GOVERNMENT OF KERALA, DEPARTMENT OF SCIENCE & TECHNOLOGY Kerala State Council for Science, Technology & Environment (Sasthra Bhavan, Pattom, Thiruvananthapuram – 695004) NOTICE INVITING REQUEST FOR PROPOSALS Selection of Architectural Firms for Architectural Consultancy with Specified Project Management Activities and Preparation of Detailed Project Report for Srinivasa Ramanujan Institute of Basic Sciences at Pampady, Kottayam District Last date of receipt of Request for Proposals : 3.00 pm on 10-10-2014 Issued to :
37
Embed
Selection of Architectural Firms for Architectural ... · and Preparation of Detailed Project reports for Srinivasa Ramanujan Institute for Basic Sciences. Having been prequalified
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
GOVERNMENT OF KERALA, DEPARTMENT OF SCIENCE & TECHNOLOGY
Kerala State Council for Science, Technology & Environment
Selection of Architectural Firms for Architectural Consultancy with
Specified Project Management Activities and Preparation of
Detailed Project Report for Srinivasa Ramanujan Institute of Basic Sciences
at Pampady, Kottayam District
Last date of receipt of Request for Proposals : 3.00 pm on 10-10-2014
Issued to :
2
TABLE OF CONTENTS
Chapter Description Page No.
Notice Inviting Request for Proposal 3
I Information and Instruction to Architects/Consultants 4 – 10
II Conditions of Assignment 11
III Scope of Services 12-23
Schedule - I
List of Services to be rendered under Design Consultancy and Project Management
24-27
IV Data Sheet 28-30
V Application for RFP
Schedule B – Financial Statement
Schedule C – Additional Information
Schedule D – Detailed description of the design concept
Schedule E – Contour plan of Site
31
32
33
34
35
VI Financial proposal (To be submitted in separate cover)
Financial proposal form Schedule for fee for consultancy services
36
37
3
Government of Kerala, Department of Science & Technology
Kerala State Council for Science, Technology and Environment, Sasthra Bhavan
Srinivasa Ramanujan Institute of Basic Sciences, Pampady (SRIBS)
REQUEST FOR PROPOSAL
No. 05/SRIBS-DPR/2014/KSCSTE Date : 9-9-2014
Sub : Selection of Architectural Firms for Architectural Consultancy with specified Project Management Activities and Preparation of Detailed Project reports for Srinivasa Ramanujan Institute for Basic Sciences.
Having been prequalified by the Building Committee of the, SRIBS based on your Expression of Interest submitted, the following four Architectural firms are hereby invited for submitting the Request for Proposals for the subject work.
Flat No.4-B, 81, Valluvarkottam High Road Nungambakkam, Chennai – 600 034
RFP documents can be downloaded from websites www.sribs.kerala.gov.in and www.kscste.kerala.gov.in from 10-9-2014 on words. Last date for submission of RFP : 10-10-2014 upto 3.00 PM Opening of RFP : 10-10-2014 at 3.30 PM at Sastra Bhavan, Pattom P O Thiruvananthapuram, Kerala (Technical proposal only) The financial proposal will be opened on a predetermined date and time after due intimation to all bidders.
Cost of RFP documents (non refundable) shall be `. 1,560/- cost (`. 1500/-+VAT4%) to be paid in the form of
demand draft payable at State Bank of Travancore, Pampady, Kottayam drawn in favour of Finance Officer SRIBS to be submitted at the time of submission of R F P. Applications without this demand draft shall not be considered. For details/information, kindly visit our website. You are requested to submit the RFP in the prescribed format along with all documents/credentials within the stipulated date and time. M. Rajan Panicker Special Officer, SRIBS Sastra Bhavan, Pattom P O Thiruvananthapuram – 695 006 Kerala
Signature of the Bidder with name Office seal and Date
staff etc. at the first instance and other such facilities. The proposal is to entrust the complete design,
project management and supervision of construction of the building and services to a Architect/
Firm/Consortium selected for this purpose. The scope of this total consultancy assignment covers the
following areas.
1. The Architect/Firm/Consortium shall execute an agreement with SRIBS within Fourteen (14)
days from the date of intimation of appointment.
2. Immediately after signing the agreement, the Architect/Firm/Consortium shall get in touch with
SRIBS, for obtaining the site plan and details of requirements of accommodation and facilities to
be provided in the project and shall prepare preliminary conceptual drawing or models etc., for
the said project giving due consideration to all statutory rules and regulations for such buildings.
3. The preliminary conceptual plans, elevations etc. prepared by the Architect/Firm/Consortium
shall be shown to the employer for their approval and the Architect/Firm/Consortium shall
modify the same if desired by SRIBS without any additional cost till the concept drawings are
accepted by SRIBS.
4. After obtaining the written approval of SRIBS three copies of the approved preliminary design
and drawings (also referred to as revised or design development) including plans, elevation,
perspective drawings etc. shall be furnished to SRIBS along with brief specifications and
preliminary project estimate on square meter basis supported with details of rates and quantities
to the satisfaction of SRIBS. It is also essential to give a note of Green standards
achieved/obtained in the design. The project estimate should contain provision for all services
and allied items that are required for the completion of the whole project.
