Top Banner
Environmental Impact of Steel and Concrete as Building Materials Jan Bujnak University of Zilina, Slovakia Life Cycle Assessment (LCA) – technique for assessing the environmental aspect and potential impacts associated with product (building). Most widely used method (MWU) - predominant method for steel or concrete material to be manufactured, shipped and erected on a typical construction site. Each construction project is unique; no two projects are completed or conducted in the exact same way. The following three environmental concerns are focused: - Energy consumption, - Harmful air emissions & their impacts on global warming, - Depletion of limited natural resources. Energy consumption Increased energy prices, Instability in major oil producing countries, Energy shortage in the not so distant future, Alternative energy sources, Improved energy efficiency in existing systems Buildings – large energy consumers 1
24

seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Dec 11, 2015

Download

Documents

Semina Demović

seminarski rad
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Environmental Impact of Steel and Concrete as Building Materials

Jan BujnakUniversity of Zilina, Slovakia

Life Cycle Assessment (LCA) – technique for assessing the environmental aspect and potential impacts associated with product (building).

Most widely used method (MWU) - predominant method for steel or concrete material to be manufactured, shipped and erected on a typical construction site. Each construction project is unique; no two projects are completed or conducted in the exact same way.

The following three environmental concerns are focused:

- Energy consumption,- Harmful air emissions & their impacts on global warming,- Depletion of limited natural resources.

Energy consumption

Increased energy prices,Instability in major oil producing countries,Energy shortage in the not so distant future,Alternative energy sources,Improved energy efficiency in existing systems

Buildings – large energy consumers

Accounting about 39% of total energy consumption,

1

Page 2: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Building consumption energy can be divided:- embodied energy used in the construction and pre-used phase,- operating energy required to operate and maintain the structure,

including : providing heat, light, air-conditioning, water for the building occupants.

Operational energy far outweighs embodied energy accounting for an estimated 80 to 90 % of total building energy.Because average building life spans are decreasing and operational energy efficiency is improving, the embodied energy impact on the environment cannot be ignored.

Air Emissions

Global warming & climate changes.

Building industry is the largest contributor to the total upstream dioxide carbon CO2 emissions accounting for 7% of the annual global greenhouse gas emissions.

Resource Depletion

The construction industry accounts for a vast majority of raw material consumers.

Source: Matos and Wagner, USGS, 1998

Environmental challenges because of:- limited supply of natural resources at disposition,- extraction and use has potential impact on environment.

2

Page 3: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Solutions:- new concrete with recycling admixtures- refinement of the steel manufacturing process with to nearly 100%

recycling content.

Regional Characteristics

Obviously the MWU method can be different in other geographical areas. The true comparison between the use of concrete and steel as building materials should assume a location and the relevant flows for the region.

Time Frame

The construction industry is very cyclical. The predominant or most common method today may not be the same one tomorrow. Changes in markets have effects on the MWU method.

Backwards Modeling

The four-story, 10 thousands square meters office building is used as representative size of new construction. This ensures that standard construction procedures are used on the construction of this functional unit.

3

Page 4: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

The process flow charts can be derived by working backwards from the construction site. It allows important intermediate steps and flows to identify, including intermediate transportation hubs and bulk material storage site.

Concrete Construction Process Flow

The main product systems for a concrete building are:- concrete production,- formwork production,- reinforcing bar production,- construction.

Concrete Production

Concrete production involves the batching or mixing in standard ratio the major inputs:

- Portland cement,- fine aggregate,- coarse aggregate,- water & additional admixtures.

Generally, there are two types of batching system:- wet-batch system or central mix system (the components are mixed

at the batch plant before loading on the mix truck),- dry-batch system (the components are mixed in the truck en-route

to the job site).

4

Page 5: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Cement Production

Raw materials are extracted from quarries, blended and crushed into powder. This powder is then fed through a kiln, where the materials are chemically combined under extreme heat (pyro-processing with temperature reaching 1800 0C) into clinker. This clinker is then cooled and ground with a small amount of gypsum into very fine powder – Portland cement.

Clinker production is the most energy intensive process with temperature reaching 1800 0C. Because of this, Portland cement accounts for 94 % of the energy used to produce concrete, but only accounts for 12 % of the volume.

The pyro-processing also means a large amount of CO2 emitted as by-product of calcinations, which occurs in the kiln at roughly 900 0C. Calcination is the chemical process where limestone (CaCO3) is converted to lime (CaO) and CO2 at very high temperature

CaCO3 = CaO + CO2

Approximately, 50 % of the CO2 are due to the calcination process and remaining due to release of CO2 during the burning of fossil fuels.

Aggregate Production

5

Page 6: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Aggregate is divided into two categories:- coarse aggregates (gravel, crush rock),- fine aggregates (sand).

The aggregate is derived by extracting rock from quarries and iteratively crushing and sifting to the specific size.

