ◦ R-O-W Documents have been finalized ◦ Negotiations with owners’ representative have been held and offer made ◦ Representative will present offer and is to get back with us this week ◦ Property under a trust

SE Quadrant (6 property owners) ◦ All R-O-W has been acquired

SW Quadrant (4 property owners) ◦ R-O-W documents have been finalized and previously submitted to Wabaunsee County ◦ Wabaunsee County has contacted property owners and is in process of acquiring

Page 7: Shawnee County Willard Bridge Presentation July 23, 2015

No Change ◦ Previously met with Westar ◦ Other utilities involved are: Rural Water (One service line crossing) Telephone ( line on east side of roadway)

◦ Will send final plans to utilities once design complete and right-of-way acquired

◦ Not a critical path item at this point

Page 8: Shawnee County Willard Bridge Presentation July 23, 2015

TIGER Grant – NO CHANGE Requested $16.7M in federal funds Anticipate TIGER Grant award announcements by end of

September

KDOT Request – NO CHANGE ◦ KDOT confirmed ability to advance SNCO $7-$10M in no

interest loan Provided: No drastic economic downturn in the upcoming year SNCO develops funding package for balance of project

Funding likely not available until July 1, 2016

Page 9: Shawnee County Willard Bridge Presentation July 23, 2015

City of Topeka (Sales Tax Extension) – No Change ◦ Interlocal Agreement Negotiations Upcoming Completing Negotiations Key to Moving

Forward

Funding Strategy Development ◦ Met with A-F Director to discuss various sources ◦ Developing options for additional scenarios

Page 10: Shawnee County Willard Bridge Presentation July 23, 2015

TASK

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Design

Right-of-Way

Utility Adjustment

SNCO / WabCo Agreement

Permitting

UPRR Agreement

SNCO BID

SNCO Award Contract

Construction

NOTE: Progress Schedule assumes NO Federal Funding

PROJECT PROGRESS SCHEDULE

2015 2016 2017

NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130

SNCO Project No. S-121015.00

KDOT Project No. 89C 0066-01

Bridge Const.

Page 11: Shawnee County Willard Bridge Presentation July 23, 2015
Page 12: Shawnee County Willard Bridge Presentation July 23, 2015
Page 13: Shawnee County Willard Bridge Presentation July 23, 2015

TASK

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Design

Right-of-Way

Utility Adjustment

SNCO / WabCo Agreement

Permitting

UPRR Agreement

SNCO BID

SNCO Award Contract

Construction

NOTE: Progress Schedule assumes NO Federal Funding

PROJECT PROGRESS SCHEDULE

2015 2016 2017 2018

NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130

SNCO Project No. S-121015.00

KDOT Project No. 89C 0066-01

Bridge

Road Tie-In, Final Grading,

Seeding

Page 14: Shawnee County Willard Bridge Presentation July 23, 2015

REMAINING PROJECT COSTS

2015 2016 2017 Total

Design $115,625* $115,625*

R-O-W $124,000* $124,000*

UPRR Permit $35,000* $35,000*

Utility Relocation $100,000* $100,000*

Construction $8,014,000 $12,021,000 $20,035,000

Const. Engineering $641,120 $961,680 $1,602,800

Contingencies $100,000* $641,190 $961,785 $1,702,975

TOTAL $374,625* $9,296,310 $14,044,465 $23,715,400

*Funding is Currently Available

Page 15: Shawnee County Willard Bridge Presentation July 23, 2015

YEAR

AMOUNT (est)

FUNDING SOURCE

REPAYMENT SOURCE

2016/2017 $7-$10M KDOT Advance STE* (2017-2026)?

2016 $2-$3M 2016 Gen Fund N/A

2016 $5-$10M?? TIGER Grant?? N/A

2017 $6-$7M CST** Excess N/A

2017 $1M Wabaunsee Co. N/A

2017 $2-$3M 2017 Gen Fund N/A

2017 $1-$2M STE*/Exch. Funds/PW 391

N/A

2018 (if nec.) $2-$3M 2018 Gen Fund N/A

*Sales Tax Extension **Current Sales Tax