5. After the written approval of the sketch designs and preliminary estimate has been
communicated to the Architect/Firm/Consortium by SRIBS, the architect shall prepare detailed
working drawings including necessary 1:100, 1:50, 1:20 and 1:10 and full size Architectural and
structural details and schedules of specifications. The Architects/Firm/Consultants shall also
furnish detailed estimate on the basis of the latest specifications (wherever applicable) and
schedule of rates adopted by the State PWD in the region. All analysis of rates in the case of non
13
– schedule items and all details of quantities shall be furnished with the item rated detailed
estimate. The detailed estimate shall embody provisions in respect of all services, eg. water
supply, including hot and cold water systems, sanitary installations, Electric supply Drainage,
Sewerage, Air–conditioning, Fire fighting, etc.
6. The Architect/Firm/Consortium shall indicate on his drawings and report the manner in which
it is proposed to deal with all services, eg. Electrical, Water Supply, Sanitary, Drainage, Sewerage,
Air–conditioning, Fire- Fighting, Lightning Arrestor system, Telephone and other services.
7. The Architect/Firm/Consortium shall assist SRIBS in getting the Architectural plans, blue
prints, etc. of the buildings approved by, and obtain written approval from the Municipal
Corporation and other local bodies including concerned Development Authority (hereinafter
referred to as “the competent Authority”) and make necessary modifications as may be required
by the competent authority in consultation with SRIBS without any extra charge. Fees for
submission of plans if any, will be payable by SRIBS. Follow-up action to obtain the licenses
and permits will be the responsibility of the Architect/Firm/Consortium.
8. The Architect/Firm/Consortium shall prepare tender documents for pre–qualification of
contractors in the standard format and evaluate them on receipt from the Contractor’s, a list
recommending competent contractors shall be prepared and given to SRIBS for acceptance.
9. The Architect/Firm/Consortium shall after the SRIBS getting the plans approved by the
competent authority, and the pre-qualification process completed, prepare a Draft Tender
Document for approval of the employer and revise the same, if necessary. The SRIBS will invite
tenders from contractors who have been pre – qualified. Sufficient No. of tender documents and
drawings will be prepared by the Architect/Firm/Consortium – tenders will be received by
SRIBS and opened by them in the presence of the Architect/Firm/Consortium or his
representative and the contractors or their representatives. The Architect/Firm/Consortium
shall advise SRIBS within two weeks of handing over of tenders as regard the selection of
Contractor, but the final choice will rest with SRIBS. The Architect/Firm/Consortium will assist
in the execution of the Contract (agreement) by the contractor, if required on a form drafted by
the Architect/Firm but approved by SRIBS, who may at their discretion, adopt a new form
altogether. The issue of Tender forms shall be the responsibility of SRIBS and the Architects/
Firm/Consortium will prepare and hand over sufficient No. of bid documents for issue to the
pre-qualified contractors.
10. The Architect/Firm/Consortium shall prepare for the use of the SRIBS and the Contractor six
copies of the drawings of various trades and items or any other particulars. The Architects/
14
Firm/Consortium shall also provide further details and drawings as are necessary for the proper
execution of the works.
10.1 The Architect/Firm/Consortium shall make necessary revisions and changes that may be
required by the user up to this stage. Any subsequent revisions and changes of substantial nature
on these drawings once approved made as per the order of the user shall be compensated as
additional services rendered by the Architects/Firm/Consortium on mutually agreed terms.
11. The Architect/Firm/Consortium shall not make any deviation, alteration, additions or omission
from the approved drawings without the knowledge and prior written consent of the SRIBS.
SRIBS will retain the right to omit or postpone any work or part thereof at their discretion.
12. The Architect/Firm/Consortium will get the work executed as per approved plans,
specifications and as per terms and conditions of the agreement executed with the contractor by
rendering total and complete supervision of the work and his DUTIES AND
RESPONSIBILITIES on account of this shall be as specified here in.
12.1 The Architect/Firm/Consortium shall provide sufficient site supervisory staff, give periodical
supervision and inspection and such other services as may be necessary to ensure that the works
are being carried out in accordance with the contract and be responsible for such services.
Advise SRIBS on the progress and quality of the work and furnish daily site reports.
Advise SRIBS on such measures as may be deemed necessary in respect of progress and quality
of work.
Advise SRIBS on expenditure, cost control and give advance intimation if the total authorized
expenditure is likely to be exceeded. Provide report of extra items in the work with rate analysis
as per terms of contract for approval by SRIBS.
Advise SRIBS if the contract time is likely to be varied.
Issue variation orders as deemed necessary by him on behalf of SRIBS within the scope of
the contract.
Measure, verify and approve contractor’s measurements of work, conduct checking and issue
certificates authorizing payment including final payment along with certificate that the work has
been carried out in accordance with the specifications.
Shall deposit all measurement books and level field books duly certified for accuracy and
correctness with the SRIBS after obtaining the acceptance of the contractor at the time of the
final bill for record.
15
Furnish such information to the SRIBS and advise them regarding fulfillment of contractor’s
obligations in respect of the contract such as reports, progress charts etc.
Furnish such other technical data as required and used on various materials involved in the
construction of works etc.
Arrange to conduct the required tests for the construction materials and instruct the contractor
for the removal of materials which does not satisfy specified quality.
12.2 He shall be conferred the following ‘POWERS’ by the SRIBS.
In order to enable the Architect/Firm/Consortium to carry out his functions, the SRIBS shall
authorize him in writing with such powers of SRIBS as deemed necessary from time to time and
afford him such facilities for discharge of duties.
Necessary letters of authority, notice to other concerned parties etc., shall be issued by the
SRIBS wherever necessary under advise from the Architect/Firm/Consortium.
12.3 Normally the Architect/Firm/Consortium shall not make any deviation, alterations or additions
to the scope of the contract but shall accommodate, any such items ordered in writing by the
SRIBS. However, this shall be subject to any adjustments in the terms and conditions entered in
between the SRIBS and Architect/Firm/Consortium by this contract. He shall prepare
and forward the final deviation statement before the passing of the final bill to the SRIBS
for approval.