Formwork Production

Formwork is necessary component of cast-in-place concrete. Forms are usually constructed of different types of plywood:HDO – high density overlay,MDO – medium density overlay,Normal.Plywood is manufactured by layering several layers of layers of woods veneer with resin.Obviously, formwork is rented to the contractor on the temporary per job basis. Regional formwork distributors stock several standard size forms directly from manufactures.

Steel for Formwork Bracing

The requirement for steel bracing is given by formwork system. A small-size angle sections are used.

Reinforcing Bar

Typically, re-bars are available from local warehouses and distributors that stock obvious size and lengths. There are produced in steel bar mills.

Concrete placement

On a multi-story project, concrete is placed using a bucket or pump truck. The energy requirements include the operation of mix trucks and equipment during the concrete pouring (vibrators and other tools) and form removals, once the concrete sets.

Steel Construction Process Flows

6

Page 7: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

The main product systems for a steel building are:- steel beams production,- steel connections member production,- steel fabrication,- fireproofing manufacture,- concrete production for floor slabs,- construction.

Steel beams are produced in mini-mills using electrical arc furnance (EAF) technology to turn a mixture of iron scrap (recycle iron and steel) and small input of virgin iron into structural steel. These EAF facilities are called mini-mills, because they utilize a single process to turn raw materials into finished sections.

The basic steps in mini-mill steel-making process:

Firstly, the scrap received is weighed, checked with a radioactive sensor and then sorted into piles. The scrap is then mixed with the virgin (pig) iron and placed in the EAF. The EAF uses electrodes to melt the scrap mix. The liquid iron is then ladled and de-sulfurized, the oxygen removed, and metal alloys are added, depending on the type of steel.

7

Page 8: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

The molted liquid is then casted, where it is converted from liquid to solid by cooling.The casted steel is thrn continues to the reheat furnace, where it is decaled, scarfed, and hot-rolled into standard shapes.The EAF process is very energy intensive, especially electrical.

Steel Connection Production

Steel for connections are typically angle or plate sections produced by the EAF and hot-rolling process.

Steel Fabrication

Steel fabrication involves cutting, drilling, and fitting of raw steel members to meet the project specifications. The primary output from the steel fabrication shop is a combined member, ready for erection at the construction site.

First, the beams are cut to the required length by heavy duty band saws. The ends are then drilled to provide bolted connections. In some cases, a punch is used. A plasma cutter is used, if irregular angles are to be cut. Fabrication shops have multiple stations for fitting and welding processes. If painting is required, the structural parts undergo surface preparation (sand blasting or hand sanding).

Fireproofing production

8

Page 9: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Fireproofing production is required by building codes for steel structures. There are two general types of fireproofing:

- intumescing paint,- cementitious based spray.

Concrete production

Concrete production is required for the floor slab system with only minimal reinforcement.

Steel frame- building construction

Steel erection is the actual joining of fabricated sections on construction site and the application of fireproofing. Construction equipment includes cranes and generators, which serve as the energy consumers during steel erection.

LCA results

The results are:- total raw emission of carbon dioxide in kg,- total energy requirement in MJ,- total amount of natural resources depleted in 100 kg.

The steel and concrete buildings have relatively similar impacts on the environment. The exception is the resource depletion comparison, with a difference of 70 %.

Energy Consumption

9

Page 10: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

In terms of energy consumption, steel and concrete, as primary building materials, have equivalent energy requirements in the pre-used phase. This total energy consumption equates to the embodied energy of the specific building. The total embodied energy for both materials is just over 10 Tera-Joules (TJ) per total structures with a comparable difference of less than 1%.

The energy consumption is a combination of energy requirements for all facilities, transportation, and construction site demands. The five energy types are listed in the table:

Breakdown by energy source of the total energy consumption for both steel and concrete materials is shown if the figure:

The production of electricity accounts for 43 % of the total energy requirements for steel and 28 % for concrete as given in the figure:

10

Page 11: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Steel Specific Results

Steel has total energy requirement for defined functional unit of 10,21 TJ. The percent breakdown for specific product system is shown in the figure:

The production of steel beams is the most energy intensive portion of overall process flow. It accounts 61 % of total energy requirements when compared against the other five product systems.

Extracting both the electricity production and transportation requirements from the individual product system, see figures, it is evident that the electricity production, required during beams production, is the largest consumer of energy, due to intensive energy requirement of the EAF process and the large quantity of beams in the building.

11

Page 12: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Over 50% of the total energy requirement for beam production is used in the production of electricity. A breakdown is depicted in the figure:

Concrete Specific Results

Concrete building has a total energy requirement of 10,25 TJ, only 1% greater than the steel frame. The breakdown of total energy consumption by the four main product system is shown in the figure:

12

Page 13: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

The concrete production accounts for half (51%) of the total energy requirement of cast-in-place frame structure. Extracting transportation requirements from product system, concrete production remains the largest consumer of energy resources (40%). As is shown in the next figure, the production of electricity has less impact on the concrete frame building (28%), and its impact is primarily due to steel re-bar production.