12.4. LIABILITIES
The Architect/Firm/Consortium shall perform his duties and assume such responsibilities
unreservedly in the best of spirits and faith in the interest and for the sole benefit of the
employer. If in the course of his functions, he involves himself in risks, liabilities, litigations,
disputes, acts of violence, revolts, damages suffered in the performance of his duties – natural or
otherwise, the Employer shall absolve himself fully.
12.5. LIMITATIONS
The Architect’s/Firm responsibility shall be expressly for effecting complete quality control for
the work leaving no part of the work done with out proper supervision. He/It shall render
advisory services on technical, non-technical related matters affecting progress, expenditure and
in respect of the contract and as detailed above, while every effort shall be made by him/it in
due time to set right any deficiency coming to his notice, and should the importance of such
event so warrants, then to inform the SRIBS of the deficiency being serious to engage a more
16
direct attention by the SRIBS, it shall be clearly understood that the Architect shall not be
responsible for the deficiency itself, caused by another agency.
12.6. The Architect/Firm/Consortium shall be issuing such directions and instructions on behalf of
the SRIBS to the contractor. For any delay, lapse or negligence on the part of the contractor, the
Architect shall not be responsible, and he shall under the express consent of the SRIBS, make
attempts to prevail upon the contractor to make good such delay, lapse or negligence. All such
actions shall be subject to the risk and responsibility of the SRIBS.
12.7. The Architect/Firm/Consortium shall employ necessary supervisory staff and perform his
consultancy and advisory services incurring the required expenditure towards their salary,
traveling for routine attendance to normal place of work, stationery for correspondence etc.
should additional expenditure be involved for any special journey to be undertaken outside the
normal place of work or towards a special service connected with the conduct of the work, such
as for stationery, printing, transmittal or records, materials, etc., tests to be carried out for
determination of quality of materials, works, workmanship etc., such expenditure shall be
reimbursed by the SRIBS.
12.8. Nominee of employer to transact with Architect/Firm/Consortium.
The Special Officer will fulfill the employer’s obligations in respect of the work and will deal
with the Consultant. The Architect/Firm/Consortium shall be addressing this officer for all
matters dealing with the work. Any decision or opinion expressed by such officer shall be
deemed to be the opinion of the SRIBS.
13. In the event of the failure of the Architect/Firm/Consortium to completely do his/its work
within a reasonable time and in a satisfactory manner or in the event of the Architect
committing a breach of any one or more of the terms and conditions of the Agreement, the
SRIBS shall be entitled to rescind this Agreement without prejudice to their rights to claim
damages or other rights or remedies under the law. Further if the work is delayed due to the
failure of the Architect/Firm/Consortium on account of non-issuance of instructions,
drawings and approvals in time, SRIBS will be at liberty to fix a penalty and recover the
same from the fees.
14. The Architect / Firm / Consortium shall prepare working drawings and details sufficient for the
proper execution of the works on the following also.
(a) Typical bathroom layouts with all waste and water services indicated, including sections,
elevations as necessary.
(b) Diagrammatic and isometric layout of cold and hot water services throughout the building.
17
(c) Detailed plan and section showing the connection between pumps and storage tanks.
(d) Detailed plan and section showing sewerage connections.
(e) Detailed requirements of auxiliary services such as fire prevention installations.
15. The Architect/Firm/Consortium shall prepare all necessary load calculations and design the
complete electrical installations, Air-conditioning installations, Telephone wiring, public address
system etc. He shall prepare all documents and drawing for presentation for approval of
Electrical Inspectorate and Kerala State Electricity Board.
16. The Architect/Firm/Consortium shall also supply to the SRIBS free of cost two copies of 1:100
or appropriate scale drawings (one of which shall be a reproducible print), two complete sets of
structural drawings and two sets of drawings sufficient to show the main lines of drainage,
electrical installation and other essential services. The Architect/Firm/Consortium shall, if so
required by the SRIBS supply extra copies of all such drawings free of cost whenever such
copies are required for obtaining license/permits etc. from the local authorities. He shall also
make changes required by the Electrical Inspectorate, Kerala State Electricity Board and assist
the SRIBS in getting the sanctions.
17. Further details of service to be rendered are given in schedule I and this schedule forms part and
parcel of the Agreement.
18. The Architect/Firm/Consortium shall also render any other services connected with the said
works usually and normally rendered by Architects/Firm/Consortium and not referred to in any
of the above sub clauses, but shall be paid for the services rendered as such at mutually
agreed rates.
II. CONDITIONS OF ENGAGEMENT
(1) The Architect/Firm/Consortium shall submit to the SRIBS all the necessary sketch plans,
tender documents for pre-qualification and for actual tender as and when required by the
SRIBS and as per time schedule agreed. If the Architect/Firm/Consortium fail to adhere to
the time schedule or the extended time which may be granted by the SRIBS in his sole
discretion, the SRIBS shall be entitled to terminate this agreement and entrust the work to
some other Architect/Firm/Consortium and in the case, the Architect/Firm/Consortium
shall be entitled to fees or compensation only upto the stage of work carried out by him. In
the event of the Architect/Firm/Consortium being not in a position to fulfill his works on
design and drawing in such a way that the construction work cannot be carried out as per
time schedule, the SRIBS will be free to get the design and drawings prepared by other
agencies at the risk and cost of the Architect/Firm/Consortium.
18
(2) The Architect/Firm/Consortium shall exercise all reasonable skill, care and diligence in the
discharge of duties hereby covenanted to be performed by him/it and shall exercise
inspection in regard to the said works, as may be necessary to ensure that the work is being
executed in accordance with the working drawings and specifications aforesaid and approved
by the SRIBS. The Architect/Firm/Consortium shall also conduct full supervision of the
work to ensure complete quality control, structural safety, proper finish and accuracy of
measurement and bills.
III. TIME REQUIRED FOR THE WORK
The Architect/Firm/Consortium shall undertake to complete this work as per a time schedule,
which will be worked out on mutual consultation within 15 days from the date of execution of
the consultancy agreement. However, the total time of 18 months will remain unaltered.
IV. TERMINATION OF ASSIGNMENT
(1) The Assignment given may be terminated at any time on 3 months notice on either side. In
the event of the termination by the SRIBS, the Architect/Firm/Consortium shall not be
entitled to any compensation or damage by reason of such termination, but only to the fees
for the services actually rendered upto the time of such termination.
(2) If Architect/Firm/Consortium shall close his business or die or become incapacitated for
acting as such Architect/Firm/Consortium as aforesaid, or if this Assignment is terminated
the SRIBS may make use of all or any drawings, estimates or other documents prepared by
the Architect/Firm/Consortium after payment for the same, as provided herein.
V. TRANSFER OF INTERESTS
The Architect/Firm/Consortium shall not assign, sub-let or transfer their interest without the
written consent of SRIBS.
VI. SCALE OF CHARGES
1. In consideration of the services to be rendered by the Architect/Firm/Consortium the
SRIBS shall pay a fee as agreed upon. This fee shall not be payable on the cost of the items
listed below.
A. LAND
B. Any other service, fittings or fixtures which are not provided, planned or executed by the
Architect/Firm/Consortium without SRIBS’s written approval.
C. Any in fructuous work of demolition etc. ordered by the Architect/Firm/Consortium
without the SRIBS’s written approval.
D. Payments to local authorities for approval of plans sanction of electrical load, soil-testing
fees, etc.
E. Installation of Telephones, exchanges (PABX) etc, except wiring.
19
F. Electrical fittings, tube lights and fans if supplied by the organization.
G. Cost of special finishes and special furniture designed and executed by SRIBS.
2. The fees are payable to the Architect/Firm by the SRIBS at the following rates.
I. Architectural and Services Consultancy
A. Civil construction
a) Stage I On completion of initial site evaluation project study with references to users requirement; Preparation of detailed site survey, preparation of sketch designs, layout, conceptual drawings and models. After discussion with SRIBS and user Scientists, revise design and make modified drawings and sketches and summit to SRIBS.
Up to 10%
b) Stage II Prepare drawings and plinth area estimates for getting approval from all statutory government department and local body’s and for financial sanction for the project. Completion of soil investigation (cost being met by SRIBS) and getting statutory license and permit for the project.
Up to 25%
c) Stage III On completion of preparation of detailed architectural drawings with plans, elevations, sufficient number of sections layouts etc, details of joinery, plumbing and sanitary layout and detailed electrical drawings and layouts etc, structural designs with calculations and structural drawings, detailed fabrication drawings, landscape designs including road formations, arboriculture, detailed specifications for plant & machinery, interior design work, etc. prepare detailed estimate based on current CPWD schedule of rates for approval by SRIBS Prepare tender papers and assist in tender process and give recommendation of award in the contract.
Up to 55%
d) Stage IV On award of contract, execution of agreement, completion of setting out and commencement of foundation work.
Up to 80%
e) Stage V On completion of issue of all Architectural and structural drawing, additional drawing for execution and construction reaches two floor heights.
Up to 90%
f) Stage VI On completion of entire structure of the building and furnishing all drawing and specification for finishing work.
Up to 95%
g) Stage VII On completion of building and issue of virtual completion certificate and handing over the project.
Up to 98%
h) Stage VIII After defect liability period of two years.
Up to 100%
Note : The payment to the Architect/Firm/Consortium during various stage will be fixed on
cost worked out on the following basis.
20
1) Stage
(a) Based on plinth area cost on concept design
(b) Based on revised plinth area cost as per drawing prepared for obtaining license.
(c) To (f) Contract value fixed as per tender.
(g) and (h) actual executed cost of the project.
B. Services
Electrical (H.T & L.T.), A.C., Firefighting, Plumbing, Telephone and similar works.
a) Stage I Preparation of concept and rough cost estimate and discuses with SRIBS Get feedback and modify.
Up to 20%
b)
Stage II Prepare detailed estimate tender documents and drawings. Assist in tender process and give recommendation for award of work .
Up to 55%
c) Stage III Supervision of work till the work is complete up to half stage.
Up to 75%
d) Stage IV On completion of all works upto completion of civil structure.
Up to 85%
e) Stage V On completion of all systems, testing and handing over.
Up to 95%
f) Stage VI Settlement of final bill and issue of virtual completion statement.
Up to 98%
g) Stage VII On completion of defect liability period of two years.
Up to 100%
Stages
(a) Based on rough cost estimate.
(b) Based on detailed estimate.
(c) to (e) Based on contract value.
(f) & (g) Based on completion cost.
II. Supervision and Project Management
1.0 The CONSULTANTS shall under take the supervision and management of the work
for which qualified and experienced team of engineers are to be posted.