The breakdown of energy use in concrete production (batching) on the following figure shows that the most energy intensive segment of concrete production is the process of Portland cement production requiring 74% of energy:

New technologies and production fuels are being used to reduce of Portland cement energy requirements, especially:

- using recycled scrap material to heat kiln (old tires),- replacing clinker/cement requirements with substitutes like fly ash

and blast furnace slag.

Discussion of Energy Consumption results

As it can be seen in table, steel and concrete have similar energy requirement during the stage of construction, transport and material production:

13

Page 14: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

While looking at the various life cycle stages, it is important to conduct a comparison of operational energy during building exploitation to embodied energy in construction, pre-use phase. The operational energy can be more than 90%. Because embodied energy is equal, the selection of material, i.e. steel or concrete is less significant. Operational energy is evidently a more decision making criteria in sustainable building design. However, the impact of steel or concrete frame in term of total raw energy and material depletion in the pre-use phase cannot be ignored by manufacturers.

Air Emissions

The raw results indicate that concrete has a 25% greater impact on CO2 emissions than steel both are of the same order of magnitude.

Carbon dioxide is released in almost all processes from chemical reactions or through burning of fossil fuels for kiln heating or to provide electricity to power production facilities.

Steel frame building

The CO2 emissions breakdown for steel frame construction is depicted in the figure:

14

Page 15: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

The primary contributors to CO2 emissions are steel beam production at 52% and concrete production for floor slabs at 32%. These two main product systems account for nearly 85% of total dioxide carbon emissions. This can be expected result, because the steel and concrete represent a vast majority of the materials used in steel building constructions.

Even after extracting the transportation requirement, the steel and concrete production, while less, are still major contributors to CO2

emissions. Transportation and construction stage CO2 emissions remain relatively constant, at 10,7% and 6,9% respectively, see the figure:

When electricity production is removed from six main product systems, their impact on CO2 emission is minor:

The one exception is production of concrete for the floor slabs, accounting for 27% of the total CO2 emissions.

15

Page 16: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Concrete frame building

The breakdown of CO2 emissions by product systems are shown in the figure:

The primary emitter of CO2 is the production of concrete at roughly 78%.Even with transportation and electricity requirements isolated, the concrete product system still accounts for nearly 68% of the total CO2

emissions, see the following figures:

Analyzing the individual production processes, it can be seen that the production of Portland cement accounts for 93% of the total CO2

emissions in the concrete production unit process, see the figure:

16

Page 17: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Analyzing further, actual production of Portland cement accounts for 94% of the cement production sub-unit process, with only 6% of CO2

emissions accounted for transportation and electricity to operate the cement production facilities, see the next figure:

For reducing CO2 emissions, decreasing the amount of Portland cement in the mixture ration of concrete is the obvious solution. For every 10% reduction in the amount of Portland cement in concrete by using of admixtures like mill scale or fly ash, there is a corresponding 7,5% decrease in CO2 emissions.

Resource Depletion

The nine of natural resources listed in the table are primary materials used in individual unit processes for both steel and concrete frame building constructions. The list includes renewable and non- renewable types, while other auxiliary materials could be required for process flows.

Concrete, when used as a building material, has four times impact on natural resources depletion compared to steel as shown in the figure:

17

Page 18: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

Steel specific results

In steel frame construction, total resources consumed is equal to 276 thousands tons. The primary natural resources are virgin iron ore required for pig iron production, and gypsum for fireproofing manufacture. The only resource that steel consumes more of compared to concrete is iron ore. However, the actual EAF process uses progressively higher recycled content in form of iron scrap.

Concrete specific results

The total quantity of resources consumed is 885 toms. In eight out of nine resource areas, the amount of concrete exceeds steel.

18

Page 19: seminarski rad01_Environmental Impact of Building Materials_Jan Bujnak

The conclusion is that a concrete construction uses four times the amount of total raw materials than steel. Moreover, the use of scrap iron also accounts for some difference, because recycled steel is not counted as one of the raw resources.

The important result to note is that both materials, in the construction of a single building require over 10 thousands tons of gross raw materials (without water) and consume more than 100 thousands tons of water. These impacts cannot be ignored.

Concluding remarks

While the question posed is “which material is better”, steel is clear winner in CO2 emissions and resource depletion, with 25% less total dioxide carbon emission and 68% less total natural resources used. The energy consumption is equal and therefore does not effect the determination.

But what if total energy requirement of steel exceeded concrete, for instance due to requirements to receive steel from more energy intensive foreign mills.

Where does it say that impacts of energy consumption are less important than CO2 emissions and resource consumption?

Further, what is an acceptable threshold of CO2 emissions?Thus, decision makers have to avoid identifying winners and take

into account that both materials have a significant impact on the global environment.

19