1.1 Prepare program schedule for the work
1.2 Setting out of the lay out plan on the site
1.3 Full time supervision and inspection of all works executed
1.4 Prepare weekly progress reports and its submission to client
1.5 Inform short falls in the program
1.6 Inform the client if the contract time is likely to vary
21
1.7 Inform the client if the total expenditure is likely to vary.
1.8 Maintenance of “Measurement Books”
The ARCHITECT shall record the pre-measurement in “Measurement Books”
and conduct due check measurement from time to time. The measurements will be
recorded by the site supervisors and check measured by the Project Engineer of the
Architects/Firm/Consortium
1.9 Check CONTRACTOR’s Bills for interim payments and make recommendations to
the SRIBS.
1.10 Check CONTRACTOR’s final bills and settlement of the same.
2.0 Time Management
The Consultant is responsible for the Systematic management of available time for the
satisfactory completion of the project.
2.1 Prepare Master construction programme and submit for the SRIBS’s acceptance
2.2 Obtain Contractor’s preliminary construction programme and check against the Master
programme and incorporate necessary modifications if any jointly.
2.3 Establish and implement effective monitoring and control systems.
2.4 Arrange for daily/weekly progress review meetings and analyse the program and progress
in line with the master programme.
2.5 Submission of reports.
3.0 Cost Management
3.1 Advise on management of cash flow.
3.2 Receive, scrutinize, certify and make recommendations to the SRIBS on the
CONTRACTOR’s bills including statutory tax deduction observing all codal formalities.
3.3 Assess and issue authorized change orders.
3.4 Reconcile all the materials supplied by client, if any.
3.5 Submit weekly cost reports including variation in cost, reasons for variation and the
projected total cost.
3.6 Verify final bills and advise on issuance of completion certificates.
4.0 Quality Management
The consultant shall take all possible effective steps to maintain excellent quality for all works
subject to the approved specifications.
4.1 Ensure all works are carried out based on the approved and agreed specifications and if
any deviation found it should be brought to the notice of the SRIBS.
22
4.2 Enforce quality control procedures by way of checklist for concrete, steel and all other
materials used for construction.
4.3 Initiate regular checks during progress of works on materials and workmanship
4.4 All materials used at site shall have the approval of the FIRM/ARCHITECT/
CONSORTIUM through the Project Engineer.
4.5 The ARCHITECT/FIRM/CONSORTIUM shall check that all the products used at site
shall be of approved quality. To ensure the quality of products received, the
CONSULTANT shall furnish details, which are in conformity with the specifications. In
other words the products should not be specified or recommended by brand name.
4.6 The ARCHITECT/FIRM/CONSORTIUM shall ensure and certify the structural stability
of all the works designed and executed and communicate to the SRIBS before the final
settlement of the bills.
Scale of Fees
C. Supervision and Project management Scale of fees
a) Stage I On completion of preliminary works and starting of foundation.
Up to 15%
b) Stage II On structure reaching first floor level
Up to 45%
c) Stage III On the completion of work of structure up to 50%
Up to 60%
d) Stage IV On completion of entire structure
Up to 75%
e) Stage V On completion of 50% of finishing works
Up to 80%
f) Stage VI Completion of finishing work.
Up to 90%
g) Stage VII All virtual completion
Up to 95%
h) Stage VIII On settlement of final bill
Up to 98%
i) Stage IX After defect liability period of two years
Up to 100%
Payment for stage (a) will be based on contract value. For all other stages payment will be based
on actual executed cost at each stage.
In case only a part of the project is continued beyond any stage the deduction for payments
made against earlier stages shall only be in respect of proportionate cost of the said part of
the project.
23
ABSTRACT OF FEES
Sl. No.
Descriptions Rate (Percentage)
Figures Words
1. A. Civil Construction (Architectural Consultancy Services) (All items of works described under Chapter – III Scope of Services of bid document) The fees should be expressed as a percentage on project cost of relevant portion as included in the accepted schedule above)
2. B. Services (Engineering Services Consultancy) (All items of works described under Chapter – III Scope of Services of bid document) The fees should be expressed as a percentage on project cost of relevant portion as indicated in the accepted schedule above)
3. C. Supervision and Project Management (All items of works described under Chapter – III Scope of services of bid document) The fees should be expressed as a percentage on project cost of relevant portion as indicated in the accepted schedule above)
VII. TAXES
The applicable taxes like Service tax and Education cess at the prevailing rates as on date of billing will
be paid extra. All other taxes are considered as included in the above rates.
The tax will be calculated after effecting the discount if any.
Income tax will be deducted at prevailing rates and remitted to Central Government.
VIII. PERIOD OF CONTRACT
The consultancy and supervision contract awarded is for a period of 18 months from the date of signing
the agreement. Out of this, 2 months will be for the design, estimate and tender, 14 months for
construction and 2 months for settlement of all final bills. If supervision of work is extended beyond
this for no fault of Architect/Firm/Consortium then a monthly charge equal to the amount actually paid
to the supervisory staff limited to the maximum of `. 15,000/- (Rupees Fifteen thousand only) per
month will be paid additionally for a further period agreed upon mutually. However, the Architect/
Firm/Consortium will conduct periodical inspections at suitable intervals during the defect liability
period of 24 months without any extra payment.
IX. JURISDICTION OF COURTS
In all regular issues the decisions of SRIBS is binding on the Architect/Firm/Consortium. How ever, if
any reference to a court of law is required to settle a dispute, then courts having jurisdiction over
Thiruvananthapuram alone shall be approached.
Special Officer
SRIBS
24
SCHEDULE - I
LIST OF SERVICES TO BE RENDERED UNDER DESIGN CONSULTANTCY
AND PROJECT MANAGEMENT
I. ARCHITECTURAL WORK
1. Visit site and take SRIBS’s instructions, prepare sketch designs to comply with
their requirements and in consultation with them, indicate the Architect’s/Firm/
Consortium interpretation.
2. On approval of the sketch design by the SRIBS prepare rough estimate of cost of plinth
area basis.
3. Prepare necessary drawings of the sketch designs approved by the SRIBS and forms for
submission to the local authorities to obtain approvals.
4. Prepare Architectural working drawings and details sufficient for the proper execution of the
work and supply to the contractor’s sufficient copies of working drawings, schedules,
specifications and other contract documents to enable them properly to fulfill their
obligations under conditions of contract.
5. Prepare a compete project report for establishing the institute at Pampady with all furniture,
vehicle, library racks and books etc. in consultation with the Special Officer, SRIBS.
6. Call for pre-qualification tenders in consultation with the SRIBS and assist in preparing a list
of pre-qualified contractors.
7. a) Prepare detailed cost estimate of the general building work on the basis of the schedule
of quantities and specifications and rate adopting current PWD schedule of rates and on
approval supply enough copies of tender documents for sale.
b) Prepare detailed cost estimate of the general building work on the basis of the schedule
of quantities and specifications.
c) Assist the SRIBS to invite tenders, advise the SRIBS on the selection of contractor and
prepare draft contract documents.
8. Supervise the work to ensure quality, accuracy and finish assuming full responsibility for
the same.
9. Measure, check – measure and record in standard measurement Books and field books all
the work done by the contractor, prepare interim and final certificate of payments to the
contractor, issue virtual completion certificate, certify on quality and safety consideration and
hand over the project to the SRIBS.
10. Inspect periodically the building and other services for the defect liability period of
24 months and issue final recommendation for release of security of the contractor.
25
II. STRUCTURAL ENGINEERING WORKS
1. Prepare preliminary structural drawings on the basis of preliminary sketch designs
approved by the SRIBS.
2. Determine economics and modules, prepare detailed analysis and design of structure
and prepare RCC Drawings and specifications and other details relating to planning of
the structure.
3. Supply to the contractors sufficient number of copies of working drawings, schedules,
specifications and other contract documents to enable them properly to fulfill their
obligations under conditions of contract.
4. Prepare schedule of quantities and general specifications for structural work.
5. Prepare detailed cost estimate of the structural work on the basis of the schedule of
quantities, specifications and structural design.
III. DRAINAGE, PLUMBING AND FIRE FIGHTING WORK
6. Take SRIBS’s instructions and prepare preliminary report and rough indication of
estimated cost.
7. On approval of the preliminary estimate, prepare preliminary drawings indicating drainage,
water supply and plumbing work.
8. Prepare working drawings and details sufficient for the proper execution of the works
as follows.
Typical bathroom layouts with all waste and water services indicated, including sections,
elevations etc, as necessary.
9. Prepare schedule of quantities, general specifications based on the approved designs and
prepare tender documents.
10. Call for pre-qualification tenders in consultation with the SRIBS and assist in preparing a
list of pre-qualified contractors.
11. a) Prepare detailed cost estimate of the Drainage and Plumbing work on the basis of the
schedule of quantities and specifications and on approval supply enough copies of
tender documents for sale.
b) Prepare detailed cost estimate of the work on the basis of the schedule of quantities
and specifications.
26
c) Assist the SRIBS to invite tenders, advise the SRIBS on the selection of contractor and
prepare draft contract documents.
d) Submit drawing and get clearance from fire safety department.
12. Supervise the work to ensure quality, accuracy and finish assuming full responsibility for
the same.
13. Measure, check measure and record in standard measurement Books and field books all
the work done by the contractor, prepare interim and final certificate of payments to the
contractor, issue virtual completion certificate, certify on quality and safety consideration
and hand over the project to the SRIBS.
14. Inspect periodically the building and other services for the defect liability period of
24 months and issue final recommendation for release of security of the contractor.
IV. AIR-CONDITIONING
15. Take SRIBS’s instructions and prepare preliminary report and rough indication of
estimated cost.
16. On the basis of the preliminary report and estimated cost approved by the SRIBS, prepare
the preliminary design drawings on the project for approval of the organization.
17. Prepare design drawings for inviting tenders.
18. a) Prepare detailed cost estimate of the A C work on the basis of the schedule of
quantities and specifications and on approval supply enough copies of tender
documents for sale.
b) Prepare detailed cost estimate of the work on the basis of the schedule of quantities
and specifications.
c) Assist the SRIBS to invite tenders, advise the SRIBS on the selection of contractor and
prepare draft contract documents.
19. Supervise the work to ensure quality accuracy and finish assuming full responsibility for
the same.
20. Measure, check – measure and record in standard measurement books all the work done
by the contractor, prepare interim and final certificate of payments to the contractor, issue
virtual completion certificate, certify on quality and safety consideration and hand over the
project to the SRIBS.
21. Inspect periodically the building and other services for the defect liability period of
24 months and issue final recommendation for release of security of the contractor.
27
V. ELECTRICAL WORK
These services will include electrical, telephone wiring, public address system, thermal
installations etc.
1. Prepare all the preliminary load calculations and design the complete electrical installations.
2. Prepare necessary drawings and other details of the system and get it approved by the
SRIBS for submission to the local authorities and obtain their approval.
3. Prepare schedule of quantities, specifications and draft tender documents.
4. a) Prepare detailed cost estimate of the electrical works on the basis of the schedule of
quantities and specifications and on approval supply enough copies of tender
documents for sale.
b) Prepare detailed cost estimate of the work on the basis of the schedule of quantities
and specifications.
c) Assist the SRIBS to invite tenders, advise the SRIBS on the selection of contractor
and prepare draft contract documents.
5. Supervise the work to ensure quality, accuracy and finish assuming full responsibility for
the same.
6. Measure, check measure and record in standard measurement books all the work done by
the contractor, prepare interiors and final certificate of payments to the contractor, issue
virtual completion certificate, certify on quality and safety consideration and hand over the
project to the SRIBS.
7. Inspect periodically the building and other services for the defect liability period of
24 months and issue final recommendation for release of security of the contractor.
VI. MISCELLANEOUS WORKS
1. Advise the SRIBS if the total of authorized expenditure is likely to be exceeded..
2. Advise the SRIBS if the contract time is likely to be exceeded.
3. Obtain the SRIBS’s approval for any material deviation in design or cost or working
drawings, schedule and specifications, certify accounts.
28
CHAPTER – IV
DATA SHEET
Information to Consultants
1.1 The Name of the Client is : Special Officer, SRIBS
1.2 The method of selection is : Technical and Financial Proposals and QCBS Principle
1.3 Pre-qualification and financial
proposals are requested : Yes
1.4 The name, objective and : Total Consultancy for Design, Project Management
description and Construction, Supervision of Buildings for
Srinivasa Ramanujan Institute of Basic Sciences
(SRIBS) at Pampady, Kottayam District
1.5 Terms of Payment : Given under scope of work
1.6 The number of days before
the submission to request a
clarification in proposal : 5 days before the last date of Submission of date
The address for last date of : The Special Officer
A set of key experts / professional staff with minimum professional experience required are listed
below. Please examine the T.O.R and add more experts as required for the proper completion of
the assignment.
Sl. No
Position Qualification and
Professional Experience Specific experience
1. Chief Architect Degree in Architecture
Should be a member of
Council of Architecture
(India). Should be
registered with the
Council of Architecture.
15 years experience
Should be head of the Architectural
firm, having worked as a total
consultant for at least 5 major works.
Should be capable of coordinating all
the agencies involved in the work.
Should be able to design and execute
multi-storied buildings to meet high
standards. Should be capable of
designing Green buildings.
2. Project Manager/
Project Engineer
Degree in Civil
Engineering
5 years experience
Proficient in managing major works
costing more than `. 3.00 crores.
Experience in coordinating different
agencies.
3. Structural
Consultant
Post graduate degree in
structural Engineering
7 years experience
Should have designed multi-storied
buildings including foundation, water
retaining structures and storage
structures.
4. Electrical / Air-
conditioning /
Fire Consultant
Degree in Electrical /
Mechanical Engineering
5 years experience
Should have designed and executed
similar projects costing more than
`. 50.00 lakhs (Electrical / Air-
conditioning part) should be able to
design services with lesser, power and
water consumption adopting Green
building techniques.
5. Quantity
Surveyor
Degree / Diploma in Civil
Engineering
5 years experience
Should have experience in quantifying
multi storied buildings, taking
measurements, preparation of
bills etc.
C Vs may be given in standard format given in clause. 3.3 of
30
Chapter. I. Information and Instructions to Architects/Consultants.
The information on: : Proposal for the total consultancy service for design, project the outer envelope is management & construction, supervision of Building for
Srinivasa Ramanujan Institute for Basic Science (SRIBS) at Pampady, Kottayam district.
The proposal submission address is : The Special Officer, SRIBS, Sastra Bhavan, Pattom P O Thiruvananthapuram - 695004
Tel. : 0471 - 2548401 Fax : 0471 - 2540085
1.10 Proposals must be submitted not later than the following date and time : 10-10.-2014, 3.00 P.M.
1.11 Evaluation criteria
Marks obtained in prequalification evaluation - 40% - 40 points Experience and competency of the key personnel - 10% - 10 points Concept and Architectural design presented - 50% - 50 points Total 100 points 75% marks is the cutoff level for technical proposal. The financial bid of only those agencies who score more than 75% will be opened and evaluated. Experience and competency of the key personnel (10 points) i. Chief Architect - 4 points ii. Project Manager/Project Engineer - 2 points iii. Structural Engineer / Design Consultant - 2 points iv. Quantity Surveyor - 2 points
Sub criteria for Evaluation of Experience and competency of the key personnel
Points given to evaluation of sub-criteria for qualification of staff are : (a) Educational Qualifications : 35 points (b) Experience in similar tasks : 30 points (c) Competency of the key professional staff for the assignment : 35 points
Total : 100 points 1.12 The date, time and address of the proposal opening are :
Technical Bid - 3.30 PM on 10-10-2014
Financial Bid - will be informed separately
1.13 The final selection will be done by the SRIBS after presentation on concept & methodology.
1.14 The consultancy cost shall be determined by taking the project cost of `. 25.00 crores with
`. 20.00 crores for Civil works and `. 5.00 crores for services. The percentage fees quoted shall
be applied on the cost of `. 25.00 crores as stated above and financial proposal valued. Of this
the lowest cost will be given a score of 100 and all other Financial bids will be given scores
inversely proportional to the amounts quoted, as detailed else where in the document.
1.15 The address for negotiations is : The Special Officer, SRIBS, Sasthra Bhavan, Pattom P O
Thiruvananthapuram - 04
1.16 The Assignment is expected to commence by October 2014.
31
Special Officer
SRIBS
CHAPTER - V
APPLICATION
Architectural Consultancy Services with Specified Project Management Activities
and Preparation of Detailed Project Report for Srinivasa Ramanujan Institute of
Basic Science at Pampady, Kottayam District
To Date : ….-…..-…….
The Special Officer
SRIBS
Sastra Bhavan, Pattom P O
Thiruvananthapuram – 695004
Dear Sir, Having examined the bid document indicating scope of works and time framed of the work I / We
hereby submit all the necessary information and relevant documents for selecting me / us for the above-
mentioned work. The application is made by me / us on behalf of ………...………………………………….………..
……………………………………………………………………………..……………………………
(Group firms) in the capacity of ……………………………………………….. duly authorized to
submit the offer. The necessary evidence admissible in law in respect of authority to me/us on behalf of
the group of firms for applying and for completion of the contract document is attached herewith. I / We understand the SRIBS reserves the right to reject any application without assigning any reason. I / we undertake that all the information furnished by me/us in the Technical bids are true to the best
of my / our knowledge and belief. If any of the information are found to be false on subsequent
verification, I / We undertake that I / We may be excluded from the list of pre-qualified bidders and not
to consider my / our bids for the work.
SIGNATURE OF THE APPLICANT
(Name in brackets, including title and
32
capacity in which application is made)
Encl : 1. RFP document (Sealed Cover)
2. Evidence of authority to sign
SCHEDULE – B
FINANCIAL STATEMENT
1. Name of Architect / firm (Partner in case of joint venture / consortium)
2.
Capital
a. Authorized
b. Issued and paid up
3. Attach audited balance sheets and profit and loss statement for the past three years.
4. Annual value of works, undertaken for each of the last three years and projected for the
current year.
Year Current One year before Two years before Three years before
Home
Abroad
SIGNATURE WITH SEAL
5. Approximate value of works in hand ……………………………………….
6. Value of anticipated orders for next two Financial years.
……………………………………….
33
SCHEDULE – C
Additional Information
(The applicant can add here any further information relevant to the valuation of their Technical bid)
34
SCHEDULE - D
Detailed description of the design concept stipulated
(A set of concept plan, sections and elevations to be enclosed)
FACILITIES NEEDED FOR SRIBS OFFICE AT PAMPADY, KOTTAYAM
TOTAL LAND AREA AVAILABLE -ACRES
Sl.No. Sq.ft.
1. Administrative block including Security, Reception, Store, Visitors, Lounge
25,000 Sq.ft.
2. Library etc. 5,000 Sq.ft.
3. Auditorium 500 capacity 10,000 Sq.ft.
4. Seminar Rooms (6 Nos.) Each with 100 capacity 24,000 Sq.ft.
5. Cafeteria 8,000 Sq.ft.
6. Labs (6 Nos. - including Scientists cabins, lab stores)
The following facilities also have to be provided. 1. Solar Energy 2. Rain Water Harvesting 3. Security Cameras 4. Car Parking facilities for 50 cars 5. Two wheeler parking – 100 Nos. 6. Landscaping & Gardening 7. Electrical Room, Pump House etc. 8. Generator room 9. Water Storage Tanks 10. Inside Roads 11. Compound Wall & Gate 12. Sewage disposal plant 13. Water purification plant 14. Tube wells Since the land is limited buildings may be designed in multiple storeys of 3 floors. Kerala Architectural style and Green House Technology may be adopted.
35
36
(To be submitted in separate cover)
CHAPTER - VI
FINANCIAL PROPOSAL
FINANCIAL PROPOSAL SUBMISSION FORM
(Location, Date) From : (Name of Firm): To : (Name and Address of Client)
Ladies/ Gentleman :
Subject : Bid for Architectural Consultancy Services with Specified Project Management
Activities and Preparation of Detailed Project Report for Srinivasa Ramanujan
Institute of Basic Sciences at Pampady, Kottayam District.
Financial Proposal.
We, the undersigned offer to provide the consultancy services for the above in accordance with
your request for proposal dated …………………. and our proposal (Technical and Financial
proposals). Our financial proposal entered in the schedule is enclosed. This fee is inclusive of
income tax liability but is exclusive of other local taxes which we have estimated and given in
the schedule.
Our financial proposal shall be binding upon us subject to the modifications resulting from contract
negotiation, up to the validity period of the proposal, 180 days from the date of submission.
We undertake that, in competing for (and if the award is made to us, executing) the above contract, we
will strictly observe the laws against fraud and corruption in force in India namely “Prevention of
Corruption Act 1988”.
I / We understand you are not bound to accept any proposal you receive.
I / We remain,
Yours sincerely
Authorized signature :
Name and Title of Signatory :
Name of Firm :
Address :
37
SCHEDULE FOR FEE FOR CONSULTANCY SERVICES
Sl. No.
Description
Rate (% of appd. Estimated cost/ Completion cost)
Figures Words
1. ARCHITECTURAL CONSULTANCY SERVICE
(All items of work described under chapter – III Scope of
Work and specifically listed under item I & II Architectural
Work under schedule–I viz., “List of Services to be
rendered”)
The fees should be expressed as a percentage on project
cost for civil and allied works.
2. SERVICES (Engineering Services Consultancy)
(All items of work described under chapter – III Scope of
Work and specifically listed under item III, IV, & V viz.,
“List of Services to be rendered”)
The fees should be expressed as a percentage on project
cost for all services.
3. SUPERVISION AND MANAGEMENT
(All items of work covered under supervision and project
management as listed under Chapter III Scope of Work and
specifically listed under the respective item)
The fees should be expressed as a percentage on project
cost for all items of works.
TAXES
The applicable taxes on the above mentioned fees are given below.